SPIRAL 2 Commissioning Status

Similar documents
Setting the Spiral2 control system for the on-going commissioning. Eric Lécorché/ Epics meeting 21/10/2014 1

IFMIF mini-workshop on Beam Instrumentation. Ciemat, Madrid (Spain) 2-3 July 2007

The SARAF 40 MeV Proton/Deuteron Accelerator

OVERVIEW OF THE BEAM DIAGNOSTICS FOR THE DRIVER OF SPIRAL2

Heavy Ion Accelerators for RIKEN RI Beam Factory and Upgrade Plans. Upgrade Injector

The Accelerator System for ReA3 the New Re-accelerated RIBs Facility at MSU

SPIRAL-2 FOR NEUTRON PRODUCTION

R&D on µ-lom monitors for High intensity Linacs like LIPAc

A small but EFFICIENT collaboration for the Spiral2 control system development

Report on PIAVE G. Bisoffi

Study of Analyzing and Matching of Mixed High Intensity Highly Charged Heavy Ion Beams

Beam Diagnostics and Instrumentation JUAS, Archamps Peter Forck Gesellschaft für Schwerionenforschnung (GSI)

Beam. RF antenna. RF cable

Status & Plans for the TRIUMF ISAC Facility

Progress of RAON Heavy Ion Accelerator Project in Korea

A high intensity p-linac and the FAIR Project

Accelerators for the Advanced Exotic Beam Facility

LHC operation in 2015 and prospects for the future

Beam Diagnostics for Low Energy Proton and H - Accelerators. Vic Scarpine Fermilab 2012 BIW April 16-19, 2012

PIP-II Injector Test s Low Energy Beam Transport: Commissioning and Selected Measurements

Present status of RIBF accelerators at RIKEN

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

The SARAF CW 40 MeV Proton/Deuteron Accelerator

THE DESIGN AND COMMISSIONING OF THE ACCELERATOR SYSTEM OF THE RARE ISOTOPE REACCELERATOR ReA3 AT MICHIGAN STATE UNIVERSITY*

Commissioning of the SNS Beam Instrumentation

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

Beam Diagnostics for RIBF in RIKEN

BEAM DYNAMICS IN A HIGH FREQUENCY RFQ

The SPIRAL 2 Project at GANIL

HIGH INTENSITY ACCELERATORS FOR NEUTRON PRODUCTION AT CEA SACLAY

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

IFMIF High energy beam line design and beam expansion using non-linear multipole lenses and "step-like" magnet

HIGH CURRENT PROTON BEAM INVESTIGATIONS AT THE SILHI-LEBT AT CEA/SACLAY

Chopping High-Intensity Ion Beams at FRANZ

PIP-II Injector Test Warm Front End: Commissioning Update

Review of ISOL-type Radioactive Beam Facilities

Cornell Injector Performance

TEST MEASUREMENTS WITH THE REX-ISOLDE LINAC STRUCTURES*

Development of the UNILAC towards a Megawatt Beam Injector

LHC Status and CERN s future plans. Lyn Evans

NEW DEVELOPMENT IN HIGH POWER RFQ ACCELERATORS*

THE ADVANCEMENT OF SPIRAL 2 PROJECT

Diagnostics at SARAF

Conditionnement et caractérisation de l injecteur IFMIF à Rokkasho au Japon

Overview of the EURISOL post-accelerator design and studies

Operational Experience in PIAVI-ALPI Complex. E. Fagotti INFN-LNL

STATUS REPORT ON SPIRAL1 F. Chautard October 2 nd, 2007

Low Energy RHIC electron Cooling (LEReC)

GANIL/SPIRAL2 The adventure continues

LHC status & 2009/2010 operations. Mike Lamont

ALBA Synchrotron Light Source Commissioning

arxiv: v2 [physics.acc-ph] 21 Jun 2017

Status of Proof-of-Principle Experiment of Coherent Electron Cooling at BNL

1.5-GeV FFAG Accelerator as Injector to the BNL-AGS

Large Hadron Collider at CERN

SPES Conceptual Design Report

BESSY Status. Peter Kuske, Helmholtz-Zentrum Berlin, Germany

4GLS Status. Susan L Smith ASTeC Daresbury Laboratory

Raising intensity of the LHC beam in the SPS - longitudinal plane

Performance of the ANL ECR Charge Breeder. with Low Mass Beams. Investigations with low mass species. Review of charge breeder design

NSCL Operations and ReAcclerator Facility at MSU. Daniela Leitner Michigan State University

OVERVIEW OF RECENT RFQ PROJECTS *

Status of the ESR And Future Options

A new sc cw-linac for Super Heavy Element Research. S. Jacke LINAC department, GSI Helmholtz-Institut Mainz (HIM) Germany

Statusreport. Status of the GSI accelerators for FRS operation. Jens Stadlmann (FAIR Synchrotrons)

Elliptical Cavities: Proven SRF Option

Diagnostic Systems for Characterizing Electron Sources at the Photo Injector Test Facility at DESY, Zeuthen site

GANIL STATUS REPORT. B. Jacquot, F. Chautard, A.Savalle, & Ganil Staff GANIL-DSM/CEA,IN2P3/CNRS, BP 55027, Caen Cedex, France.

Development of Large Scale Optimization Tools for Beam Tracking Codes

In-Flight Fragment Separator and ISOL Cyclotron for RISP

UPGRADE AND COMMISSIONING OF THE PIAVE-ALPI ECR INJECTOR AT LNL

The New Superconducting RF Photoinjector a High-Average Current & High-Brightness Gun

Development and application of the RFQs for FAIR and GSI Projects

An Accelerator Driven System MYRRHA

TTF and VUV-FEL Injector Commissioning

ESS Linac Beam Physics Design Update

DEVELOPMENT OF JINR FLNR HEAVY-ION ACCELERATOR COMPLEX IN THE NEXT 7 YEARS

Jlab FEL Photoemission DC Guns

Experimental Measurements of the ORION Photoinjector Drive Laser Oscillator Subsystem

DEVELOPMENT OF FFAG AT KYUSYU UNIVERSITY

WG2 on ERL light sources CHESS & LEPP

Introduction Frankfurt Neutron Source at Stern-Gerlach-Zentrum FRANZ Development of new accelerator concepts for intense proton and ion beams. High in

Beam dynamics studies of H-beam chopping in a LEBT for project X

Progress of SPIRAL2 project

Diagnostics Needs for Energy Recovery Linacs

Linac4: From Initial Design to Final Commissioning

What have we learned from the LCLS injector?*

ELECTRON COOLING OF PB54+ IONS IN LEIR

Design Status of the PEFP RCS

arxiv: v1 [physics.acc-ph] 20 Jun 2013

Tuning Techniques And Operator Diagnostics for FACET at SLAC National Accelerator Laboratory. Chris Melton SLAC Accelerator Operations

ERL FACILITY AT CERN FOR APPLICATIONS

Advanced Design of the FAIR Storage Ring Complex

Short Introduction to CLIC and CTF3, Technologies for Future Linear Colliders

Accelerator Option for Neutron Sources & the

ECOS-LINCE PROJECT: A highintensity light- and heavy-ion facility for nuclear structure and reactions

SPS LLRF Measurements and lessons learned

Design of a Sector Magnet for High Temperature Superconducting Injector Cyclotron

ANURIB Advanced National facility for Unstable and Rare Ion Beams

System Integration. E. Fagotti

Transcription:

SPIRAL 2 Commissioning Status Jean-Michel Lagniel (GANIL) for the SPIRAL 2 Team With thanks to the SPIRAL 2 team Page 1

Menu 1- SPIRAL 2 facility (Phase 1) presentation 2- Injector commisionning (Sources and RFQ) 3- SC linac status 4- Summary Page 2

-1- SPIRAL 2 Facility 4 levels 7,200 m 2 More than 100 rooms Page 3

-1- SPIRAL 2 Facility - 9.50 m (beam level) Page 4

-1- SPIRAL 2 Construction SPIRAL 2 building site preparation January 2011 Page 5

-1- SPIRAL 2 construction 2011 +3.5 years : September, 2014 Page 6

-2- SPIRAL 2 injector commissioning Free space for the future A/Q = 7 injector connection RFQ 1 < A/Q < 3 18 GHz 60 kv LPSC Grenoble Medium Energy Beam Transfer Line Fast shopper (Bunch selector) 2.45 GHz 40 kv IRFU Saclay 0.75 MeV/u RFQ Page 7

-2- SPIRAL 2 p/d source commissioning First beam at GANIL December 19, 2014 Protons Issue = noise (emittance growth) Page 8

-2- SPIRAL 2 Heavy-Ion A/Q = 3 source commissioning First beam (230 μa Argon 9+) July 10, 2015 Test He 4 2+ A/Q = 2 D beam forbidden! Page 9

-2- SPIRAL 2 p/d and HI source commissioning 0.2 π mm mrd rms norm. Long period stability (6 ma CW) Emittance measurements f(i) July + August + Sept Ability to extract 11 ma CW from the p source => 6 ma proton beam Beam intensity and emittance control using 6 H and 6 V slit systems Page 10

-2- SPIRAL 2 RFQ low level rf tuning CEA-Saclay-IRFU responsibility + GANIL Team Installation / alignment / vacuum tests Nov. 2014 to Feb. 2015 Voltage law (bead-pull) measurements + adjustments (40 plungers) OK March 2015 Max error = 2.3 % on the quadrupolar mode (+3 % longitudinal emittance increase) Expected transmission = 99.7 % Page 11

-2- SPIRAL 2 RFQ equipment RFQ cabling Cooling / tuning system tests rf amplifiers tests / load JM Lagniel HB 2016, Malmö, Sweden July. 5, 2016 Page 12

-2- SPIRAL 2 RFQ high-power rf commissioning 4 x 60 kw rf amplifiers (tubes / 4 x 3 kw solid state preamplifier) DB electronica (Padova, Italy) First campaign mid October 2015 (~ 2 weeks) Pulsed mode, multipactor issues at low level Procedure adjustments / adjustment of the feedback loop coefficients Second campaign November 2015 (~ 3 weeks) with 3 amplifiers rf power ramp-up up to CW, November 6 : 38 kv CW (2 amplifiers) November 23 : A/Q = 2 field = 75 kv CW (89 kw ) End November : 85 kv CW (with 3 amp / 4) 4 amplifiers needed for the A/Q = 3 field = 113 kv (180 kw => 4 x 45 kw) Page 13

-2- SPIRAL 2 RFQ beam commissioning 2015, December 03, 9h26 : First RFQ beams (Protons) RFQ in CW rf operation (up to 50 kv) Pulsed beam 200 μa, 200 μs, 2 Hz 5 ma with 100% transmission at the end of the working day (SPIRAL 2 nominal beam current) TraceWin / TOUTATIS Page 14

-2- SPIRAL 2 RFQ beam commissioning First CW proton beam : December 18, 2015 : 2.3 ma First 5 ma CW proton beam : December 23, 2015 100 % transmission Fine tuning using the RFQ vacuum A/Q = 2 beam up to 1.5 ma 4 He 2 + February 25, 2016 : First pulsed beam, 250 μa First CW beam : June 04, 2016 ~ 1 ma Transmission > 99 % Proton & A/Q = 2 : RFQ always operated CW from the rf point of view rf operation stable and reliable (with 3/4 amps, up to 80 kv) Page 15

-2- SPIRAL 2 RFQ beam commissioning 3 main objectives for the commissioning 1 = Measure the RFQ beam characteristics, including the longitudinal emittances using a rebuncher + FFC & BEM 2 = Debug / measure the performances of the diagnostics (BTI) 3 = Prepare the Superconducting LINAC commissioning measuring the beam characteristics for the different commissioning phases (low current) TraceWin Measurement Page 16

-2- SPIRAL 2 Injector Test Bench (BTI) Fast Current Transformer FCT Beam Position Monitor BPM Time Of Flight TOF Bunch Ext. Monitor Emittance meas. Slits Beam Position Monitor BPM Time Of Flight TOF DCCT Beam dump Camera port Profileur MIGR Profileur EMS Fast Faraday cup Slow Faraday cup Diagnostics IBIC 16, Barcelona, September Page 17

-2- SPIRAL 2 RFQ A/Q > 2 rf conditioning A/Q = 3 A/Q = 2 MTTR Amplifiers : 20 min to restart (delays) + Field ramp up : 40 to 90 min (slow feedback) V max achieved today 96 kv CW 114 kv 15% duty cycle Page 18

-2- SPIRAL 2 RFQ A/Q > 2 rf conditioning Issue # 1 = rf amplifiers reliability / availability Availability : one short period with 4 amps, 3/4 amps most of the time, 2/4 today MTBF too short (over protections?) MTT Repair / Restart too longs (spares / shorter delays?) Issue # 2 = LLRF LLRF : amplitude and phase control of 4 amps coupled to one RFQ cavity Variable frequency mode unavailable Variable frequency mode implemented based on internal I/Q vector rotations of the 4 signals Amplifier issue? (differences between the 4 amps, delayed response, nonlinearities ) LLRF issue? Page 19

-2- SPIRAL 2 RFQ A/Q > 2 rf conditioning Issue # 3 = RFQ cavity tuning loop Very difficult to tune at high power Too slow Unstable Long water lines 3-Way valve response time = 30 s Long delay Stability = Long time constant (> 2 D) Slow response of the cavity tuning loop Slow rf power ramp-up Page 20

-3- SPIRAL 2 Facility 88 MHz QWR 12 x 1 = 12 β = 0.07 cavities Superconducting LINAC 7 x 2 = 14 β = 0.12 cavities CW Energy max beam (MeV/n) power (kw) Q/A I max (ma) P 1/1 5 2-33 165 D 1/2 5 2-20 200 Ions 1/3 1 2-14.5 45 1/7 1 2-8 48 Wide range of particles, intensities, energies, duty-cycles (CW up to single bunch) JM Lagniel HB 2016, Malmö, Sweden July. 5, 2016 Page 21

-2- SPIRAL 2 LINAC cryomodules Today : 12 /12 CM-A + 6 /7 CM-B aligned and connected to their valve boxes Page 22

-2- SPIRAL 2 LINAC hot section installation 18 / 20 hot-section installed Page 23

-2- SPIRAL 2 SC linac installation All the valve-boxes have been re-fabricated (mechanical errors, cryo. leaks ) 2 cryomodules with cryogenic leaks Page 24

-2- SPIRAL 2 LINAC cryogenic system Cryogenic system (1,300 W equivalent 4.5 K) installed, first liquid helium in July 2015 Page 25

-2- SPIRAL 2 LINAC RF system One solid state amplifier / cavity Up to 20 kw Amplifiers, feeders, circulators, LLRF and interlock PLC have been tested independently, installed in the building and interconnected Page 26

-2- SPIRAL 2 HEBT line installation Page 27

-5- Summary Good advances of the SPIRAL 2 project since January 2011!!! - Both light and heavy ion sources working very well - RFQ working well with protons and A/Q = 2 ions (He and O) - RFQ conditioned up to 96 kv CW A/Q = 2.4 ions - RFQ improvements -rf amplifiers (reliability) LLRF (variable freq. loop) Tuning system (faster and stable) - Superconducting linac : first cooling down this week (cooling down of all the valve-boxes + 2 cryomodules) - The installation and commissioning progresses are limited by the availability of the GANIL team Operation of the GANIL cyclotron facility in // - First linac beam beginning 2017 J-M Lagniel ESS, Lund Feb. 23, 2016 Page 28