The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

Similar documents
The World Bank Bangladesh Modern Food Storage Facilities Project (P120583)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank BiH Floods Emergency Recovery Project (P151157)

The World Bank Indonesia: Geothermal Energy Upstream Development Project (P155047)

The World Bank Earthquake Housing Reconstruction Project (P155969)

Public Disclosure Copy

The World Bank Sri Lanka Agriculture Sector Modernization Project (P156019)

The World Bank. Kenya: Off-grid Solar Access Project for Underserved Counties (P160009) Key Dates. Project Development Objectives.

Urban Water Supply Project (P156739)

Public Disclosure Copy

Public Disclosure Copy. AFCC2/RI-The Eastern Electricity Highway Project under the First Phase of the Eastern Africa Power

The World Bank Guilin Integrated Environment Management (P133017)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Local and Regional Competitiveness Project (P154263)

Public Disclosure Copy. Implementation Status & Results Report KH - Livelihood Enhancement and Association of the Poor Project (LEAP) (P153591)

Public Disclosure Copy

The World Bank Earthquake Housing Reconstruction Project (P155969)

Public Disclosure Copy. Implementation Status & Results Report Pacific Islands Regional Oceanscape Program - Solomon Islands (P151777)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Georgia National Innovation Ecosystem (GENIE) Project (P152441)

The World Bank Zambia Water Resources Development Project (P114949)

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965)

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report UGANDA North Eastern Road-corridor Asset Management Project (NERAMP) (P125590)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Girls Education and Womens Empowerment and Livelihood Project (P151451)

The World Bank Zambia Water Resources Development Project (P114949)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Ethiopia: National Quality Infrastructure Development Project (P160279)

The World Bank Uganda Energy for Rural Transformation III (P133312)

Public Disclosure Copy. Implementation Status & Results Report AGRICULTURAL COMPETITIVENESS IMPROVEMENT PROJECT (P122812)

SUSTAINABLE CITIES (P128605)

The World Bank Greater Maputo Water Supply Expansion Project (P125120)

The World Bank Regional Infrastructure Development Fund (P154947)

Public Disclosure Copy. Implementation Status & Results Report Emergency Agricultural Livelihoods and Climate Resilience Project (P166328)

Public Disclosure Copy

The World Bank China: Qinghai Xining Urban Transport Project (P127867)

EC Ibarra Transport Infrastructure Improvement Project (P147280)

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

Public Disclosure Copy

The World Bank Mali Reconstruction and Economic Recovery (P144442)

Sierra Leone Energy Access Project - Sierra Leone Infrastructure Development Fund (P126180)

The World Bank Ethiopia Geothermal Sector Development Project (P133613)

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy. Implementation Status & Results Report Small Town Water Supply and Urban Septage Management Project (P156738)

Public Disclosure Copy

The World Bank Decentralized Community Driven Services Project (P117764)

Public Disclosure Copy

Public Disclosure Copy. Implementation Status & Results Report Strengthening Institutional Capacity for Government Effectiveness Project (P149176)

The World Bank Bangladesh Weather and Climate Services Regional Project (P150220)

Public Disclosure Copy. Implementation Status & Results Report DJ-Rural Community Development and Water Mobilization Project (PRODERMO) (P117355)

The World Bank Local and Regional Competitiveness Project (P154263)

The World Bank Third Northern Uganda Social Action Fund (NUSAF 3) (P149965)

West Bank and Gaza: Finance for Jobs (P151089)

SÃO PAULO METRO LINE 4 (PHASE 2) (P106390)

Public Disclosure Copy

Relaunching Agriculture: Strengthening Agriculture Public Services II Project (GAFSP - IDA) (P126744)

The World Bank Cusco Regional Development (P117318)

The World Bank Integrated Forest Ecosystem Management (P151102)

PAMSIMAS Support Trust Fund (P116236)

Public Disclosure Copy. Implementation Status & Results Report Cambodia Global Partnership for Education Second Education Support Project (P144715)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

The World Bank Can Tho Urban Development and Resilience (P152851)

NI - INTEGRATED PUBLIC PROVISION OF HEALTH CARE SERVICES (P164452)

The World Bank Transport Connectivity and Asset Management Project (P132833)

The World Bank Ecuador - Sustainable Family Farming Modernization Project (P151963)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

SUSTAINABLE CITIES (P128605)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

Name Previous Rating Current Rating

The World Bank Mali Reconstruction and Economic Recovery (P144442)

The World Bank Second Irrigation and Drainage Improvement Project (P086592)

The World Bank Pakistan: Third Punjab Education Sector Project (P154524)

Public Disclosure Copy

Public Disclosure Copy

Public Disclosure Copy

The World Bank Senegal Tourism and Enterprise Development Project (P146469)

The World Bank Swaziland Health, HIV/AIDS and TB Project (P110156)

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

The World Bank OECS Regional Tourism Competitiveness (P152117)

Public Disclosure Copy

Public Disclosure Copy

Transcription:

SOUTH ASIA Bangladesh Agriculture Global Practice IBRD/IDA Investment Project Financing FY 2014 Seq No: 5 ARCHIVED on 22-Apr-2016 ISR23210 Implementing Agencies: Directorate General, Ministry of Food Key Dates Key Project Dates Bank Approval Date:30-Dec-2013 Planned Mid Term Review Date:31-Mar-2017 Original Closing Date:30-Jun-2020 Effectiveness Date:27-May-2014 Actual Mid-Term Review Date:-- Revised Closing Date:30-Jun-2020 Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall Project development objective is to increase the grain reserve available to households to meet their post-disaster needs and improve the efficiency of grain storage management. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A Construction of Modern Grain Storage Silo Facilities:(Cost $195.00 M) Component B Support for Food and Market Planning and Monitoring Program:(Cost $25.00 M) Component C - Project management, Construction Supervision, Technical Assistance, Training and Strategic Studies:(Cost $20.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial 4/22/2016 Page 1 of 8

Implementation Status and Key Decisions Implementation status has been assessed based on findings of regular implementation monitoring meetings between the Bank Task Team and the Government Team. The project is in early implementation. Overall, the project implementation is progressing reasonably well and additional disbursement amount of about US$8.180 million is expected by June 30, 2016. Procurement processes critical to the implementation and disbursement performance are completed, in particular for consulting services (e.g. silo design and construction supervision; development of a food policy research program; distribution of domestic silo and beneficiary training) and works (production of household silos). In fact, the Design and Supervision Consultants Contract has been signed and the consultant M/S Gerico of France has started mission in February 01, 2016. Two other major contracts are expected to be signed in April 2016: (i) Consultants contract for Food Policy Research; and (ii) Contract for service provider for distribution and training of household silos. Except the sites at Barisal and Dhaka, the preparatory works (site development, boundary wall and site office building) required for construction of modern grain storage silo facilities at 8 sites are progressing satisfactorily and expected to be completed within the extended completion dates. The prequalification of contractors for construction of modern grain storage facilities at 8 sites is progressing satisfactorily. The Project Management Unit is expected to submit the list of prequalified contractors for Bank s comments/approval by end of April 2016. 4/22/2016 Page 2 of 8

Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Substantial Substantial Macroeconomic -- Moderate Moderate Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Substantial Substantial Institutional Capacity for Implementation and Sustainability -- High High Fiduciary -- Substantial Substantial Environment and Social -- Substantial Substantial Stakeholders -- Moderate Moderate Other -- -- -- Overall -- Substantial Substantial 4/22/2016 Page 3 of 8

Results Project Development Objective Indicators PHINDPDOTBL P1. Increased grain storage capacity in public and household storage facilities (Number, Custom) Value 0.00 0.00 0.00 446000.00 PHINDPDOTBL P2. Direct Project beneficiaries (Number (Thousand), Custom) Value 0.00 0.00 0.00 10000.00 PHINDPDOTBL Direct Female Beneficiaries (Number (Thousand), Custom Breakdown) Value 0.00 0.00 0.00 5000.00 PHINDPDOTBL P3. Reduction in grain storage and handling losses in public storage facilities (Percentage, Custom) Value 0.00 0.00 0.00 50.00 Overall Comments 4/22/2016 Page 4 of 8

Intermediate Results Indicators Households provided with safe grain storage containers (Number (Thousand), Custom) Value -- -- -- 400.00 Site development works completed (Number, Custom) Value 0.00 0.00 0.00 8.00 Date 01-Feb-2014 31-Jan-2015 07-Apr-2016 30-Jun-2020 CSDs and LSDs connected to a centralized public food storage and distribution management system (Percentage, Custom) Value 0.00 0.00 0.00 80.00 Date 01-Feb-2014 31-Jan-2015 07-Apr-2016 30-Jun-2020 Research papers completed and approved (Number, Custom) Value 0.00 0.00 0.00 15.00 4/22/2016 Page 5 of 8

Policy notes prepared under the Food Policy Reasearch Program published (Number, Custom) Value 0.00 0.00 0.00 8.00 Client days of training provided (number) (Number, Core) Value 0.00 0.00 0.00 200000.00 Date 01-Feb-2014 31-Jan-2015 07-Apr-2016 30-Jun-2020 Client days of training provided - Female (number) (Number, Core Breakdown) Value 0.00 0.00 39.00 200000.00 Date 01-Feb-2014 31-Jan-2015 07-Apr-2016 30-Jun-2020 Public food grain silo constructed and operational (Number, Custom) Value 0.00 0.00 0.00 8.00 Overall Comments Data on Financial Performance 4/22/2016 Page 6 of 8

Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P120583 IDA-52650 Effective XDR 136.60 136.60 0.00 7.56 129.04 6% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P120583 IDA-52650 Effective 30-Dec-2013 07-Apr-2014 27-May-2014 30-Jun-2020 30-Jun-2020 Cumulative Disbursements Restructuring History Level 2 Approved on 19-Aug-2015 Related Project(s) There are no related projects. 4/22/2016 Page 7 of 8

4/22/2016 Page 8 of 8