LHC. Construction Understanding first the commissioning. Prospects for

Similar documents
The LHC Collider. STOA lecture, Brussels, 27 th November 2012 Steve Myers Director of Accelerators and Technology, CERN

LHC Commissioning and First Operation

LHC status & 2009/2010 operations. Mike Lamont

Large Hadron Collider at CERN

Status of the LHC Machine

LHC operation in 2015 and prospects for the future

The LHC: the energy, cooling, and operation. Susmita Jyotishmati

LHC accelerator status and prospects. Frédérick Bordry Higgs Hunting nd September Paris

2008 JINST 3 S Main machine layout and performance. Chapter Performance goals

Tools of Particle Physics I Accelerators

LHC Commissioning in 2008

LHC Status and CERN s future plans. Lyn Evans

LHC Commissioning The good, the bad the ugly

Status and Outlook of the LHC

Beam. RF antenna. RF cable

Practical Lattice Design

LHC commissioning. 22nd June Mike Lamont LHC commissioning - CMS 1

STATUS OF LHC COMMISSIONING

The LHC. Part 1. Corsi di Dottorato Corso di Fisica delle Alte Energie Maggio 2014 Per Grafstrom CERN and University of Bologna

The LHC accelerator: Technology and First Commissioning

BEAM TESTS OF THE LHC TRANSVERSE FEEDBACK SYSTEM

LHC Collimation and Loss Locations

Transverse dynamics Selected topics. Erik Adli, University of Oslo, August 2016, v2.21

The Large Hadron Collider Lyndon Evans CERN

The Luminosity Upgrade at RHIC. G. Robert-Demolaize, Brookhaven National Laboratory

SPPC Study and R&D Planning. Jingyu Tang for the SPPC study group IAS Program for High Energy Physics January 18-21, 2016, HKUST

Signaling the Arrival of the LHC Era December Current Status of the LHC. Albert De Roeck CERN Switzerland

Overview of LHC Accelerator

Gianluigi Arduini CERN - Beams Dept. - Accelerator & Beam Physics Group

Much of this material comes from lectures given by Philippe Lebrun (head of CERN's Accelerator Technology Department), at SUSSP, Aug

Plans for 2016 and Run 2

The CERN Accelerator School holds courses in all of the member states of CERN. 2013, Erice, Italy

LHC Run 2: Results and Challenges. Roderik Bruce on behalf of the CERN teams

First propositions of a lattice for the future upgrade of SOLEIL. A. Nadji On behalf of the Accelerators and Engineering Division

LHC Luminosity and Energy Upgrade

LHC Beam Operations: Past, Present and Future

Beam Dynamics. D. Brandt, CERN. CAS Bruges June 2009 Beam Dynamics D. Brandt 1

The Beam Instrumentation and Diagnostic Challenges for LHC Operation at High Energy

Longitudinal Dynamics

III. CesrTA Configuration and Optics for Ultra-Low Emittance David Rice Cornell Laboratory for Accelerator-Based Sciences and Education

Engines of Discovery

LIS section meeting. PS2 design status. Y. Papaphilippou. April 30 th, 2007

TUNE SPREAD STUDIES AT INJECTION ENERGIES FOR THE CERN PROTON SYNCHROTRON BOOSTER

Putting it all together

The TESLA Dogbone Damping Ring

Machine Protection Basics of Accelerator Science and Technology at CERN

SLS at the Paul Scherrer Institute (PSI), Villigen, Switzerland

Accelerators. There are some accelerators around the world Nearly all are for industrial (20 000) or clinical use (10 000)

D. Brandt, CERN. CAS Frascati 2008 Accelerators for Newcomers D. Brandt 1

Accelerators. Lecture V. Oliver Brüning. school/lecture5

Particle physics experiments

International Scientific Spring 2010, March 1-6, 1. R. Garoby. slhc

OTHER MEANS TO INCREASE THE SPS 25 ns PERFORMANCE TRANSVERSE PLANE

Conceptual design of an accumulator ring for the Diamond II upgrade

LHC upgrade based on a high intensity high energy injector chain

FY04 Luminosity Plan. SAG Meeting September 22, 2003 Dave McGinnis

Accelerator. Physics of PEP-I1. Lecture #7. March 13,1998. Dr. John Seeman

Main aim: Preparation for high bunch intensity operation with β*=3.5 m and crossing angle (-100 µrad in IR1 and +100 µrad in IR5)

Beam losses versus BLM locations at the LHC

Low Energy RHIC electron Cooling (LEReC)

Machine Protection Systems

(a) (b) Fig. 1 - The LEP/LHC tunnel map and (b) the CERN accelerator system.

Challenges and Plans for the Proton Injectors *

Operational Experience with HERA

THE ALIGNMENT OF THE LHC DURING THE SHUT-DOWN D. Missiaen, CERN, Geneva, Switzerland. Fiducialisation

Beam Loss Monitors, Specification

Particle Physics Columbia Science Honors Program

RHIC - the high luminosity hadron collider

Compressor Lattice Design for SPL Beam

Plans for ions in the injector complex D.Manglunki with the help of I-LHC and LIU-PT teams

A Project to convert TLS Booster to hadron accelerator 1. Basic design. 2. The injection systems:

Superconducting Magnets for Future Electron-Ion Collider. Yuhong Zhang Thomas Jefferson National Accelerator Facility, USA

LHC RunII Commissioning and HL-LHC Status

Thanks to all Contributors

Lattice Design and Performance for PEP-X Light Source

Introduction to accelerators for teachers (Korean program) Mariusz Sapiński CERN, Beams Department August 9 th, 2012

8 lectures on accelerator physics

Injection: Hadron Beams

Accelerators for Beginners and the CERN Complex

MACHINE PROTECTION ISSUES AND STRATEGIES FOR THE LHC

ACCELERATOR PHYSICS AND TECHNOLOGY OF THE LHC

RF System Calibration Using Beam Orbits at LEP

Lattice Design for the Taiwan Photon Source (TPS) at NSRRC

The Booster has three magnet systems for extraction: Kicker Ke, comprising two identical magnets and power supplies Septum Se

PBL (Problem-Based Learning) scenario for Accelerator Physics Mats Lindroos and E. Métral (CERN, Switzerland) Lund University, Sweden, March 19-23,

COMBINER RING LATTICE

Bernhard Holzer, CERN-LHC

Physics 610. Adv Particle Physics. April 7, 2014

Run2 Problem List (Bold-faced items are those the BP Department can work on) October 4, 2002

Commissioning of the LHC collimation system S. Redaelli, R. Assmann, C. Bracco, M. Jonker and G. Robert-Demolaize CERN, AB department

Optimization of the SIS100 Lattice and a Dedicated Collimation System for Ionisation Losses

SMR/ Summer School on Particle Physics June LHC Accelerators and Experiments (part I) Marzio Nessi CERN, Switzerland

OVERVIEW OF THE LHEC DESIGN STUDY AT CERN

An Introduction to Particle Accelerators. v short

Daniel Wollmann, CERN

Accelerator Design and Construction Progress of TPS Project

Overview of Acceleration

3. Particle accelerators

Linac4: From Initial Design to Final Commissioning

PUBLICATION. Consolidated EIR design baseline: Milestone M3.6

Transcription:

LHC Overview The problem what and is fixing LHC it? Construction Understanding first the commissioning problem Making Beam sure commissioning there no Titanic II Prospects for 2009 2010 LHC is a superconducting proton synchrotron based collider installed in the 27km circumference LEP underground tunnel at CERN 2 1

LHC basic design parameters Luminosity (defines rate of doing physics) 10 34 cm -2 s -1 Need lots of particles to achieve this rate Hence proton proton machine (unlike Tevatron or SppbarS) Separate bending fields and vacuum chambers in the arcs 3 LHC basic design parameters Energy 7TeV per beam Dipole field 8.33Tesla Superconducting technology needed to get such high fields Tunnel cross section (4m) excludes 2 separate rings (unlike RHIC) Hence twin aperture magnets in the arcs 4 2

LHC dipoles (1232 of them) operating at 1.9K 7TeV 8.33T 11850A 7MJ 5 Cooled by liquid helium, distributed around 27km 6 3

Schematic of the LHC RF system Beam extraction collimators 8 distinct sectors for cryogenics and powering collimators injection beam 1 injection beam 2 2.9km transfer line 7 2.7km transfer line The arcs 23 regular FODO cells in each arc 106.9m long, made from two 53.45m long half-cells Half cell 3 15m cryodipole magnets, each with spool-piece correctors 1 Short Straight Section (~6m long) Quadrupole and lattice corrector magnets 4

Dispersion suppressors Standard arc cells with missing dipole magnet and individually powered quadrupoles Threefold function adapt the LHC reference orbit to the geometry of the LEP tunnel cancel the horizontal dispersion arising in the arc and generated by the separation / recombination dipole magnets and the crossing angle bumps help in matching the insertion optics to the periodic solution of the arc Insertion regions (points 1, 2, 5, 8) 10 5

Optics in the arc cell Optics in the high luminosity insertions IP 6

LHC arc 13 Injection systems (points 2 and 8) 14 7

RF systems (point 4) 400MHz 200MHz 2 Modules per beam 4 Cavities per module 15 Beam extraction (point 6) Beam Dump Block H-V kicker for painting the beam Septum magnet deflecting the extracted beam 15 kicker magnets 16 8

Collimators (points 3 and 7) 56.0 mm 1 mm 17 Triplets (points 1, 2, 5, 8) 18 9

Experiments (points 1, 2, 5, 8) 19 Luminosity 2 2 N kb f N kb f L F F * 4 4 x y n n Thus, to achieve high luminosity, all one has to do is make (lots of) high population bunches of low emittance to collide at high frequency at locations where the beam optics provides as low values of the amplitude functions as possible. PDG 2005, chapter 25 Nearly all the parameters are variable Number of particles per bunch Number of bunches per beam k b Relativistic factor (E/m 0 ) Normalised emittance n Beta function at the IP * Crossing angle factor F Full crossing angle c Bunch length z Transverse beam size at the IP * F 1/ 1 c z * 2 2 20 10

LHC nominal performance Nominal settings Beam energy (TeV) 7.0 Number of particles per bunch 1.15 10 11 Number of bunches per beam 2808 Crossing angle ( rad) 285 Norm transverse emittance ( m rad) 3.75 Bunch length (cm) 7.55 Beta function at IP 1, 2, 5, 8 (m) 0.55,10,0.55,10 Derived parameters Luminosity in IP 1 & 5 (cm -2 s -1 ) 10 34 Luminosity in IP 2 & 8 (cm -2 s -1 )* ~5 10 32 Transverse beam size at IP 1 & 5 ( m) 16.7 Transverse beam size at IP 2 & 8 ( m) 70.9 Stored energy per beam (MJ) 362 * Luminosity in IP 2 and 8 optimized as needed 6/8/2011 21 So what is LHC? Big Cold Complex Very powerful Nimitz class aircraft carrier (90 000 tons) at battle-speed of 30 Knots Energy = ½ mv 2 ~ 10GJ Nominal performance Energy stored in the magnets Energy stored in each beam 10 GJ 362 MJ Copper Melting point 1356 K Specific heat capacity 386 J kg -1 K -1 Latent heat of fusion 205000 J kg -1 So to heat and melt 1kg takes (1354*386+205000) J --- or --- 362MJ would heat and melt half a tonne of copper 22 11

CERN accelerator complex 1976 1972 LHC beam route 1959 LINAC2 BOOSTER (PSB) PS SPS 6/8/2011 23 Injector chain The present accelerators are getting old (PS is 50 years old ) and they operate far beyond their initial design parameters Luminosity depends directly upon beam brightness N/ * Brightness is limited by space charge at low energy in the injectors 1 N L * k X, Y b Q : number of X, Y N X, Y : normalized transverse emittances R : mean radius of the accelerator :classical R 2 N : number of protons/bunch b : normalized transverse emittances SC X, Y N : number of protons/bunch b b b N k b b bunches per ring relativist ic parameters Need to increase the injection energy in the injection synchrotrons 6/8/2011 24 12

Output energy 6/8/2011 Strategy for injector chain upgrade Replace Linac 2 with Linac 4 Consolidate all machines Upgrade PSB energy to 2 GeV (PSB+) 50 MeV Linac2 Linac4 160 MeV 1.4 GeV PSB PSB+ 2 GeV 26 GeV PS 450 GeV SPS 7 TeV LHC 6/8/2011 25 LHC Overview The problem what and is fixing LHC it? Construction Understanding first the commissioning problem Making Beam sure commissioning there no Titanic II Prospects for 2009 2010 13

Sector 78 commissioning Sector 45 commissioning Definitive cooldown and commissioning for 5TeV Beam Breakdown 6/8/2011 LHC and LEP timeline Same tunnel! 1982 : First studies for the LHC project 1984 : Start of LEP construction 1989 : Start of LEP operation 1994 : Approval of the LHC by the CERN Council 1995 : Start of LHC experiment civil engineering 1996 : Final decision to start the LHC construction (7TeV machine) 2000 : End of LEP operation 2002 : Start of the LHC construction 2006 : Start of hardware commissioning 2007 : End of installation and start of cool-down 2008 : First beam commissioning 27 Construction and commissioning 2002-2008 Tunnel activity determined by LEP Helium Distribution Line Triplet Cryo 2002 2003 2004 2005 2006 2007 2008 Magnet tests PC SC tests Required magnet storage Allowed magnet sorting Magnet installation Magnet interconnects While not forgetting several major accelerator systems Injection systems Extraction systems RF systems Collimation systems Vacuum systems Beam instrumentation systems Machine protection systems Controls Experiments 28 14

Definitive cool down 2008 Sector by sector Quickest took 6 weeks 29 Commissioning of the electrical circuits for 5TeV Sector 12 Sector 23 Sector 34 Sector 45 Per sector : 200 circuits ~ 1500 tests to be made Why 5TeV? Magnet detraining seen in sector 56 Sector 56 Sector 67 Sector 78 Sector 81 30 15

Beam tests October 2004 September August 08-10 22-24 5-7 October 2007 31 Incident of September 19 th 2008 During a few days period without beam while recovering from transformer failure Making the last step of the dipole circuit in sector 34, to 9.3kA Sector 56 Sector 78 Sector 81 Sector 23 Sector 67 Sector 12 Sector 45 Sector 34 At 8.7kA, development of resistive zone in the dipole bus bar splice between Q24 R3 and the neighbouring dipole Later estimated (from cryogenic data on heat deposition) to be 220nΩ Electrical arc developed which punctured the helium enclosure, allowing helium release into the insulating vacuum Large pressure wave travelled along the accelerator in both directions 16

Development of resistive zone in dipole bus bar splice 33 Arc and helium released into the insulating vacuum Liquid to Gas Expansion Factor 1000 34 17

Q D D D Large pressure wave travelled along the accelerator Self actuating relief valves opened but could not handle all Cold-mass Vacuum vessel Line E Cold support post Warm Jack Compensator/Bellows Vacuum barrier PT QV QV SV (DN90) QV SV (DN90) QV QV Q D D D Q D D D Q D D D Q D D D Q Q23 50m Cold-mass Vacuum vessel Line E Cold support post Warm Jack Compensator/Bellows Vacuum barrier 100m 50m Q24 Q25 Q26 Q27 Large forces exerted on vacuum barriers located every 2 cells Connections to cryogenic line also affected in several places Beam vacuum system also affected Multi ka electrical arc 18

Consequences Magnets displaced Consequences Magnets displaced 19

Beam vacuum Beam Screen (BS) : The red color is characteristic of a clean copper surface BS with some contamination by super-isolation (MLI multi layer insulation) BS with soot contamination. The grey color varies depending on the thickness of the soot, from grey to dark. LSS3 LSS4 Repair 100m Had to treat to lesser or greater degree all magnets Q19 to Q33 as shown 53 had to be brought to the surface (39 dipoles and 14 quads) Replaced with spare or refitted, then retested and reinstalled Huge enterprise; last magnet back in mid April 2009 Not forgetting cleaning the beam pipes Then have to align, make all interconnections, cool down, power test 20

Magnet removal Special tooling needed for safe transport of damaged magnets Underground logistics tricky at best Surface activities 21

Preventing recurrence Sector 34 repair Restart Q4 2008 Q1 2009 Q2 2009 Q3 2009 Q4 2009 Electrical measurements everywhere at cold (measuring nω) Had to warm up sectors 12 56 67 Electrical measurements everywhere at warm or at 80K (measuring µω) Had to warm up sector 45 Major new protection system based on electrical measurements Pressure relief valves installed everywhere Reinforcement of floor anchors everywhere Superconducting splices limit operation to 5 TeV Copper stabilizers limit operation to 3.5 TeV Q4 2008 Q1 2009 Q2 2009 Q3 2009 Q4 2009 12 Cold Cold Warm Warm Warm Cold Cold 23 < 100K < 100K < 100K Cold Cold 80K Cold Cold 34 Warm Warm Warm Warm Cold Cold 45 < 100K < 100K < 100K Warm Warm Cold Cold 56 Cold Cold Warm Warm Warm Cold Cold 67 Cold Cold Warm Warm Warm Cold Cold 78 Cold < 100K < 100K 80K 80K Cold Cold 81 Cold < 100K < 100K 80K 80K Cold Cold LHC Overview The problem what and is fixing LHC it? Construction Understanding first the commissioning problem Making Beam sure commissioning there no Titanic II Prospects for 2009 2010 22

Evolution of target energy When Why 7 TeV 12 ka 2002-2007 Design 5 TeV Summer 2008 Detraining 9 ka Late 2008 Splices 3.5 TeV 6 ka Summer 2009 Stabilizers 450 GeV 1.18 TeV 2 ka October 2009 nqps 6/8/2011 45 The way back Train magnets Should be easy to get to 6TeV 6.5 TeV should be in reach 7 TeV will take time 7 TeV 6.5 TeV When 2016? 2015 What Training Stabilizers Fix stabilizers for 12kA Complete pressure relief system Fix connectors Commission nqps system Commission circuits to 6kA 3.5 TeV 6 ka 2012 2011 2010 nqps 450 GeV 1.18 TeV 2 ka 2009 6/8/2011 46 23

Commissioning strategy At whatever energy Correct everything we can with safe beams Then establish references Then set up protection devices (injection, collimators, beam dump) Then increase intensity incrementally Low bunch currents, increase k b Increase bunch current Higher bunch current, low k b, same total current Higher bunch currents, increase k b Once k b > 50 or so, need bunch trains At each stage, re-qualify machine protection systems Some numbers What Limit Comment Pilot Single bunch of 5 10 9 protons Quench limit Safe beam 10 12 protons at 450 GeV Damage limit Energy Safe beam 0.45 1.00E+12 1.18 1.94E+11 3.5 3.06E+10 Scales with 1/E 1.7 6/8/2011 7 9.41E+09 47 The operational cycle Squeeze Collisions Ramp Rampdown Injection Injection Ramp Squeeze Collisions Rampdown Many schemes Injection channel Dynamic effects Feedbacks Optics Collimators Beam steering Beam-beam All through the cycle Beam dump Collimations system Protection devices Ramp rates Reproducibility 6/8/2011 48 24

Ions Ions 6/8/2011 Early beam operation 2009 2010 2011 2012 Repair of Sector 34 1.18 nqps TeV 6kA 3.5 TeV I safe < I < 0.2 I nom β* > 2 m 3.5 TeV < 0.5 I nom β* 1.5 m 3.5 TeV < I nom β* 1.5 m No Beam B Beam Beam Beam 2009 Energy limited to 1.18 TeV 2010 Energy limited to 3.5 TeV Intensity carefully increased to collimation limit β* not too low to provide margins Target luminosity 10 32 cm -2 s -1 2011 Energy limited to 3.5 TeV Push the intensity to 50% nominal β* pushed as low as possible Target luminosity 10 33 cm -2 s -1 Target integrated luminosity > 1 fb -1 40% efficiency for physics 10 6 seconds collisions per month 10 6 seconds @ <L> of 10 33 cm -2 s -1 1 fb -1 2009 450 GeV 1.18 TeV 2 ka AIMS 450 GeV collisions 10 6 events Ramp to 1.18 TeV Collisions at 1.18 TeV Do this with SAFE BEAMS 10 12 at 450 GeV 2 10 11 at 1.18 TeV LIMITS 2 on 2 with 5 10 10 per bunch at 1.18 TeV 4 on 4 with 2 10 10 per bunch at 1.18 TeV 25

2010 Hardware commissioning for 3.5 TeV Ramp beams to 3.5 TeV Machine protection systems qualified Colliding safe stable beams (2 on 2 pilots) Squeeze to 2m Low bunch currents, increase k b Machine protection systems qualified 13 on 13 low intensity bunches at 2m High bunch currents, low k b Increase k b Machine protection systems qualified 50 on 50 high intensity bunches at 3.5m Bunch trains on crossing angles, 150 ns Increase k b Machine protection systems qualified 368 on 368 high intensity bunches at 3.5m 20 MJ stored energy per beam 6/8/2011 51 2010 - Beam transfer and Injection 26

2010 - Injection oscillations OFF ON Transverse damper - Crucial device to keep emittance growth under control! 6/8/2011 53 2010 - Ramp - Tunes Tune excursions during the ramp Losses on resonances 6/8/2011 54 27

2010 - Ramp Tune feedback Feedback employed early. Reconstructed tune excursions 6/8/2011 55 2010 - Ramp - Orbit feedback RMS orbit change B1 (during ramp) The orbits are now stable in ramp (and squeeze) to 50 m rms Previously ~ 300-400 m >> Better collimation efficiency. >> Better protection (tighter interlocks). RMS orbit change B2 (during ramp) 6/8/2011 5656 28

2010 - Squeeze in points 1 and 5 6/8/2011 57 2010 - Beta-beat B1 on flat top (10/11 m) - reproducible 6/8/2011 58 29

2010 - Beta-beat B1 at 3.5 m - reproducible 6/8/2011 59 2010 - Collimation system commissioning Collimation system is for beam cleaning and passive protection Each collimator has to be positioned using beam based alignment 6/8/2011 60 30

Momentum Cleaning Dump Protection Col. 6/8/2011 2010 - Collimation system efficiency Provoked vertical beam loss on beam 1, 2m optics IR2 IR5 IR8 IR1 6/8/2011 61 2010 - Zoom around betatron cleaning factor 4,000 factor 1,000 factor 600,000 IR8 OK for stable beams from collimation 6/8/2011 62 31

2010 - Beam dump IR6 H Beam2, extracted IR6 H Beam2, circulating 6/8/2011 63 2010 - Beam dump protection systems Protection devices to catch beam in abort gap 6/8/2011 64 32

2010 - Beam dump protection systems efficiency Provoked asynchronous beam dump 1e-3 leakage to tertiary collimators in IR s OK for stable beams from beam dump 6/8/2011 65 2010 - Collisions 6/8/2011 66 33

2010 - Collisions emittance blow up Machine parameters very well controlled! calculated with measured bunch intensity, nominal = 3.75 m and * =3.5m CALCULATED ATLAS CMS Emittance growth 6/8/2011 67 2010 - Collisions beam-beam effects Losses only in first 4 bunches, from bucket 1 onwards 6/8/2011 68 34

2010 - Collisions behaviour of different beams / bunches 6/8/2011 69 LHC status 2010 - Unwanted excitation - source still unknown Tunes External excitation 6/8/2011 70 35

Progress in 2010 with nominal intensity bunches Date Bunches/beam Colliding bunches Luminosity cm -2 s -1 15th November 121 113 2.88e25 9th November 17 16 3.5e24 4th November LHC switched to heavy ions (fully stripped lead) 20 MJ 25th October 368 348 2.07e32 16th October 312 295 1.35e32 14th October 248 233 1e32 8th October 248 233 8.8e31 4th October 204 186 7e31 29th September 152 140 5e31 25th September 104 93 3.5e31 23rd September 56 47 2e31 22nd September 24 16 4.6e30 1st - 22nd September Bunch train commissioning, 150 ns bunch spacing 29th August 50 35 1e31 6/8/2011 71 Comments on 2010 Machine commissioned with beam under strict conditions Machine parameters under control Machine protection paramount and dictated intensity Low bunch currents, increase k b Increase bunch current Higher bunch current, low k b, same total current Higher bunch currents, increase k b Big surprise that we could easily get to nominal N Nominal bunch intensities thereafter, just increasing k b Intensity related effects starting to show up UFOs Electron cloud SEUs 6/8/2011 72 36

2011 Re-commission machine for 3.5TeV Squeeze to 1.5m at 3.5 TeV Get back to 2010 performance levels 200 on 200 high intensity bunches, 75 ns Prepare machine for high intensity (scrub) Increase number of bunches Operate machine with higher intensity 1000 on 1000 high intensity bunches, 50 ns Increase number of bunches to 1400 Operate machine with higher intensity Try not to break anything! 1400 on 1400 high intensity bunches, 50 ns 100 MJ stored energy per beam 6/8/2011 73 Progress in 2011 (to end May) Date Bunches/beam Colliding bunches (Atlas & CMS) Luminosity cm -2 s -1 29th May 1092 1042 1.2e33 22nd May 912 873 1.1e33 1st May 768 700 8.4e32 27th April 624 598 6.7e32 21st April 480 424 4.67e32 16th April 336 322 3.57e32 14th April 220 214 2.28e32 24-27th March 75 MJ 1.38 TeV run (followed by technical stop and scrubbing) 22nd March 200 194 2.5e32 6/8/2011 74 37

Observation No battle plan ever survives contact with the enemy Original plan was Equidistant bunches, moderate bunch intensity 75 ns, moderate bunch intensity 25ns, moderate bunch intensity 25ns, nominal bunch intensity What actually happened was Equidistant bunches, moderate bunch intensity Equidistant bunches, nominal bunch intensity 150 ns, nominal bunch intensity 75 ns, nominal bunch intensity 50 ns, nominal bunch intensity 25ns, nominal bunch intensity (still to do) 6/8/2011 75 Summary After a long and painful birth, LHC came online in 2008 Major incident of September 2008 took a year to fix Lessons learned from this impacted on the commissioning At start-up II (2009/10), fantastic set of tools at our disposal Allowed fast commissioning with beam Machine protection (hardware and beam) paramount Necessarily slowed down the progress Fantastic progress through 2010 5 orders of magnitude increase in instantaneous luminosity to 2 10 32 50 pb -1 delivered at com 7 TeV Similarly impressive progress so far through 2011 At 1.2 10 33 already, and integrated luminosity looking good (> 0.5 fb -1 ) Expect to deliver 1-3 fb -1 before we switch to ions in November Let s hope that there is something there to find! 6/8/2011 76 38

Future schools Year Special topic (May, June) Accelerator physics (September) 2011 High Power Hadron Machines, Bilbao, ES Level II, Chios, GR 2012 Ions Sources, Senec, SK Level I, Granada, ES 2013 Applications of Superconductivity, Erice, IT Level II, Norway, Finland 2014 Power Convertors, CH Level I, Hungary, Portugal 2015 Vacuum 2016 Medical applications (or do as a JAS in Russia?) 6/8/2011 R. Bailey, CAS 77 39