LHC. LHC Crabs, Status. Brief Overview. Status of Technology R&D. Status of Simulations & Experiments. Rama Calaga RFTECH, Dec 2-3, 2010

Similar documents
HL-LHC: parameter space, constraints & possible options

LHC Upgrade Plan and Ideas - scenarios & constraints from the machine side

6D weak-strong beam-beam simulations with SixTrack: theory and simulations

LHC Luminosity and Energy Upgrade

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

HL-LHC OPERATIONAL SCENARIOS

Beam-Beam DA Simulations for HL-LHC

A Luminosity Leveling Method for LHC Luminosity Upgrade using an Early Separation Scheme

THE HIGH LUMINOSITY LHC PROJECT 1

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Deliverable Report SIMULATION MODELS FOR ENERGY DEPOSITION

Beam. RF antenna. RF cable

SPS LLRF Measurements and lessons learned

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

e + e Factories M. Sullivan Presented at the Particle Accelerator Conference June 25-29, 2007 in Albuquerque, New Mexico e+e- Factories

LHC Upgrade (accelerator)

Simulations of HL-LHC Crab Cavity Noise using HEADTAIL

HL-LHC ALTERNATIVES SCENARIOS

LHC Collimation and Loss Locations

LUMINOSITY OPTIMIZATION AND LEVELING

Lattice Design and Performance for PEP-X Light Source

Aperture Measurements and Implications

The TESLA Dogbone Damping Ring

Transverse beam stability and Landau damping in hadron colliders

OVERVIEW OF THE LHEC DESIGN STUDY AT CERN

Correction of β-beating due to beam-beam for the LHC and its impact on dynamic aperture

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

Possible Uses of Rapid Switching Devices and Induction RF for an LHC Upgrade

BEAM DYNAMICS STUDIES FOR HILUMI LHC

Fermilab HG cavity and coupler R&D

Beam Physics at SLAC. Yunhai Cai Beam Physics Department Head. July 8, 2008 SLAC Annual Program Review Page 1

Beam losses versus BLM locations at the LHC

Luminosity for the 100 TeV collider

Overview of LHC Accelerator

We acknowledge the support of the European Community-Research Infrastructure Activity under the FP6 "Structuring the European Research Area"

DYNAMIC APERTURE STUDIES FOR HL-LHC V1.0 *

HE-LHC Optics Development

arxiv: v1 [physics.acc-ph] 21 Oct 2014

Status of Optics Design

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

STATUS OF BEPC AND PLAN OF BEPCII

Emittance Growth and Tune Spectra at PETRA III

DEVELOPMENT AND BENCHMARKING OF CODES FOR SIMULATION OF BEAM-BEAM EFFECTS AT THE LHC

Longitudinal Dynamics

Impedance & Instabilities

Construction Status of SuperKEKB

Status of linear collider designs:

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

ILC Beam Dynamics Studies Using PLACET

LHC operation in 2015 and prospects for the future

Plans for the LHC Luminosity Upgrade Summary of the CARE-HHHAPD-LUMI-05 workshop

NEXT GENERATION B-FACTORIES

Electron-Cloud Theory & Simulations

Beam-beam issues for LHC upgrade phases 1 and 2

Plans for CESR (or Life Without CLEO)

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

Simulations of single bunch collective effects using HEADTAIL

FLUKA studies on the radiation in the Point 5 Q6-Q7 area: Roman Pots, TCL6 and RR

LHC upgrade based on a high intensity high energy injector chain

Review of proposals of ERL injector cryomodules. S. Belomestnykh

Operational Experience with HERA

IR status. 2009/3/19 M. Iwasaki For Super-KEKB MDI group U. Tokyo, Tohoku U., and KEK

EuCARD-2 Enhanced European Coordination for Accelerator Research & Development. Conference/Workshop Paper

LUMINOSITY LEVELLING TECHNIQUES FOR THE LHC

PUBLICATION. Consolidated EIR design baseline: Milestone M3.6

The HL-LHC Accelerator Physics Challenges

MEASUREMENT AND SIMULATION OF LUMINOSITY LEVELING IN LHC VIA BEAM SEPARATION

The Large Hadron electron Collider (LHeC) at the LHC

Colliders and the Machine Detector Interface

ELIC Design. Center for Advanced Studies of Accelerators. Jefferson Lab. Second Electron-Ion Collider Workshop Jefferson Lab March 15-17, 2004

Low Energy RHIC electron Cooling (LEReC)

Luminosity Goals, Critical Parameters

Status of SuperKEKB Design: Lattice and IR

LHC Commissioning in 2008

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

TUNE SPREAD STUDIES AT INJECTION ENERGIES FOR THE CERN PROTON SYNCHROTRON BOOSTER

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

The 2015 erhic Ring-Ring Design. Christoph Montag Collider-Accelerator Department Brookhaven National Laboratory

Frequency and time domain analysis of trapped modes in the CERN Proton Synchrotron

TLEP White Paper : Executive Summary

Physics 610. Adv Particle Physics. April 7, 2014

BEPC AND THE FUTURE PROGRAM AT IHEP

Letter of Intent for KEK Super B Factory

LHC Status and CERN s future plans. Lyn Evans

Future Light Sources March 5-9, 2012 Low- alpha mode at SOLEIL 1

An Early Separation Scheme for the LHC Luminosity Upgrade

Update on SuperKEKB Design

PBL SCENARIO ON ACCELERATORS: SUMMARY

Accelerator. Physics of PEP-I1. Lecture #7. March 13,1998. Dr. John Seeman

Introduction to Collider Physics

Tevatron Beam-Beam Phenomena and Counter-Measures

Interface with Experimental Detector in the High Luminosity Run

WG2 on ERL light sources CHESS & LEPP

ACHIEVABLE SPACE-CHARGE TUNE SHIFT WITH LONG LIFETIME IN THE CERN PS & SPS

Raising intensity of the LHC beam in the SPS - longitudinal plane

Large Hadron Collider at CERN

COLLECTIVE EFFECTS IN THE LHC AND ITS INJECTORS

Beam Dynamics Issues in SuperKEKB

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

Transcription:

LHC Crabs, Status Rama Calaga RFTECH, Dec 2-3, 2010 Brief Overview Status of Technology R&D Status of Simulations & Experiments LHC Thanks to all LHC-CC collaborators

X-Angle & Crab X-ing Long-Range Beam-Beam (~10 Nominal Sep) 32 Interactions/IP Head-On Beam-Beam (Limited by Max Tune Shift) With crab crossing Increase peak luminosity with increasing x-angle due LR Beam-Beam Increase intensities and smaller emittances beyond head-on beam-beam limit Level luminosity (reduce Pile-up, radiation damage)

Reduction Factor Nominal LHC & KEK-B LHC Upgrade Eff. beam size /R

Gain, Crabs+Leveling HL-LHC, single upgrade envisioned for 2020-21: IR magnet upgrade (HL-LHC, WP3) Collimation upgrade (HL-LHC, WP5) Crab crossing + luminosity leveling (HL-LHC, WP4 project document) {E, max βcrab} 7 TeV Peak Lumi Int. Lumi β* = 55 cm 10% - β* = 25 cm 63% 22% β* = 14 cm 190% 31% Integrated luminosities (G. sterbini): Freq: 400 MHz, Volt < 12 MV, βcc: ~3 km Nb = 1.7 x 1011, * = 0.14 cm, Run time = 10 hrs, TAT = 5 hrs Approx: 265 fb-1/yr (217 fb-1/yr w/o CCs) 2 yr reduction in run time (for 3000 fb-1)

LHC Constraints Bunch length: 7.55 cm (highest frequency 800 MHz) Snaked Beams K. Ohmi B1-to-B2 separation: 194 mm (PB 800 MHz ~ 250mm radius) mm 150 mm 194 mm B2 With few exceptions... (IR4, collimation, exps)

Conventional to Compact ~250 mm outer radius (Not compatible in most of the LHC ring) Compact cavities aiming at small footprint (150 mm) & 400 MHz, 5-10 MV/cavity HWDR, JLAB,OD HWSR, SLAC-LARP DR, UK, TechX Rotated Pillbox, KEK

Compacts, Status RF Geometrical 4 primary compact candidates + 1 elliptical back up HWDR (J. Delayen) HWSR (Z. Li) 4-Rod (G. Burt) Rotated Pillbox (N. Kota) Cavity Radius [mm] 150 145 115 150 Cavity Height [mm] 380 391 280 668 Beam Pipe [mm] 42 45 45 75 Peak E-Field 29 52 62 85 Peak B-Field 105 97.5 113 328 RT/Q 413 215 802 - Kick Voltage: 5 MV, 400 MHz Exact voltage depends on cavity placement & optics Cavity parameters are evolving

SLAC-LARP Design 290 mm Fairly complete design of cavity-couplers Prelim mechanical/thermal analysis also done 580 mm PORTS FOR LOM/HOM v COUPLER ADJACENT BEAM PIPE SHORT RE ENTRANT B.P. END TE11 like mode B-field deflection LONG RE ENTRANT B.P. END FPC PORT Courtesy Z. Li et al.

SLAC-LARP Design

Stress & Temp Distribution AES-SBIR, Phase I Eight Locations of stress over yield Yield Strength 7000 psi Add stiffeners 0.0 1169 2337 3506 4674 5843 7011 8180 9348 3.788 4.235 4.682 5.129 5.576 10517 Stress psi No Coolant in double wall Beam Pipe 2.0 Double wall coax region 2.447 2.894 3.341 Wall Power Loss: 13.4 watts at temperature 6.023 Temperature K

JLAB-ODU Design Cavity complete,. HOM couplers etc.. underway Power Coupler 4.6 cm TEM-Mode B-Field Top plane Moving Towards Cylindrical shape Fewer HOM modes E-Field deflection Mid plane Niowave-STTR, Phase I Phase II approved For building cavity prototype (ODU-Niowave) Courtesy J. Delayen et al.

JLAB-ODU, HOMs Deflecting Mode Accelerating Mode

UK (JLAB) Design Cavity complete,. HOM studies underway 4-Rod TEM Cavity Towards Conical rods HOM Damping Concepts Courtesy G. Burt et al.

KEK-Kota Design Rotated Pillbox with shielding cones HOM studies and damping scheme underway Power Coupler HOM Damping o X Courtesy K. Nakanishi et al.

KEK-Kota, Preliminary HOMs HOM damping calculations still underway

US-Project, Timeline

Simulations Overview Machine protection Sixtrack collimation loss maps for failure scenarios MADX tracking with crab failures Crab RF noise, Beam-Beam Noise simulations: Weak-strong & Strong-strong Synchro-betatron resonances and dispersion KEK-B RF noise measurements RF & Impedance Cavity simulations RF failures and system configuration Analytical estimates and Growth rates and damping criteria Baseline Optics SLHC V3.0 + Crabs Physical & dynamic aperture, *, chromatic compensation, field non-linearity

RF Trip Example (KEKB) Klystron output Pick up power Cavity phase Beam trajectories Beam current Intentional/non-intentional phase changes corresponding orbit changes and beam losses Approx time scale 400 ms (4 turns) Courtesy KEK-B

Simulation Setup Sixtrack & MADX are now setup for abrupt failure scenarios (J. Barranco, R. Calaga, R. Tomas) Collimators In Single crab in IR4 Voltage Phase Collimators In Record Tracks MADX has update function (more flexibility)

Loss Maps, Abrupt Phase Failure No phase failure but with 1 global crab 3 turn phase failure with 1 global crab Initial Distribution Sigma [nominal] Particles lost W/O Crabs 1 Global Crab, IR4 Gaussian Gaussian x1.5-3 x1.5-3 0.009-12.6% 0.01-13.7 % 3 Turn Phase Failure 900 Voltage maintained constant Beam size very large

SPS Tests Crabs potentially in SPS is at COLDEX.41737 (4020 m, LSS4) Crab Bypass similar to COLDEX to move it out of the way during high intensity operation SPS beam tests, 2010 to check emittance lifetime @55/120 GeV coast with m norm emittance Machine protection Setup with 2 collimators: No effect at 1st & full crab effect at 2nd second collimator Primary goal is beam measurement (No implementation of interlocks, BPMs-fast & RF-slow) Failure scenarios (for example: abrupt voltage/phase changes, RF trips etc..) Details: http://emetral.web.cern.ch/emetral/ccins/ccins.htm

KEKB Cryostat 0.48 m 1.5 m Aperture: 150/94 mm (Left/Right) 0.725 m (Radius) Weight: 5830.5 kg, Length: 5 m Crab voltage: {HER, LER} - 1.6 MV, 1.5 MV (design: 1.44 MV) Operational voltage: {HER, LER} 1.4 MV, 0.9 MV Dismantle cavity + ancilliary equipment in clean room Stretch the cavity to arrive +2 MHz Cavity to HP rinsed, transported to CERN and assembled with coupler and cryostat Need atleast 1 year and estimated at $2.5 M ** Crab expert, K. Hosoyama, retires at end of 2010 Courtesy KEK-B

Recent SPS Studies For final decision on crab tests in the SPS (natural emittance growth at 55/120 GeV) Parameter Unit Sep 23 Oct 20 Energy GeV 55 120-0.13/0.18 0.13/0.18 2-3 2 x 1011 1.1 0.5 (12 bunches) x,y m 3.1/2.8 1.5-2.0 RF Voltage MV 3.0 4.0 (also 2) Qx,y x,y Intensity

SPS Studies R. Calaga, L. Ficcadenti, E. Metral, G. Rumolo, R. Tomas, J. Tuckmantel, F. Zimmermann Emittance growth too large for crab experiments (larger in horizontal plane) 55 GeV: Sep 23, 2010 Wire stuck Emittance growth in vertical plane seem reasonable (larger in H-plane) 120 GeV: Oct 20, 2010 Repeat the experiments with different horizontal tune (simulations H. J. Kim)

Conclusions Crab R&D (EuCARD + LARP + KEK) Crab project under HL-LHC Advanced technology designs waiting for prototyping Advanced studies on several beam physics fronts Focus on development & construction of compact cryomodules A draft report in place (schedule/resources) Synchronize prototyping within the other major collaborators SPS tests Initial tests promising but need more MDs to establish beam conditions Finalize the use of KEK-B cavities and preparation of SPS (Dec 2010) Many thanks to all the LHC-CC collaborators LHC

LHC-CC10 Announcement of the 4th LHC-CC Workshop series Venue: CERN Date: Dec 15-17, 2010 Charge: 1. Can compact cavities for the LHC be realized and made robust with the complex damping schemes? 2. Are crab cavities compatible with LHC machine protection, or can they be made to be so? 3. Should a KEKB crab cavity be installed in the SPS for test purposes? http://indico.cern.ch/conferencedisplay.py?confid=100672