Numerical Simulation on Support of Roadway with Compound Roof and Large Cross Section

Similar documents
Study of Soft Rock Roadway Support Technique

Roadway Support Technology with Sliding Cracking Surrounding Rock under Tectonic Stress

Research on Coal Pillar Width in Roadway Driving Along Goaf Based on The Stability of Key Block

Predicting Roadway Surrounding Rock Deformation and Plastic Zone. Depth Using BP Neural Network

APPLICATION OF FLAC3D FOR SIMULATION OF THE BOREHOLE HYDRAULIC MINING OF NONG AN OIL SHALE

Numerical Analysis of the Influence of Seepage on the Displacement Law of Different Overburden Strata

Effect Of The In-Situ Stress Field On Casing Failure *

International Conference on Mechanics and Civil Engineering (ICMCE 2014)

The Mine Geostress Testing Methods and Design

Optimum Size of Coal Pillar Dimensions Serving Mechanised Caving Longwall Face in a Thick Seam

Calculation of Surrounding Rock Pressure Based on Pressure Arch Theory. Yuxiang SONG1,2, a

Experimental investigation into stress-relief characteristics with upward large height and upward mining under hard thick roof

Journal of Engineering Science and Technology Review 10 (6) (2017) Research Article

Application of a transversely isotropic brittle rock mass model in roof support design

Seismic analysis of horseshoe tunnels under dynamic loads due to earthquakes

Overburden Failure and Ground Pressure Behaviour of Longwall Top Coal Caving in Hard Multi-layered Roof

Effects of load distribution exerting on coal pillars on the stress and energy distribution of the floor strata

Effect of Displacement Loading Rate on Mechanical Properties of Sandstone

Behaviour of Blast-Induced Damaged Zone Around Underground Excavations in Hard Rock Mass Problem statement Objectives

Experimental Research on Ground Deformation of Double Close-spaced Tunnel Construction

End-wall Slope Stability Analysis of Surface Coal Mine under the Combined Open-pit Mining with Underground Mining

Haulage Drift Stability Analysis- A Sensitivity Approach

Influences of material dilatancy and pore water pressure on stability factor of shallow tunnels

Numerical Study on Effect of Longwall Mining on Stability of Main Roadway under Weak Ground Conditions in Indonesia

Further Research into Methods of Analysing the October 2000 Stability of Deep Open Pit Mines EXECUTIVE SUMMARY

Simplify the Structure of The Surface Mining and Analytic Calculation

EXAMINATION PAPER MEMORANDUM

Main controlling factors of hydrocarbon accumulation in Sujiatun oilfield of Lishu rift and its regularity in enrichment

PHYSICAL AND MECHANICAL PARAMETERS OF BOREHOLE HYDRAULIC MINING OF NONG AN OIL SHALE

Finite difference modelling in underground coal mine roadway

Characteristics of Deformation and Destruction to the Mining Roadway Floor of Three-soft Thick Coal Seam by Field Measurement

Open Access Support Technique of Horse Head in Weakly Cemented Soft Rock

THE INFLUENCE OF ROOF BOLTS LOCATION ON ITS INTERACTION WITH THE ROCK MASS.

Evaluation on source rocks and the oil-source correlation in Bayanhushu sag of Hailaer Basin

Numerical Analysis on Shaft Lining Stability during Aquifer Quick Drainage in Eastern Chinese Coal Mines

Research Article Theoretical Calculation and Analysis on the Composite Rock-Bolt Bearing Structure in Burst-Prone Ground

Mining-Caused Activation of Fault

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE COAL MINING OPTION

Stress and Wear Analysis of the Disc Cutter of Rock Tunnel Boring Machine

Investigation into strata behaviour and fractured zone height in a high-seam longwall coal mine

25th International Conference on Ground Control in Mining

Open Access Study on Creep Characteristics of Cemented Waste Rock Backfills

Natural Boundary Element Method for Stress Field in Rock Surrounding a Roadway with Weak Local Support

Successful Construction of a Complex 3D Excavation Using 2D and 3D Modelling

Calculation of periodic roof weighting interval in longwall mining using finite element method

SYLLABUS AND REFERENCES FOR THE STRATA CONTROL CERTIFICATE. METALLIFEROUS MINING OPTION Updated November 1998

ON THE FACE STABILITY OF TUNNELS IN WEAK ROCKS

Seismic stability safety evaluation of gravity dam with shear strength reduction method

Tunnel Reinforcement Optimization for Nonlinear Material

Research of concrete cracking propagation based on information entropy evolution

Experimental and numerical simulation studies of the squeezing dynamics of the UBVT system with a hole-plug device

STUDY ON THE LAW OF MINING STRESS EVOLUTION AND FAULT ACTIVATION UNDER THE INFLUENCE OF NORMAL FAULT

Research Article Failure Mechanism Analysis and Support Design for Deep Composite Soft Rock Roadway: A Case Study of the Yangcheng Coal Mine in China

In-situ Experiments on Excavation Disturbance in JNC s Geoscientific Research Programme

GROUND RESPONSE AND SUPPORT MEASURES FOR PIR PANJAL TUNNEL IN THE HIMALAYAS

CONTROL TECHNOLOGY FOR SOFT ROCK ROADWAY IN INCLINED COAL SEAM: A CASE STUDY IN NUI BEO MINE, QUANG NINH, VIETNAM

Prediction of Elastic Constants on 3D Four-directional Braided

INFLUENCE OF SHALLOW MINE-WORKINGS ON CRACK FAILURE OF OVERBURDEN STRATA. 1. Introduction. 2. General situation. Yu Xueyi*, Huang Senlin*

Underground Drilling and Packer Test in Fault F16 of Wugou Coal Mine

Numerical modelling for estimation of first weighting distance in longwall coal mining - A case study

Three-Dimensional simulation for the rock fragmentation induced by TBM with GFEM

Calculation and analysis of internal force of piles excavation supporting. based on differential equation. Wei Wang

Study on Coal Methane Adsorption Behavior Under Variation Temperature and Pressure-Taking Xia-Yu-Kou Coal for Example

Test Study on Uniaxial Compressive Strength of Fine Sandstone after High. Temperature. Chongbang XU1, a *

Module 5: Failure Criteria of Rock and Rock masses. Contents Hydrostatic compression Deviatoric compression

Tectonic stress environment of coal-rock dynamic hazard in Kailuan mining area, China

Key rock mechanical problems of underground powerhouse in Shuibuya hydropower station

Advanced Detection Theory and Application Research of Multi-wave and Multi-component Seismic Exploration in Mine

Research on Tomography by Using Seismic Reflection Wave in Laneway

The Mathematical Analysis of Temperature-Pressure-Adsorption Data of Deep Shale Gas

Numerical Simulation of Unsaturated Infilled Joints in Shear

1. Rock Mechanics and mining engineering

A STUDY ON THE BLASTING VIBRATION CONTROL OF CREEP MASS HIGH SLOPE

Research Article Experimental Investigation on Creep Deformation Behavior of Medium-strength Marble Rock

A research on the reservoir prediction methods based on several kinds of seismic attributes analysis

Influence of foliation on excavation stability at Rampura Agucha underground mine

Seismic Analyses of Concrete Gravity Dam with 3D Full Dam Model

Module 9 : Foundation on rocks. Content

Table of Contents Development of rock engineering 2 When is a rock engineering design acceptable 3 Rock mass classification

Journal of Engineering Science and Technology Review 11 (3) (2018) Research Article

Estimation of the Residual Stiffness of Fire-Damaged Concrete Members

Deep buried tunnel surrounding rock stability analysis of the cusp catastrophe theory

A new design approach for highway rock slope cuts based on ecological environment protection

Strong Weighting Events in Shallow Multi-seam Longwall Mining

DEPILLARING DEPILLARING OF THE ANJAN HILL 0 SEAM WORKINGS

An Equation for the Adsorption Under Variable Temperature and Pressure Condition

Experimental Study on the Mechanical Properties of Coal Seam as a Main Aquifer of Xiaojihan Coal Mine

HIGHWALL STABILITY DUE TO GROUND VIBRATIONS FROM BLASTING. Dr. Kyle A. Perry Dr. Kot F. Unrug Kevin Harris Michael Raffaldi

Introduction and Background

3D ANALYSIS OF STRESSES AROUND AN UNLINED TUNNEL IN ROCK SUBJECTED TO HIGH HORIZONTAL STRESSES

Rupture characteristics of the overlaying soil with. interlayer due to reverse faulting

Unwedge Geometry and Stability Analysis of Underground Wedges. Sample Problems

Finite Element Simulation of Fracture Initiation Pressure of Coal Seam Gas Well Perforation Completion

Stability of roadways in coalmines alias rock mechanics in practice

Stabilitation Research of the Tunnel Anchorage of Dadu River Bridge in Luding in Yaan to Kangding Expressway

Study on Numerical Simulation of Steam Huff and Puff Based on Deformable Medium Model

Technique of fault interpretation

ISMS Paper No Influence of weak planes on rockburst occurrence. Amin Manouchehrian, Ming Cai *

Fig. 1 Location of the New Shanghai No. 1 Mine in Inner Mongolia, China.

Characteristics of stratigraphic structure and oil-gas-water distribution by logging data in Arys oilfield

Transcription:

Numerical Simulation on Support of Roadway with Compound Roof and Large Cross Section YUE Zhong-wen, YANG Ren-shu, YAN Zhen-dong, WANG Guo-dong, WU Bao-yang School of Mechanics & Civil Engineering China University of Mining & Technology(Beijing) Beijing, China Zwyue75@163.com Abstract: In order to study the stability of coal roadway surrounding rock with large cross-section and compound roof, three dimensional numerical simulation of optimization of support on big section roadway with FLAC 3D was studied under the engineering background of Zhaozhuang Mine of Jincheng Mining Group. Stress distribution and deformation of surrounding rock, stress state of rock-bolt and anchor cable were obtained under different supporting schemes. The affection of the spacing of anchor, the length and spacing of anchor cable to the support in mining roadways were obtained and the optimization of supporting parameters were brought out, which is suitable for joint support of anchor arm and anchor cable of the compels roof on big section roadway. Keywords: compound roof; large section roadway; support technology; parameter optimization 1. Introduction In recent years, coal minning technology of digging overall height floor coal at one time under the condition of thick seam adopted fully has been spread across nation. Meanwhile some problems about excavation and support of the large-cross-sectional roadway were put on the agenda [1]. Two reasons lead to the roof ascend calamity. Firstly, weakness of the roof structure caused by longspan drift and roof increases the probability of roof falling in roadway. Secondly, the research on support theory in big section roadway and equipment investment is weak [2]. Under large cross-section coal roadway with anchor nets supporting, coal seam roof and floor are belong to sedimentary layers and deformation and failure of surrounding rock are produced by excavation. Mechanism of force and deformation about bolt is very complicated in roadway. Under the condition of supporting of bolt + anchor + steel joist + metal mesh. And reasonable supporting parameter will guarantee the good effect of support of surrounding rock [3-7]. In this paper, based on an example of Zhaozhuang Mine of Jincheng Mining Group, FLAC 3D numerical simulation combined with field test is used to study different supporting effect of bolt anchors net distance among the rows, cable length, cable location and other parameters in large section of the coal, which may serve as an important reference for the support parameters. 2. Project background Supported by the Special Fund from the Central Collegiate Basic Scientific Research Bursary. Zhaozhuang Mine of Jincheng Mining Group is a new modern production mine which designing productivity is 6Mt/a. Main mining average thickness of 3# coal seam is 4.5m, the coal bed is thick and stable. The following one is a stable layer of shale or carbonaceous mudstone partings, medium faults in the region is less developed, small faults and collapse columns are more developed. Driving along the full height roof and floor is used, and the section of roadway excavation is 5.5m 4.5m. In the underground construction process, as the special geological structure of soft coal, low strength and seam strength of Figure 1. The numerical model different levels, development of coal fracture, after digging the coal fracture is growth and coal expands under the side compression. Meanwhile, high stress, serious well-bedded and many micro crevasse roof are easy to make the crag surface decency to be broken, and eventually lead to roof falling, sides damaging, floor heaving and other forms. 978-1-935068-25-9 2010 SciRes. 138

3. Model establishment FLAC 3D software is used to analyse the coal seam. The model size is long wide high =50m 30m 40m. The roadway, which section is a rectangle and size is wide high=5.5m 4.5m which is located in the central model. Fig.1 shows three-dimensional model of 30750 units and 34272 nodes generated by FLAC 3D software. In order to inspect the tunnel adjacent formation distortion and the stress situation accurately, the cell near the roadway is closer, while it is sparse away from the roadway department. Parameter Terrance Description of Petro Physical Property Table 1. Rock Parameters Elastic Poisson Modulus Ratio (GPa) Density kg/m3 Cohesive Strength (MPa) Angle of Internal Friction Tensile Strength (MPa) Main Roof Sandy and Argillaceous Rocks 0.23 23.5 2540 1.5 30 4.06 Main Roof Fine-median Grained Sandstone 0.23 26.8 2650 1.6 35.5 8.60 Immediate Bottom Roof Sandy and Argillaceous Rocks 0.24 23.5 2400 1.8 25 1.20 Coal 0.30 14.7 1500 1.2 25 2.0 Immediate Sandy and Argillaceous Rocks 0.29 18.9 2570 1.5 30 4.62 Main Bottom Fine-median Grained Sandstone 0.21 25.9 2650 1.6 35.5 8.60 Table 2. Calculation Parameters of Supporting Structure Materials for Support Elastic Modulus(GPa) Elastic Limit(MPa) Tensile Strength(MPa) Length(m) Diameter Anchor of Roof 210 425 590 2.0 22 Anchor Cable of Roof 195 \ 1730 8.4 22 Coal Side Anchor 210 425 590 2.0 22 Coal Side Anchor Cable 195 \ 1730 5.3 17.8 Joist of Roof 200 265 405 5.1 16 Joist of Coal Side 200 265 405 4.5 16 In support design, under the premise of ensuring safety, reasonable bolt distance between the rows should reduce material consumption and labor quantity, improve driving speeds. However, this is always counter-balance relationship between several factors. Therefore, many programs need to be selected in the optimal solution to play a good supporting effect. 1) Simulation programs Through orthogonal experimental method the simulation is carried out in three different parameters of row After the model has been built, the boundary conditions are set and initial stress is given on the model, the model is balanced in the elastic condition and forms the initial stress field. Mohr - Coulomb elastic-plastic constitutive is given to rock formation. Then roadway excavation and support are implemented. Table 1 shows various rock layers mechanics parameter, while table 2 gives the mechanical parameters of support. Because of the main original rock stress of horizontal stress and absolute advantage of tectonic stress, Zhaozhuang Mine belongs to the typical tectonic stress field. The direction of maximum principal stress is consistent with the roadway excavation in the model. The vertical stress is in the size of 12.5MPa and 13.5MPa, while horizontal stress is between 7.77MPa and 8.47MPa. 4. Support parameters simulation results and analysis 4.1. Inter-row spacing of anchor and spacing of supporting. According to the actual site support design, row spacing changes, meanwhile, anchor row spacing has also been adjusted accordingly. The parameters of the support programs are showed in Table 3. In this nine support programs, bolt, top cable and help cable length are respectively 2400mm, 8400mm and 5300mm. The anchors lay out symmetrically along the roadway, with the side anchor cable spacing 1500mm and anchor cable spacing 2000mm. 139 978-1-935068-25-9 2010 SciRes.

Program The row spacing of anchor Spacing between the anchor Table 3. Scheme of Bolt Distance And Simulation Results Anchor Cable Row spacing Sink measurement Bulge measurement Roof-tofloor convergence Left side displacement Right side displacement Two sides displacement 1 800 800 1600 42.27 26.79 69.06 55.14 55.18 110.32 2 800 950 1600 42.63 26.91 69.54 56.54 56.63 113.17 3 800 1050 1600 43.16 27.08 70.24 57.60 57.62 115.22 4 900 800 1800 42.66 26.93 69.59 56.59 56.38 112.97 5 900 950 1800 43.04 27.04 70.08 57.71 57.71 115.42 6 900 1050 1800 43.53 27.17 70.70 58.80 58.76 117.56 7 1000 800 2000 43.10 27.05 70.15 57.52 57.48 115.00 8 1000 950 2000 43.39 27.12 70.51 58.69 58.81 117.69 9 1000 1050 2000 43.85 27.24 71.09 59.55 59.58 119.13 2) Results analysis From the Table 3, we can see that in nine support programs as bolt inter-row spacing changes from 800mm 800mm to 1050mm 1000mm, top floor and two sides convergence respectively increase only 2.03mm and 8.81mm. Therefore, roadway deformation is small. The two support forms of program 5 and on-site 5102 lane are same, shown in Fig.2. From Fig.2, simulation distortion and measured rules of two groups in tunnel are consistent basically. In the first two weeks the deformation rate was greater, and then it decreased after two weeks. Roadway deformation almost ceases and entries into the stable stage after 40 days. The difference is that deformation of simulation is smaller than the measured one. The actual distortion speed has two inflexions, while the deformation rate of simulated is smooth. This is because that, in the actual project, the effect factors of blasting seismic along with penetration of crossheading and construction, while simulation of tunnel deformation is done under quasi-static. Overall, the simulation results and actual values are in agreement. 180 两帮收敛量 /mm 160 140 120 100 80 60 40 20 0 5102-1#( 实测 ) 5102-2#( 实测 ) 支护方案 5( 模拟 ) 0 20 40 60 80 100 120 140 时间 / 天 Figure 2. Convergence of two sides Figure 3. Comparison of Min-stress distribution Fig.3 shows the minimum principal stress distribution of surrounding rock of program 1 and program 9, respectively. As can be seen from Fig.3, the small tensile stress exists in the shallow rock middle of bottom, besides that, the minimum principal stress is compressive stress. The maximum value of the two minimum principal stresses respectively is 8.74MPa and 8.78MPa and is equivalent to the level of the original rock stress. In anchoring areas the minimum principal stress is basically same. But the stress between the 2MPa and 4MPa in the area of the outside of roof bolting of program 1 is bigger than that of program 9. Therefore, increasing density of roof bolting is conducive to the protection of the integrity of the roof. 978-1-935068-25-9 2010 SciRes. 140

Fig. 4 shows the distribution of maximum principal stress of program 1 and program 9, respectively. The higher stress areas of the two programs are focused on the two sides of deep surrounding-rock, which peak value of maximum principal stress reaches 20MPa. The measured maximum strength of coal is only 20MPa, so rock will be destructed under the peak stress. The destroy range of the coal sides will easily develop to the deep without effective limit of the two sides deformation of shallow surrounding rock. Therefore, there should be enough bolt consistency of the two sides. Fig.5 shows the comparison of horizontal displacement distribution. Which can be inferred from the diagram, the horizontal displacement mainly occurs on the two sides and the max displacement occurs in the middle part. The two sides show curved surface after deformation. The extending range and depth of two sides of rock range in program 9 is more than that of program 1. Therefore, the restriction of the maximum displacement of high-density supporting is more significant than controlling the whole surrounding rock deformation. Figure 5. Comparison of horizontal displacement distribution Figure 4. Comparison of Max-stress distribution Figure 6. Comparison of vertical displacement distribution 141 978-1-935068-25-9 2010 SciRes.

Fig.6 shows the comparison of vertical displacement distribution. It can be inferred from the figure 6 that the vertical displacement mainly occurs on the two sides and the maximum displacement occurs in the middle part. The two sides also show curved surfaces after deformation. The area of roof subsidence above 30mm in program 9 is larger than that in program 1, especially the range of roof subsidence above 40mm. So the deformation of low-density supporting is more than high-density supporting. In a certain range increasing supporting density can not change stress distribution of surrounding rock and limit the maximum displacement, but can limit failure mode and damage degree of shallow surrounding rock. In the numerical simulation, the rock of model tunnel is isotropic and elastoplasticity, and the unit can not be separated. In fact, there are a lot of joints and cracks in the surrounding rock. So after the destruction of surrounding roadway surface will be stripped, which led to the development of continued damage to the deep, especially this situation will be even more intense after being affected by mining. The increase in the support density can reduce the number of surrounding rock surface damage. In practice, it can reduce the peel and fall off. The simulation results show that in a certain extent the supporting density of the bolt (cable) has little effect on maximum deformation of roadway, but obvious effect on the controlling deformation of surrounding rock. Therefore, in practical engineering, the inter-row spacing can not be designed long. 4.2. Length analysis of roof anchor cable The roof anchor cable plays an important role in supporting reinforcement by suspending a whole anchorage body formed by bolts to deep stable rock mass. So it is very important of safety and efficiency by designing a reasonable length of roof anchor cable. According to the analysis of distance between rows of program 9, the length of anchor cable is changed and other parameters are the same which is showed in Table 4. The simulation process monitors the convergence between roof and floor and convergence between two sides as the supporting effect standard. And the monitoring points are located in the middle of bottom-top and two sides. Plan Length of Roof Anchor cable Table 4. Scheme of roof bolt length and results of simulation Roof Convergence Floor Heave Roof to Floor Convergence Left Side Right Side Two Sides A 4400 43.90 27.24 71.14 59.56 59.63 119.19 B 5400 43.87 27.25 71.12 59.60 59.63 119.23 C 6400 43.91 27.24 71.15 59.59 59.61 119.20 D 7400 43.88 27.25 71.13 59.59 59.63 119.22 E 8400 43.85 27.24 71.09 59.55 59.58 119.13 F 9400 43.87 27.24 71.21 59.59 59.63 119.22 As showed from Table 4, roof to floor convergence and two sides displacement almost do not change if the length of roof anchor cable is between 4400mm and 9400mm. So increasing the length of anchor cable has little influence if there is a complete roof. The results show that a certain length of roof anchor cable is conducive to the stability of deep roof rock and achieve the purpose of coupling support. But there is no need to design a too long length because anchorage sections should anchor in stable strata. Based on the analysis results and actual geological conditions of mining, the immediate roof is sandy mudstone with an average thickness of 4.8m and the main roof is middle-fine sandstone with an average thickness of 9.2m. Cable length designed 7.5m is reasonable. 4.3 Layout optimization of anchor cable Based on the analysis of program 9, it is to investigate the deformation of the tunnel affected by anchor cable position which changes the cable position. Roof and each side lay out two cables for each row with a total of 6. Each row and two cables lay out in symmetrical arrangements according to the middle and height of tunnel. Simulation is carried out for five supporting programs in Table5 by changing the spacing of cables. Among them, program Ⅲ is the same to spacing of bolts in program 9. The simulation process monitors the convergence between roof and floor and convergence between two sides as the supporting effect standard. And the monitoring points are located in the middle of bottom-top and two sides. The results are shown in table 5. Showed by table 5, the maximum surface displacement has a reduction to some extent with the narrow space between cables. Analysis showed that it can reduce the overall displacement of surrounding rock, especially the two sides. It is not obvious of roof convergence by reducing roof anchor spacing. The approximately 2m cable spacing is reasonable from the perspective of maintaining the integrity of the roof. It is obvious of two sides displacement by reducing anchor spacing of two sides. Considering the actual construction, the length designed for 1m or so of anchor cable is reasonable. 978-1-935068-25-9 2010 SciRes. 142

Table 5. Scheme of bolt arrangement and simulation results Program Spacing of Side Anchor Cable(m) Spacing of Roof Anchor Cable(m) Roof ConverGence Floor Heave Roof to Floor Convergence Left Side Right Side Two Sides Ⅰ 2.5 3.5 43.95 27.24 71.19 60.48 60.55 121.03 Ⅱ 2 2.5 43.88 27.25 71.13 59.98 60.11 120.09 Ⅲ 1.5 2 43.85 27.24 71.09 59.55 59.58 119.13 Ⅳ 1 1.5 43.80 27.25 71.05 58.88 58.88 117.76 Ⅴ 0.5 1 43.74 27.24 70.98 58.22 58.25 116.47 5. Conclusions 1) It is not obvious that changing spacing range of bolt row between 800mm 800mm and 1050mm 1000mm for maximum deformation of the tunnel. And the relatively short spacing can control the extent of the shallow rock damage. The length designed for 950mm 900mm of anchor cable is reasonable. 2) Based on the practical geological conditions, the length optimal design of anchor cable for 7.5m is reasonable. 3) It is not obvious of reducing spacing of anchor cable for reducing roof convergence than that of controlling deformation of two sides. The length designed for 2m of spacing of roof anchor cables and 1m of spacing of sides anchor cables is reasonable. References [1] Yang Yong-gang, Zhang Hai-yan, Jie Pan-Shi, Research and Practice of Large Section Roadway Support System in Complex Surrounding Rocks, Journal of Mining & Safety Engineering. vol. 26, pp. 354-358, March 2009. [2] ZHONG Xun-hong, Wang Zhen-jiang, Zhang Xue-Liang, Causal Analysis and Prevention of Roadway Roof Accidents. Jiangxi Coal Science &Technology. pp. 43-44, March2007. [3] ZENG You-fu, WU Yong-ping, LAI Xing-ping, WEI Cheng, Analysis of Roof Caving Instability Mechanism of Large- Section Roadway Under Complex Conditions. Journal of Mining & Safety Engineering. Vol.26, pp. 423-427, April2009. [4] Chen Youbao, Wang Jinan, Zhou Yuefeng, Han Zhe, Bolt-mesh Support Technique for Large Sectional Tunnel Under Mined Gob whit Thin Top-coal. China Mining Magazine. Vol.26, pp.58-61, Januray 2009. [5] XU Bang-gui, Research on the Bolt Supporting for Fully- Mechanized Simultaneous Drifting with Large Section Roadway. Journal of Mining & Safety Engineering. Vol.23, pp. 370-373, March2006. [6] SUN Hai-liang, Practice on bolt and steel mesh support in high inclined and large cross section gateway of three soft seam with potential outburst. Coal Science and Technology. vol.31, pp. 32-34, November2003. [7] Zhang Yan Jin, Liu Kedong, Wang Liwei, large section tunnel shotcrete support. Ground Pressure and Strata Control. pp. 30-32, April2001. 143 978-1-935068-25-9 2010 SciRes.