LHC Commissioning in 2008

Similar documents
LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

LHC status & 2009/2010 operations. Mike Lamont

LHC Status and CERN s future plans. Lyn Evans

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Large Hadron Collider at CERN

LHC operation in 2015 and prospects for the future

LHC Collimation and Loss Locations

Interface with Experimental Detector in the High Luminosity Run

Early Physics with the CMS detector at LHC

Status of the LHC Beam Cleaning Study Group

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

Status of the LHC Machine

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

Beam losses versus BLM locations at the LHC

Beam Cleaning and Collimation Systems

LHC. Construction Understanding first the commissioning. Prospects for

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

LHC Beam Operations: Past, Present and Future

ASPECTS OF MACHINE INDUCED BACKGROUND IN THE LHC EXPERIMENTS

Plans for 2016 and Run 2

Practical Lattice Design

STATUS OF LHC COMMISSIONING

Beam Loss Monitors, Specification

Status and Outlook of the LHC

Overview of LHC Accelerator

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

BETATRON SQUEEZE: STATUS, STRATEGY AND ISSUES

Collimators and Cleaning, Could this Limit the LHC Performance?

Signaling the Arrival of the LHC Era December Current Status of the LHC. Albert De Roeck CERN Switzerland

LHC Commissioning and First Operation

Operational Experience with HERA

New LSS optics for the LHC (status)

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION

Accelerators. Lecture V. Oliver Brüning. school/lecture5

The Large Hadron Collider Lyndon Evans CERN

Tools of Particle Physics I Accelerators

Beam. RF antenna. RF cable

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

LHC Commissioning The good, the bad the ugly

Machine Protection Systems

Simulations of HL halo loss and IR losses. R. Bruce, F. Cerutti, R. de Maria, A. Marsili, S. Redaelli

AFP - TCL collimator studies

The TESLA Dogbone Damping Ring

Simulations and measurements of collimation cleaning with 100MJ beams in the LHC

Daniel Wollmann, CERN

LC Commissioning, Operations and Availability

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

1.1 Machine-Detector Interface

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

Are we ready for the 2009 beam operation?

Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug

Sources of machine-induced background in the ATLAS and CMS detectors at the CERN Large Hadron Collider

LHC Luminosity and Energy Upgrade

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

Machine Protection Basics of Accelerator Science and Technology at CERN

(a) (b) Fig. 1 - The LEP/LHC tunnel map and (b) the CERN accelerator system.

MACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC

Beam-induced radiation in the compact muon solenoid tracker at the Large Hadron Collider

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

LHC APERTURE AND COMMISSIONING OF THE COLLIMATION SYSTEM

Turn-around improvements

Chamonix XII: LHC Performance Workshop. Requirements from the experiments in Year 1*

Low Energy RHIC electron Cooling (LEReC)

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

e + e Factories M. Sullivan Presented at the Particle Accelerator Conference June 25-29, 2007 in Albuquerque, New Mexico e+e- Factories

LHC: Past, Present and Future

The Very Large Hadron Collider Beam Collimation System

Luminosity for the 100 TeV collider

DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *

The HL-LHC Accelerator Physics Challenges

Run II Status and Prospects

HL-LHC OPERATIONAL SCENARIOS

(Lead) Ions in the LHC

1.1 Electron-Cloud Effects in the LHC

Higgs Factory Magnet Protection and Machine-Detector Interface

Longitudinal Dynamics

THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN D. Missiaen, CERN, Geneva, Switzerland. Fiducialisation

On-axis injection into small dynamic aperture

LUMINOSITY LEVELLING TECHNIQUES FOR THE LHC

Status of linear collider designs:

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

LHC RUN 2: RESULTS AND CHALLENGES

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

SMR/ Summer School on Particle Physics June LHC Accelerators and Experiments (part I) Marzio Nessi CERN, Switzerland

Status and Results of the UA9 Crystal Collimation Experiment at the CERN-SPS

OPERATION OF THE LARGE HADRON COLLIDER WITH HEAVY IONS

The LHC accelerator: Technology and First Commissioning

NEW ARRANGEMENT OF COLLIMATORS OF J-PARC MAIN RING

Report from the Luminosity Working Group of the International Linear Collider Technical Review Committee (ILC-TRC) Chairman: Greg Loew

Update on Development of High Current Bunched Electron Beam from Magnetized DC Photogun

FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR

Particle Physics, Astrophysics and Quantum Field Theory. The Status of the CMS Experiment

LHC RunII Commissioning and HL-LHC Status

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

ALIGNMENT RESULT FOR MAGNET UNITS OF THE SPRING-8 STORAGE RING

R&D ON FUTURE CIRCULAR COLLIDERS

Transcription:

LHC Commissioning in 2008 Mike Lamont AB/OP Schedule slides c/o Lyn Evans (MAC 14/6/07)

Status: Installation & equipment commissioning LHC commissioning - CMS June 07 2 Procurement problems of remaining components (DFBs, collimators) now settled Good progress of installation and interconnection work, proceeding at high pace in tunnel Numerous non-conformities intercepted by QA program, but resulting in added work and time Technical solutions found for inner triplet problems, but repair of already installed magnets will induce significant delays Commissioning of first sectors can proceed by isolating faulty triplets, but will have to be re-done with repaired triplets (needing additional warm-up/cooldown cycles) First sector cooled down to nominal temperature and operated with superfluid helium; teething problems with cold compressor operation have now been fixed. Power tests now proceeding.

Sector 78 LHC commissioning - CMS June 07 3 Should power the main de-focusing quadrupole circuit today. End hardware commissioning 6 th July for warm-up

Schedule LHC commissioning - CMS June 07 4 12 23 34 45 56 67 78 81 Consolidation. Operation testing of available sectors Machine Checkout Beam Commissioning to 7 TeV Interconnection of the continuous cryostat Leak tests of the last sub-sectors Inner Triplets repairs & interconnections Global pressure test &Consolidation Flushing Cool-down. Warm up Powering Tests

LHC commissioning - CMS June 07 5 General co-ordination schedule - Milestones Pressure test Cool-down Powering tests Sector 12 27-28 Oct. 07 03 Dec. 07 25 Jan. 08 28 Jan.08 18 Apr.08 Sector 23 15-16 Sep.07 05 Nov. 07 14 Dec.07 17 Dec. 07 21 Mar. 08 Sector 34 11-12 Aug. 07 17 Sep. 07 26 Oct. 07 29 Oct. 07 30 Nov. 07 03 Mar. 08 28 Mar. 08 31 Mar. 08 02 May 08 Sector 45 Done 25 Jun. 07 14 Sep. 07 17 Sep. 07 30 Nov. 07 10 Mar. 08 04 Apr. 08 07 Apr. 08 02 May 08 Sector 56 18-19 Aug. 07 01 Oct. 07 09 Nov. 07 12 Nov. 07 15 Feb.08 Sector 67 25-26 Sep. 07 22 Oct. 07 30 Nov. 07 03 Dec. 07 15 Feb.08 Sector 78 Done Done Started 29 Jun. 07 08 Oct. 07 16 Nov. 07 19 Nov. 07 22 Feb. 08 Sector 81 16-17 Jun. 07 27 Aug. 07 09 Nov. 07 12 Nov. 07 22 Feb. 08

LHC commissioning - CMS June 07 6 2008 LHC Accelerator schedule

LHC commissioning - CMS June 07 7 2008 LHC Accelerator schedule

LHC commissioning - CMS June 07 8 General Schedule Engineering run originally foreseen at end 2007 now precluded by delays in installation and equipment commissioning. 450 GeV operation now part of normal setting up procedure for beam commissioning to high-energy General schedule being reassessed, accounting for inner triplet repairs and their impact on sector commissioning All technical systems commissioned to 7 TeV operation, and machine closed April 2008 Beam commissioning starts May 2008 First collisions at 14 TeV com July 2008 Pilot run pushed to 156 bunches for reaching 10 32 cm -2 s -1 by end 2008 No provision in success-oriented schedule for major mishaps, e.g. additional warm-up/cool-down of sector

Commissioning Plans

LHC commissioning - CMS June 07 10 Commissioning stages Establish colliding beams as quickly as possible Safely Without compromising further progress Initial optics: β*= 11 m in IR 1 & 5 β*= 10 m in IR 2 & 8 Crossing angles off 1, 12, 43, 156 bunches per beam No parasitic encounters - no long range beam-beam Larger aperture in IRs

LHC commissioning - CMS June 07 11 Phase A: Beam Start with Pilot Beam: Single bunch, 5 to 10 x 10 9 protons Intermediate single: 3 to 4 x 10 10 ppb 4 bunches etc. pushing towards 43 (and possibly 156) bunches 3 to 4 x 10 10 ppb (3.1 ma - 2 MJ) Good for Instrumentation (bunch spacing), RF, vacuum Relatively safe beam Reduced demands on beam dump system, Collimation & Machine protection

Stage A: Commissioning Phases LHC commissioning - CMS June 07 12 Have to commission: Hardware: RF, beam Dump, Collimators, Kickers etc Instrumentation: BPMs, BLMs, BCT, Beam size, luminosity etc. Controls Machine Protection Measure optics, energy, aperture etc. etc. etc. Procedures: Injection, snapback, ramp, squeeze, recover etc. Details available

Beam commissioning to 7 TeV collisions 20/6/2007 Rings Total [days] 1 Injection and first turn 2 4 2 Circulating beam 2 3 3 450 GeV - initial 2 4 4 450 GeV - detailed 2 5 5 450 GeV - two beams 1 1 6 Snapback - single beam 2 3 7 Ramp - single beam 2 6 8 Ramp - both beams 1 2 9 7 TeV - setup for physics 1 2 10 Physics un-squeezed 1 - TOTAL TO FIRST COLLISIONS 30 11 Commission squeeze 2 6 12 Increase Intensity 2 6 13 Set-up physics - partially squeezed. 1 2 14 Pilot physics run LHC commissioning - CMS June 07 13

Stage A: First collisions LHC commissioning - CMS June 07 14 Approx 30 days of beam time to establish first collisions Un-squeezed Low intensity Approx 2 months elapsed time Given optimistic machine availability Continued commissioning thereafter Increased intensity Squeeze

Stage A: Ramp LHC commissioning - CMS June 07 15 Start of the ramp could be messy Persistent currents (main contribution dipoles) decay on the injection plateau Potentially big shifts in chromaticity, tune, momentum Snapback at start of ramp (timescale ~ 1 minute) large parameter shifts have to corrected Learn with low beam currents Collimators have to protect arc aperture (~7.5 σ) Experiments are un-squeezed plenty of aperture in IRs (Unless any weak magnets show up expect to go to 7 TeV)

LHC commissioning - CMS June 07 16 Stage A - Luminosities 1 to N to 43 to 156 bunches per beam N bunches displaced in one beam for LHCb Pushing gradually one or all of: Bunches per beam Squeeze Bunch intensity IP 1 & 5 Bunches β* I b Luminosity Event rate 1 x 1 18 10 10 10 27 Low 43 x 43 18 3 x 10 10 3.8 x 10 29 0.05 43 x 43 4 3 x 10 10 1.7 x 10 30 0.21 43 x 43 2 4 x 10 10 6.1 x 10 30 0.76 156 x 156 4 4 x 10 10 1.1 x 10 31 0.38 156 x 156 4 9 x 10 10 5.6 x10 31 1.9 156 x 156 2 9 x 10 10 1.1 x10 32 3.9

Stage B 75ns LHC commissioning - CMS June 07 17 Parameter tolerances: Tightened up. Optics/beta beating under control Commission crossing angles. Injection, ramp and squeeze long range beam-beam, effect on dynamic aperture, Need for feedback orbit plus adequate control of tune and chromaticity through snapback. Lifetime and background optimization in physics with a crossing angle and reduced aperture needs to be mastered. Bunch train bunch-to-bunch variations, implications for beam instrumentation. Emittance conservation through the cycle Plus Machine Protection with increased intensity Won t happen overnight

Issues

Collimators - system overview Phase 1 Momentum Cleaning Final system: Layount is 100% frozen! 20/6/2007 Betatron Cleaning LHC commissioning - CMS June 07 19

Collimators - Functional Description LHC commissioning - CMS June 07 20 Two-stage cleaning (robust CFC primary and secondary collimators). Catching the cleaning-induced showers (Cu/W collimators). Protecting the warm magnets against heat and radiation (passive absorbers). Local cleaning and protection at triplets (Cu/W collimators). Catching the p-p induced showers (Cu collimators). Intercepting mis-injected beam (TCDI, TDI, TCLI). Intercepting dumped beam (TCDQ, TCS.TCDQ). Scraping and halo diagnostics (primary collimators and thin scrapers).

Collimation - goals LHC commissioning - CMS June 07 21 The plan is have almost all the 118 initial LHC collimators/absorbers of the phase 1 collimation system in place for the 2008 startup. Full passive protection & high cleaning efficiency (> 99.99%) will be there. Last collimators for installation ready in January 2008. Tertiary collimators will be installed in IP 1 & 5 Ralph Assmann

LHC commissioning - CMS June 07 22

Aperture LHC commissioning - CMS June 07 23 Triplets only become potential aperture limits at around β* 5 m.

Vacuum Will start with warm vacuum chambers baked and NEG activated, both in the experimental region and in the LSS. The static pressure after this is expected to be of order 10-11 mbar (as already achieved in ALICE). Cold sections will be simply cooled Followed by conditioning with beam: Dynamic vacuum: increase beam current induced multipacting lower secondary electron emissions. Things get a bit worse. After conditioning things will improve. 20/6/2007 LHC commissioning - CMS June 07 24

Vacuum LHC commissioning - CMS June 07 25 Residual gas density estimations in LHC Insertion Regions IR1 and IR5 and the experimental regions of ATLAS and CMS for different beam operations. Adriana Rossi LPR 783

Background (briefly!) Nikolai Mokhov Residual gas within experiments Baked out etc. low rates Residual gas in adjacent straight sections See Adriana Rossi Gas pressure in adjacent cold sectors Residual gas pressures expected in the cold arcs 20 times those in the cold sections of the LSS Elastic scattering into IRs Muons Inefficiency of cleaning in IR7 & IR3 Tertiary halo on tertiary collimators Not an issue initially See: M. Huhtinen, V. Talanov, G. Corti, N. Mokhov et al 20/6/2007 LHC commissioning - CMS June 07 G. Corti, V. Talanov 26

Conclusions LHC commissioning - CMS June 07 27 Beam commissioning Should start May 2008 2 months to get first collisions First collisions - low intensity, un-squeezed. We will be careful. Phase A No crossing angle Gradual increase in current - up to 156 bunches/beam Pilot physics: un-squeezed to partial squeeze 10 32 cm -2 s -1 Collimation Phase 1 scheme will be in place Full and appropriate machine protection will be pursued. http://cern.ch/lhccwg/