Hydro-engineers.ch HEC-RAS ANALAYSIS. River: L Aïre Mesfin Tewolde. Hydro-engineers.ch 23 oct. 2017

Similar documents
Floodplain Modeling and Mapping Using The Geographical Information Systems (GIS) and Hec-RAS/Hec-GeoRAS Applications. Case of Edirne, Turkey.

WATERCOURSE HARNESSING BANK EROSION AND CONSOLIDATION

Pirai river (Bolivia)

UPPER COSUMNES RIVER FLOOD MAPPING

Technical Memorandum No Sediment Model

Technical Memorandum No

GEOL 1121 Earth Processes and Environments

UGRC 144 Science and Technology in Our Lives/Geohazards

ENGINEERING HYDROLOGY

Dam Break Analysis Using HEC-RAS and HEC-GeoRAS A Case Study of Ajwa Reservoir

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

Floods Lecture #21 20

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water.

Modeling Great Britain s Flood Defenses. Flood Defense in Great Britain. By Dr. Yizhong Qu

EFFECT OF TWO SUCCESIVE CHECK DAMS ON DEBRIS FLOW DEPOSITION

A SIMPLE GIS METHOD FOR OBTAINING FLOODED AREAS

Instream Erosion Control General

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

Degradation Concerns related to Bridge Structures in Alberta

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Flooding in Dolgellau

Grant 0299-NEP: Water Resources Project Preparatory Facility

Continuing Education Associated with Maintaining CPESC and CESSWI Certification

Earth Science Chapter 6 Section 2 Review

CASE STUDY NATHPA JHAKRI, INDIA

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

USGS Flood Inundation Mapping of the Suncook River in Chichester, Epsom, Pembroke and Allenstown, New Hampshire

MATHEMATICAL MODELING OF FLUVIAL SEDIMENT DELIVERY, NEKA RIVER, IRAN. S.E. Kermani H. Golmaee M.Z. Ahmadi

Running Water Earth - Chapter 16 Stan Hatfield Southwestern Illinois College

Appendix A Flood Damages in 2013

Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

EFFECT OF SAND MINING ACTIVITY ON THE SEDIMENT CONTROL SYSTEM (A CASE STUDY OF SOMBE-LEWARA RIVER, DONGGALA, INDONESIA)

CASE STUDY NATHPA JHAKRI, INDIA

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

Beaver Creek Corridor Design and Analysis. By: Alex Previte

LOMR SUBMITTAL LOWER NESTUCCA RIVER TILLAMOOK COUNTY, OREGON

Flood zoning estimation and river management by using HEC-RAS and GIS model

FLOOD RISK MAPPING AND ANALYSIS OF THE M ZAB VALLEY, ALGERIA

Summary of the 2017 Spring Flood

CHANGES OF RUNOFF MECHANISM OF THE BRANTAS RIVER OVER THE PAST 30 YEARS

Dolores River Watershed Study

Impact of sediments and constructions on river flooding in Coimbra, Portugal

Why Stabilizing the Stream As-Is is Not Enough

APPENDIX A M&T/Llano Seco Long-Term Water Reliability Study These photos are examples of rock spurs in use throughout the United States

Evaluation of Scour Depth around Bridge Piers with Various Geometrical Shapes

Influence of dam removal and past sediment mining on river morphology and biology: example of the Vienne River (France)

Controlling Processes That Change Land

Modelling and Simulation of Floods in Barsa River near Pasakha, Bhutan. Kirtan Adhikari

Gully Erosion Part 1 GULLY EROSION AND ITS CAUSES. Introduction. The mechanics of gully erosion

Four Mile Run Levee Corridor Stream Restoration

Why Geomorphology for Fish Passage

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

Section 5. Low-Gradient Streams. What Do You See? Think About It. Investigate. Learning Outcomes

Strategies for managing sediment in dams. Iwona Conlan Consultant to IKMP, MRCS

Analysis of the Cause for the Collapse of a Temporary Bridge Using Numerical Simulation

GEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012

Sessom Creek Sand Bar Removal HCP Task 5.4.6

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

Earth Science Floods

River Nith restoration, cbec UK Ltd, October 2013 APPENDIX A

Floodplain Risk Management in Dungog after the April 2015 Super Storm. Presentation Outline

Birecik Dam & HEPP Downstream River Arrangement R. Naderer, G. Scharler Verbundplan GmbH, 5021 Salzburg, Austria

DELINEATION OF CATCHMENT BOUNDARY FOR FLOOD PRONE AREA: A CASE STUDY OF PEKAN TOWN AREA

STREAM SYSTEMS and FLOODS

Precipitation Evaporation Infiltration Earth s Water and the Hydrologic Cycle. Runoff Transpiration

Rock Sizing for Multi-Pipe & Culvert Outlets

The last three sections of the main body of this report consist of:

Countermeasure Calculations and Design

7.3 Sediment Delivery Analysis

Engineering Hydrology

Flood Inundation Analysis by Using RRI Model For Chindwin River Basin, Myanmar

Geomorphic Importance of Winter Peak Flows and Annual Snowmelt Hydrographs in a Sierra Nevada Boulder-Bedrock River

Stop 1: Marmot Dam Stop 1: Marmot Dam

L OWER N OOKSACK R IVER P ROJECT: A LTERNATIVES A NALYSIS A PPENDIX A: H YDRAULIC M ODELING. PREPARED BY: LandC, etc, LLC

6.4 Sensitivity Tests

The Effects of Hydraulic Structures on Streams Prone to Bank Erosion in an Intense Flood Event: A Case Study from Eastern Hokkaido

YELLOWSTONE RIVER FLOOD STUDY REPORT TEXT

MAPPING THE FLASH FLOOD PRONE AREA IN THE TAITA WATERSHED (ROMANIA) USING TOPOGRAPHIC INDEXES AND HYDRAULIC MODEL

LOCATIONS OF SELECTED MITIGATION SITES IN JAPAN

The Effects of Flooding on Structures. Or What to Expect when the Drought Ends Violently

ANALYSIS OF THE FLOODS EFFECTS IN JUNE 2016 IN THE VORONET RIVER HYDROGRAPHIC BASIN

URBAN AREA HYDROLOGY AND FLOOD MODELLING

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Nevado Del Ruiz, Lahars

Rock Sizing for Waterway & Gully Chutes

Impact of Climate Change on Riverbank Erosion

9. Flood Routing. chapter Two

Hydrologic hazards can be considered in three categories; An indication of flooding potential for areas located

!"#$%&&'()*+#$%(,-./0*)%(!

WORKSHOP #2 [Modeling and Sediment Transfers Review of alternative solutions] Bucharest 07 October 2015

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Streams. Stream Water Flow

4.17 Spain. Catalonia

Erosion Surface Water. moving, transporting, and depositing sediment.

ANTHROPIC MODIFICATIONS OF THE RIVERBEDS OF IALOMIŢA AND IALOMICIOARA UPSTREAM FROM THEIR CONFLUENCE IN FIENI

IMPACTS OF SECONDARY FLOOD EMBANKMENTS ON THE WAIMAKARIRI FLOODPLAIN, NEW ZEALAND

Pequabuck River Flooding Study and Flood Mitigation Plan The City of Bristol and Towns of Plainville and Plymouth, CT

Flood and Stream Restoration

Transcription:

Hydro-engineers.ch HEC-RAS ANALAYSIS River: L Aïre Mesfin Tewolde 17 Hydro-engineers.ch 23 oct. 2017

PREPARED BY MESFIN TEWOLDE [TEMPORARY MISSION] Hydro-engineers.ch HEC-RAS ANALYSIS [January- March 2014] River: L Aïre Country: Switzerland

CONTENTS 1. HEC-RAS ANALYSIS... 1 1.1 THE RIVER AÏRE... 1 1.2 GIVEN DATA... 4 1.3 THE RESULT... 6 1.4 RESULT ANALYSIS... 7 1.5 PROPOSITIONS... 8 1.6 POINTS TO HIGHLIGHT... 8 LIST OF FIGURES Figure 1 Catchment and watercourse of L Aïre...2 Figure 2 The river reach (5.36km)...2 Figure 3 Newly constructed diversion structure and tunnel...3 Figure 4 Vegetation covers around 2.8 km of the Pont-Rouge,...3 Figure 5 Eroded bank at around 4km upstream of the D/S end...4 Figure 6 Unstable bank at around 4km of the D/S end...4 Figure 7 Cobbles along the main river bed...5 Figure 8 Vegetation covers along the river (represent 60-70%)...6 Figure 9 Longitudinal profile of the river for each return period...6 Figure 10 Plan view...7 Figure 11 Cross-section at station 4107.7m...7 LIST OF TABLES Table 1 Flow measured for four return periods...5 i

1. HEC-RAS ANALYSIS Location: Geneva, Switzerland River Reach: L Aïre Period of Analysis: January- March 2014 Enterprise: Secteur dynamique de l'eau et métrologie (SECOE), Geneva Flooding can happen whenever flowing water surpasses its bank full stage and eventually inundate the surrounding adjacent areas. These may perhaps take place during the course of intense rainfalls and when a significant amount of snow melts. In conjunction with inundation, the increase of flow velocity may possibly erode and cause damage to fragile riverbanks resulting into more devastating damages. For this reason, it is best to consider proper protection measures along the vulnerable banks before the arrival of extreme flows. Along the river Aïre many stabilization measures exist. For instance, one can see biological or organic protection as a measure to protect further degradation of banks. Moreover, certain gabion protections exist. Nevertheless, there are still spots where bank stabilization is needed. As it is pointed out in Figure 5 and 6, river-bank curvatures are prone to erosion and require protection. Construction of levees, temporary or provisional flood storage basins, and sometimes elevating the village above the flood line are some of the precautions that need to be implemented to alleviate future potential mishaps. To demonstrate the impact of various time period discharges such as 10 years of recurrence time period (Q10), 30 years of recurrence time period (Q30), 100 years of recurrence time period (Q100) and 300 years of recurrence time period (Q300) HEC-RAS model can be employed. In this analysis, the discharges for four recurrence time periods assessed and the findings of the analysis and the proposition of the result stated in the following paragraphs. 1.1 THE RIVER AÏRE The river Aïre originates at the outskirts of the villages of Presilly, Beaumont, and Feigéres in France. The diverse branches of the watercourse confluence at the small town referred as St Julien en Genevois then simply carries on flowing in the direction of Geneva city, traversing along the parts of the city that includes Confignon, Lancy. Eventually, the river unites with another river known as L Arve right underneath the Saint-Georges Bridge. The origins and the course of the river are shown below in figures 1, 2, and 3. 1

Figure 1 Catchment and watercourse of L Aïre Figure 2 The river reach (5.36km) 2

Figure 3 Newly constructed diversion structure and tunnel Figures 4, 5, and 6 demonstrate the representation of banks along the given reach. Figure 4 Vegetation covers around 2.8 km of the Pont-Rouge, (Photo was taken on 4.03.2014) 3

Figure 5 Eroded bank at around 4km upstream of the D/S end (Photo was taken on 4.03.2014) 1.2 GIVEN DATA Figure 6 Unstable bank at around 4km of the D/S end (Photo was taken on 4.03.2014) To run the HEC-RAS model, cross-sectional and hydrological data were provided. However, there was no description about the origin of the data. No information was given whether the data was a recollect of surveying data or ArcGIS extraction or any other software product. Certain cross-sections were modified. Therefore, corrections as needed were made in order to run the model. The overall length of the reach considered in this analysis was 5363.91 ms. On average there was a 23.5ms distance in between the cross-sections, there exist five bridges along the reach as well. The central waterway had cobbles and roughly 70% of the right and the left bank had vegetation covers as shown in Figures 7 and 8. Consequently, the roughness coefficient assumed to be 0.05 and 0.1 for the beds and for the banks respectively. Besides, there were lateral concrete structures and tributaries along the 4

stream.the flow fluctuates along the river and supplementary lateral flows pointed out at around 1690m of the downstream of the river. Flows for the given recurrence time periods are presented in Table 1. Table 1 Flow measured for four return periods Figures 7 and 8 indicate representation of the riverbed, the right and the left banks of the river. Figure 7 Cobbles along the main river bed 5

Figure 8 Vegetation covers along the river (represent 60-70%) Running the model using the data given above shown step by step in this video link 1.3 THE RESULT The Following Figures 9, 10, 11 show the result of the analysis. Figure 9 Longitudinal profile of the river for each return period 6

Figure 10 Plan view Figure 11 Cross-section at station 4107.7m 1.4 RESULT ANALYSIS The provided flow data for 100 years of return period at Pont des Marais and at Pont Rouge equals 39 Cumec and 48 Cumec respectively. The HEC-RAS simulated velocities along the river are in the range of 0.63 3.95 m/s. In this regard, it is important to check out particularly the higher velocities mainly because the rise in velocity along the channel may easily erode the banks. 3m/s velocity has the ability to erode natural ground and can carry even bigger objects along its path. For instance, throughout the regular flow periods, the velocity at Pont du Centenaire is about 0.25m/s for a discharge of 0.745Cumecs. This velocity is much less than the scouring velocity. Nevertheless, 39 Cumec discharge is capable of generating somewhat higher flow velocity in the channel causing erosion along the 7

banks. As a result of higher flows such as Q100 and Q300, overflowing and inundation may occur. Therefore, precautionary measures are necessary to have certain kind of protection from potential future damages. As the highest possible discharge that can be taken care of at the Pont Rouge (tunnel entrance) is 60 Cumec, lowering the discharge below 60 Cumec is essential. The new construction work of the diversion structure reduced effectively the amount of discharge at the Pont Rouge. The result of this HEC-RAS analysis has also demonstrated the same. 1.5 PROPOSITIONS Once the banks are eroded the water gets an easy way to spread out over the banks inundating the village and the surrounding vicinity, particularly the left and right side of the bank where there exist adjacent dwelling premises. Subsequently, precautionary measures such as gabion wall or concrete retaining wall assist to offer protection to the banks throughout the flooding periods. Moreover, inundation of the village can also be eliminated by setting up temporary detention basins at the upstream side of the river. Temporary detention dam contributes greatly to reduce the possible hazard of future harm to the downstream villagers. The following video link shows how to prepare HEC-RAS data using ArcGIS. Flood mapping analysis using HEC-RAS also shown in this video link, Video link of the reach considered for this analysis Other useful videos can also be accessed at this link 1.6 POINTS TO HIGHLIGHT Location: Geneva Reach length: 5.36km The principal Catchment area of L Aïre: 72. Sq km 8