VACUUM VESSEL LOWER PORT PENETRATIONS & IN VESSEL VIEWING PORT EXTENSION

Similar documents
Physics of fusion power. Lecture 14: Anomalous transport / ITER

TECHNICAL NOTE related to the Market survey on Water Holding Tanks for the Water Detritiation System (WDS) Prepared by Reviewed by Approved by ---

Toward the Realization of Fusion Energy

Design of structural components and radial-build for FFHR-d1

Role and Challenges of Fusion Nuclear Science and Technology (FNST) toward DEMO

ITER DIAGNOSTIC PORT PLUG DESIGN. N H Balshaw, Y Krivchenkov, G Phillips, S Davis, R Pampin-Garcia

GERDA TG4 - Cryogenic Vessel. Status Report

Technological and Engineering Challenges of Fusion

for the French fusion programme

Lessons learnt on Tritium and workers in Fusion devices

Tritiated Waste Management Opportunities Based On The Reduction Of Tritium Activity And Outgassing 15607

POLICY ISSUE (INFORMATION)

Issues for Neutron Calculations for ITER Fusion Reactor

Yuntao, SONG ( ) and Satoshi NISHIO ( Japan Atomic Energy Research Institute

STATE OF COLORADO DESIGN CRITERIA FOR POTABLE WATER SYSTEMS WATER QUALITY CONTROL DIVISION. Price: $5.00. Revised March 31, 1997

EU PPCS Models C & D Conceptual Design

Possibilities for Long Pulse Ignited Tokamak Experiments Using Resistive Magnets

The Vaisala AUTOSONDE AS41 OPERATIONAL EFFICIENCY AND RELIABILITY TO A TOTALLY NEW LEVEL.

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)

Safety considerations for Fusion Energy: From experimental facilities to Fusion Nuclear Science and beyond

Nuclear Energy in the Future. The ITER Project. Brad Nelson. Chief Engineer, US ITER. Presentation for NE-50 Symposium on the Future of Nuclear Energy

Design optimization of first wall and breeder unit module size for the Indian HCCB blanket module

Welcome to the NRC. Nuclear Energy Tribal Working Group 10/13/2016

Nuclear Fusion and ITER

Study on supporting structures of magnets and blankets for a heliotron-type type fusion reactors

Overview of IFMIF-DONES and testing of materials for DEMO

10.1 Functions, Basic Configuration and System Boundaries

Mission Elements of the FNSP and FNSF

REGULATORY GUIDE 1.54 (Draft was issued as DG-1076) SERVICE LEVEL I, II, AND III PROTECTIVE COATINGS APPLIED TO NUCLEAR POWER PLANTS

Procurement Plan. 3. Proposed Procedures for CDD Components (as per paragraph of the Guidelines:

Ultra-Small Footprint N-Channel FemtoFET MOSFET Test EVM

CRYOGENIC CONDUCTION COOLING TEST OF REMOVABLE PANEL MOCK-UP FOR ITER CRYOSTAT THERMAL SHIELD

Fusion Fuel Cycle. ing. Stefan Ionut SPIRIDON. Association Days, Institutefor Cryogenics and Isotopes Technologies Rm.

Fusion Nuclear Science - Pathway Assessment

Eutelsat practice & views on long term sustainability. COPUOS/SCST - LTS Workshop Vienna, 14 February 2013

Developing a Robust Compact Tokamak Reactor by Exploiting New Superconducting Technologies and the Synergistic Effects of High Field D.

Lamp and Control Panel (Lamp Panel)

Request for Empanelment

IBIDEN Group Green Procurement Guidelines. (Version 6)

Optimization of Plasma Initiation Scenarios in JT-60SA

A Faster Way to Fusion

Hazard Communication

Preliminary Safety Analysis of CH HCSB TBM

Local organizer. National Centralized Tokamak

Princeton Plasma Physics Laboratory

Latest Status of High Temperature Superconducting Cable Projects

HT-7U* Superconducting Tokamak: Physics design, engineering progress and. schedule

DS 300. Electronic Pressure Switch. with IO-Link interface. Stainless Steel Sensor. accuracy according to IEC 60770: 0.35 % FSO.

Chemical Health and Safety General Program

Technical Note ITER Bolometer sensors

Ion Beam Sources for Neutral Beam Injectors: studies and design for components active cooling and caesium ovens

@Copyright 2016 SKAPS Industries.

Letter to non European Union customers

Series 7500 Formed Metal Bellows Catalog 974C

Laboratory Evaluation Report for: Dielectric Pipe Unions

Fact sheet on Intermediates under REACH

A Virtual Reactor Model for Inertial Fusion Energy. Michel Decroisette Noël Fleurot Marc Novaro Guy Schurtz Jacques Duysens

Thermal Analysis. inspiration

Status of the pre-series activities of the target elements for the W7-X divertor. - October

The Fundamentals of Moisture Calibration

CURRENT LEADS FOR THE LHC MAGNET SYSTEM

Thermo-mechanical design of the SINGAP accelerator grids for ITER NB injectors

IAEA SAFETY STANDARDS Geotechnical Aspects of Site Evaluation and Foundations in NPPs, NS-G-3.6

Conceptual Design of CFETR Tokamak Machine

Innovative fabrication method of superconducting magnets using high T c superconductors with joints

IBV Series C Carbon Steel Inverted Bucket Vertical Steam Trap

IBV Series Z Alloy Steel Inverted Bucket Vertical Steam Trap

Tritium Safety of Russian Test Blanket Module

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

Simplified Method for Mechanical Analysis of Safety Class 1 Piping

Inspection of Welds in Small Pipes by NDT Ultrasonic Phased-Array techniques. Detection, positioning, sizing and classification of defects.

REQUEST FOR PROPOSALS CLOSING DATE:

16 Appendix 16 Electrical Research Association Report

DESCRIPTION OF MAIN EQUIPMENT

Weathertightness testing of Solar Slate Plate to MCS012. Prepared for: Michael Share. Solar Slate Plate. 24 th June Test report number

Ion Pump Applications

COPPER FOR BUSBARS CHAPTER 4: SHORT-CIRCUIT EFFECTS

WIESON TECHNOLOGIES CO., LTD.

STATUS OF THE WIGOS DEMONSTRATION PROJECTS

List of Legislative Regulations Dealing with Nuclear Energy and Ionizing Radiation and Related Documents

Neutronics calculations for the ITER Collective Thomson Scattering Diagnostics

M A C H I N E L I S T - P R O D U C T I O N P R O C E S S E S

Derogation Criteria for the Requirements for Generators Network Code

Neutronic Activation Analysis for ITER Fusion Reactor

The Path to Fusion Energy creating a star on earth. S. Prager Princeton Plasma Physics Laboratory

Numerical Analysis And Experimental Verification of a Fire Resistant Overpack for Nuclear Waste

System Integration. E. Fagotti

DMP 331Pi. Precision Pressure Transmitter. pressure ports and process connections with flush welded stainless steel diaphragm

SPECIFICATIONS for the INJECTION DIPOLES OF THOMX

Thermo-structural and heat load analysis of SST-1 Superconducting coils

Consideration on Design Window for a DEMO Reactor

Influence of residual stresses in the structural behavior of. tubular columns and arches. Nuno Rocha Cima Gomes

Hazard Communication Program

HAZARD COMMUNICATION SAFETY PROGRAM

Shielding for Fusion Reactors

Neutron Testing: What are the Options for MFE?

ESS TARGET STATION AN OVERVIEW OF THE MONOLITH LAYOUT AND DESIGN

Grounding and Shielding

Edward C. Robison, PE, SE. 02 January Architectural Metal Works ATTN: Sean Wentworth th ST Emeryville, CA 94608

VK2 volume flow controller Overview

Transcription:

VACUUM VESSEL LOWER PORT PENETRATIONS & IN VESSEL VIEWING PORT EXTENSION 1. Purpose Call for Nomination (C4N) Ref. IO/CFT/18/15702/JPK Summary of Technical Specifications The purpose of the contract is to execute design, prototyping, qualification, manufacturing, acceptance test, delivery support to installation & commissioning of the Lower Penetrations and In Vessel Viewing (IVV) Port Extension to the ITER Organization (IO) in Saint Paul Lez Durance, France. The procurement of is divided in in two Lots: Lot 1 corresponding to Lower Penetrations made of expansion joints, (including the 6 ones for IVV Port), penetrations and their supporting structure. Lot 2 corresponding to the procurement of the IVV Port Extension with associated electrical heaters. 2. Background ITER ( The Way in Latin) is one of the most ambitious energy projects in the world today. 35 nations are collaborating to build the world s largest Tokamak, a magnetic fusion device that has been designed to prove the feasibility of fusion as a large-scale and carbon-free source of energy based on the same principle that powers our Sun and stars. For more information on the ITER project: http://www.iter.org/ The main function of the ITER Vacuum Vessel (VV) is to provide a high quality for the fusion plasma, while shielding external components. The cryostat is to provide the environment to avoid excessive thermal loads from the hot vessel to magnets operating at cryogenic temperature within the tokamak. There are many penetrations to allow the passage of components and systems through the cryostat and VV that are needed to operate and maintain the tokamak. The lower penetrations, located in the lower cylinder area of the tokamak are primary extensions through the cryostat to the port cell area. Three types of lower penetrations are identified: odd port penetrations, even port penetrations (RH ports and cryopump ports) and IVV penetrations, see picture bellow. 1

Figure1: Lower cylinder area, with lower ports. Left: The distribution of the 6 IVV Ports is circled in red. Right: Distribution of Lower penetrations. Lot 1: The lower penetrations, located in the lower cylinder area of the tokamak are primary extensions through the cryostat to the port cell area Two types of lower penetrations are identified: odd port penetrations and even port penetrations (RH ports and cryopump ports). Lower penetrations are housing components crossing the cryostat: o Cooling and baking pipes o Diagnostic electrical cables and feedthrough o Other sensors A penetration is as follow: o A pipe, guarded in the specific case of cooling/baking pipes in stainless steel 1.4404 (316 L). o A multiply below interfacing with the pipe and the cryostat, designed following EN 14917 and/or EJMA. o A flange to fix the penetration onto the cryostat (designed following ASME III and made of SS 304) o A flange to interface with the client rooted inside the penetration o Supports limiting the degree of freedoms of the penetration, fixed onto the cryostat to be designed following the RCC-MR Ed. 2007 when required. As example the design of a penetration is as shown below (conceptual design for divertor penetrations). 2

Figure 2: Divertor odd penetration. Left picture is showing the full penetration made of and gurd pipes, expansion joints and supports. The following table summarizes the number of expansion joints to be designed and qualified as well as quantities and preliminary dimensions. As a whole, 282 bellows will be procured. Dimensions and general requirements Environment normal operation # flange diameter Safety important component Shape Type Quantity Flowing medium Inside Outside 1 408mm x 606mm non SIC oblong Multiply 9 Vacuum cryostat 2 DN650 non SIC circular Multiply 9 Vacuum cryostat 3 DN125 non SIC circular Multiply 54 Vacuum interspace 4 DN200 non SIC circular Multiply 36 Vacuum cryostat 5 DN201 non SIC circular Multiply 18 Vacuum cryostat 6 DN202 non SIC circular Multiply 3 Vacuum cryostat 7 DN203 non SIC circular Multiply 3 Vacuum cryostat 8 DN204 non SIC circular Multiply 6 Vacuum cryostat cryostat 3

9 DN205 non SIC circular Multiply 6 Vacuum cryostat 10 DN125 non SIC Circular Multiply 4 Vacuum cryostat 11 450mm x 250 mm non SIC Oblong Multiply 8 Vacuum interspace 12 DN125 non SIC Circular Multiply 4 Vacuum cryostat 13 450mm x 250 mm non SIC Oblong Multiply 8 Vacuum interspace 14 DN125 SIC1 circular Multiply 108 Vacuum Primary 15 DN400 SIC1 Circular Double 6 Vacuum Primary cryostat The primary function of the ITER Bellows is to keep pressure confinement between the Vacuum vessel and the Cryostat. The bellows also compensate for relative displacements between the connected large components (the vessel, the cryostat) induced by thermal, seismic and electromagnetic loading during operational, incidental or accidental regimes. They shall be designed to comply with strict requirement to ensure low leak rate, low risk of failure, high reliability and periodic testing of their performances to prevent failures. Bellows shall be designed to withstand temperatures from -65 C and 200 C, absolute internal and external pressure of 0.15 MPa and 0.16 MPa respectively. Displacements will be provided in the detailed technical specification. In addition, bellows used on all divertor penetrations, type 14, are confinement barrier and safety important components. These bellows shall be designed to allow stretching by 175mm providing double confinement is limited space available. They shall be designed for 5MPa internal pressure at 270 C and 4MPa internal pressure at 400 C in accidental case. Lot 2: The IVV system penetrates the VV and the cryostat extending the primary outside of the cryostat. There are a total of six IVV Ports located at the lower port # 3, 5, 9, 11, 15, 17, each port is divided in two main parts IVV Port Stub Extension, connecting with the VV sub, and IVV Port Extension connecting the Port with the cryostat, both parts are mechanically connected by an intermediate bellows. These bellows have a circular shape and are made of stainless steel. Bellows are integrated in the penetration to provide a primary tight boundary between the cryostat and the VV and allow for relative deformations. Notice that 4

these bellows are described as part of the IVV Port, but are included in the scope of Lot 1 for arrangement of the bellow procurements. Both the VV and Cryostat are normally operated under conditions, but due to the presence of high temperature and water cooled components, there is a possibility for pressurization during the leaking accident. The IVV Port Extension feature external heater bands. These are used to heat up the structures to 100deg C during operation, and 200deg C during VV baking. The IVV PE main function is to provide primary boundary as well as tritium confinement. The VV is a PIC-1 component and therefore the IVV Ports are PIC-1 components as well. As a PIC-1 component, the seismic class is SC1 (S and F). This means that structural stability and required functional seismic safety performance has to be maintained in the event of an earthquake. This is the main design driver. The materials used to manufacture the penetration shall comply with ITER requirement in terms of low Cobalt content and be compatible with interface materials. Penetrations are part of the Vacuum Vessel design. As such their design and manufacturing shall for the French nuclear code RCC-MR Ed. 2007. This code is driving all the stages of the design justification, material purchase and traceability, welding and NDE including volumetric control of welds, leak testing etc. In the specific case of bellows, EN14917 has been chosen for the justification of the design of multiply bellows. All welds shall comply with supplementary requirements as per ITER Vacuum Handbook. The geometrical context for this procurement is shown on Figure 3 and the physical boundary of the procurement is delineated in red. VV Sector IVV Port Stub Extension IVV Port Extension Cryostat cylinder Port Cell Building Weld done by the Supplier W2 W1 Intermediate Bellow covered in Lot #1 Figure 3: IVV Port components and interfaces (Poloidal cross section view) Typical thickness of the IVV Port Extension is 20mm. 5

3. Scope of work A Technical Specification will be issued for each lot. The outline of contract implementation can be summarized as follows: Final Design Development and Prototype Testing Manufacture and Factory Acceptance Testing Transport and Delivery to the ITER Site Support to Installation, Site Acceptance Testing and Commissioning The schematic below provides more information related to each lot: The Lot 1 is composed of 4 phases: - Phase 1: Design finalization of bellows - Phase 2: Prototype and qualification of bellows - Phase 3: Penetration design finalization (Option to be released after closure of phase 2 and integrability check of bellows in environment) - Phase 4: Manufacturing, acceptance test and delivery of penetration (Option to be released after closure of phase 3 and validation of design) The Lot 2 is composed of 2 phases: - Phase 1: Design finalization of IVV port extension - Phase 2: Manufacturing, acceptance test and delivery of penetration (Option to be released after closure of phase 1 and validation of design) 4. Time Schedule The contract shall start in December 2018 / January 2019 and its estimated duration is 5 years. 6

The tentative timetables is shown below, nevertheless the Supplier shall produce a Detailed Schedule showing all phases of the Contract and showing how the overall IO Schedule will be complied with. Call for Nomination June 2018 Prequalification August 2018 Tender submission date September 2018 Award date of contract December 2018 / January 2019 Contract start date February - March 2019 Contract end March 2023 This is given for information only and may be subjected to change. 5. Experience The Contractor and its personnel shall demonstrate a technical and engineering capability and relevant experience in: Using codes and standards applicable for bellows (EJMA, EN14917 ) Codes and standard applicable for support Vacuum Vessel (RCC-MR) and Cryostat (ASME) and qualification for designing and manufacturing nuclear components. Design, structural integrity analysis, fabrication, examination, quality control and testing of the IVV Port Extension in line with RCC-MR ed.2007. Manufacture and testing of multiply bellows including advanced forming and welding techniques. High technology Prototyping, qualification and testing of multi ply bellows and safety important components. Integration, installation and commissioning of large assemblies with multiply bellows in complex plant environment Development of the mechanical components for Remote Handling (RH) maintenance. The Contractor is expected to provide direct evidence of this work in their submissions. Previous experience and knowledge of the ITER project is not required, however, the companies need to be self-sufficient in seeking out detailed information in order to accomplish the contract successfully. In addition, during the tendering process the Supplier will have to provide evidence of: 7

QA system: The Tenderer shall have and maintain a valid ISO 9000 certification and shall have the duty to verify and document the equivalent quality level of all its subcontractors and consultants. Professional Software: The Tenderer shall provide a list of the professional software available and used, e.g. for structural (static, dynamic, seismic), thermal and thermomechanical analyses, electromagnetic analyses (such as ITER conventional multiphysic analysis software ANSYS), CAD software (such as ITER conventional CAD software CATIA V5 and/or V6, if it is applicable) etc. 6. Nuclear and Quality Requirements The ITER Organization is the nuclear operator of the ITER nuclear fusion facility (INB 174, ( Installation Nuclée de Base ) under French nuclear law. For Protection Important Components (Safety Important Class) (PIC/SIC), the French Nuclear Regulation must be observed, in application of the Article 14 of the ITER Agreement. Therefore the Contractor and its subcontractors must comply with the following: The Order 7th February 2012 applies to all the PIC components and Protection Important Activity (PIA) The compliance with the INB-order must be demonstrated in the chain of external contractors In application of article II.2.5.4 of the Order 7th February 2012, contracted activities for supervision purposes are also subject to a surveillance done by the Nuclear Operator. For the Protection Important Components, structures and systems of the nuclear facility, the Contractor shall ensure that a specific management system has to be implemented by any Contractor and its subcontractor working on Protection Important Activities, following the requirements of the Order 7th February 2012 and ITER Provisions for Implementation of the Generic Safety Requirements by the External Interveners. The Contractor will have to provide an evidence of implemented Quality Assurance System required for design, manufacturing, testing, qualification and shipping of nuclear components. 8

7. Candidature Participation is open to all legal persons participating either individually or in a grouping (consortium) which is established in an ITER Member State. A legal person cannot participate individually or as a consortium partner in more than one application or tender of the same contract. A consortium may be a permanent, legally-established grouping or a grouping, which has been constituted informally for a specific tender procedure. All members of a consortium (i.e. the leader and all other members) are jointly and severally liable to the ITER Organization. The consortium grouping shall be presented at the Pre-Qualification stage. The Candidate s composition cannot be modified without the approval of the ITER Organization after the Pre-Qualification. Legal entities belonging to the same legal group are allowed to participate separately if they are able to demonstrate independent technical and financial capacities. Candidates (individual or consortium) must comply with the selection criteria. The IO reserves the right to disregard duplicated reference projects and may exclude such legal entities from the Pre-Qualification procedure. 8. Reference Further information on the ITER Organization procurement can be found at: http://www.iter.org/org/team/adm/proc/overview 9