Rubicon Updates Mineral Resource Statement for the Phoenix Gold Project And Evaluates Strategic Alternatives

Similar documents
News Release. Infill Drilling Program

Underground Activities Temporarily Suspended at the Phoenix Gold Project; Rubicon to Enhance its Geological Model and Develop an Implementation Plan

Assay Results Highlights (as of November 16, 2017) representing approximately 4,500 metres ( m ) of drilling:

News Release TSX:RMX NYSE AMEX:RBY November 29, 2010

CROCODILE GOLD FILES TECHNICAL REPORTS FOR FOSTERVILLE AND COSMO GOLD MINES AND PROVIDES ANNUAL GENERAL MEETING INFORMATION

Queenston Announces 112% Increase in Indicated Resource (to 1.5 M oz. gold) and 16% Increase in Inferred Resource (to 0.7 M oz. gold) at Upper Beaver

Red Pine Releases Inferred Resource Report Improves Grade and Tonnage for Wawa Gold Project

Detour Gold Reports Drilling Results from Lower Detour

Table 1 Updated Mineral Resource Tabulation for the Vertikalny Deposits of the Mangazeisky Property. Contained Metal Ag (koz)

KIRKLAND LAKE GOLD ANNOUNCES 120 METRE DOWN-PLUNGE EXTENSION OF SWAN ZONE

IAMGOLD PROVIDES UPDATE ON ADVANCED EXPLORATION PROJECT DIAMOND DRILLING RESULTS BOTO PROJECT, SENEGAL

Wesdome Announces Interim Mineral Resource Estimate for Kiena Mine Complex and Continued Drilling Extends Kiena Deep A Zone Along Plunge

MANDALAY RESOURCES CORPORATION INCREASES MINERAL RESOURCES AND RESERVES AT ITS BJÖRKDAL GOLD MINE

Comparison Between July 2012 Technical Report and December 2012 Mineral Resource Statement July 2012 December 2012 Percentage Difference.

San Gold Drills New Mine Horizon Adjacent to Rice Lake Mine, Returns 10.4 Metres Grading 25.7 g/t Au

CANDENTE UPDATES CAÑARIACO NORTE MINERAL RESOURCE ESTIMATE

CROCODILE GOLD INTERSECTS 7.1 G/T AU OVER 4.5 METERS INCLUDING 11.2 G/T AU OVER 2.6 METERS AT THE UNION REEFS PROJECT, PROSPECT DEPOSIT

CROCODILE GOLD INTERSECTS GRAMS PER TONNE GOLD OVER 2.05 METERS BELOW THE PROSPECT DEPOSIT AT UNION REEFS

June 4, 2015 News Release Valley of the Kings Underground Infill Drilling Underway

The new sulphide mineralization lies within a 1.4 kilometer long east-west trending

NEWS RELEASE. Gold Canyon Encounters Meters at 1.81 Grams per Tonne Gold at its Springpole Gold Project

CAUTIONARY STATEMENT

News Release B2Gold Announces Updated Higher Grade Gold Resource at Wolfshag Zone, Otjikoto Mine, Namibia

TROILUS GOLD CORP. INITIATES 30,000 METRE DRILL PROGRAM ON TROILUS PROPERTY

PRESS RELEASE. Banro Announces a Mineral Reserve Estimate at its Namoya Gold Mine, Democratic Republic of the Congo

NEWS RELEASE ORCA GOLD REPORTS CONTINUED SUCCESS AT GSS

Probe Metals Intersects 3.2 g/t Gold Over 45.5 Metres At Val-d Or East

Highlights from the four holes announced in this news release include:

Form F3 MATERIAL CHANGE REPORT

NEWS RELEASE ORCA GOLD INDICATED AND INFERRED RESOURCES AT BLOCK 14 INCREASE BY 24% AND 48% RESPECTIVELY

NEWS RELEASE. Gold Canyon Encounters Meters at 1.47 Grams per Tonne Gold at its Springpole Gold Project

Minsud to recommence resource outline diamond drilling at the Chita Valley Cu- Au-Ag-Mo Project, San Juan, Argentina

CROCODILE GOLD CONTINUES POSITIVE EXPLORATION RESULTS INTERSECTS HIGH GRADE GOLD AT UNION REEFS PROJECT

Table 1: Mineral Resources at Costerfield, Inclusive of Mineral Reserves as of December 1, 2018 and December 31, 2017.

Coeur Mining Provides Silvertip Exploration Update

Probe Metals Continues to Expand Gold Zones At Val-d Or East

Probe Metals Continues to Intersect Significant Gold Mineralization in Expansion Drilling at Val-d Or East, including 4.1 g/t Gold Over 15.

July 15, 2015 News Release Valley of the Kings Underground Infill Drilling Progresses

GOLDEN MINERALS DISCOVERS ADDITIONAL HIGH GRADE VEINS AT SANTA MARIA RESULTS UP TO 1.88 g/t Au and 648 g/t Ag

IAMGOLD REPORTS HIGH-GRADE DRILL INTERSECTIONS FROM ITS 2017 DRILLING PROGRAM ON THE DIAKHA DEPOSIT, SIRIBAYA PROJECT IN MALI

Orezone s Bomboré Gold Project Reaches World Class Size

Northern Dynasty Minerals Ltd.

AVION GOLD DJAMBAYE II ZONE, TABAKOTO PROJECT, MALI, RETURNS HIGH GRADE INTERCEPTS OF 7.56 G/T Au OVER 7.0 METRES AND G/T Au OVER 3.

NEWS RELEASE FULLER PROPERTY CONTINUES TO DELIVER GOOD RESULTS 2.53 GRAMS PER TONNE GOLD OVER METRES

Strategic Phase 2 Exploration Program Launched at Island Gold High-Grade Resource Potential Identified Laterally and at Depth

PRESS RELEASE NEW MINERAL RESOURCE UPDATE AT PRAIRIE CREEK MINE. Measured + Indicated and Inferred Resource Tonnages Increased

Bellhaven Announces Updated NI Mineral Resource for La Mina Project, Colombia

(416) Highlights include:

Dalradian Intersects 2.48 metres Grading g/t Gold and 4.87 metres Grading 8.35 g/t Gold With Infill Drilling at Curraghinalt

Altynalmas Gold s new upgraded and confirmed Bakyrchik East Mineral Resource Gold deposit boosts total gold resources at Kyzyl Project in Kazakhstan

BELO SUN INTERSECTS NEW HIGH GRADE ZONE AT GROTA SECA AND EXPANDS GRANDE DEPOSIT

IDM Mining s Underground Drilling Intersects g/t Au and g/t Ag over 6.80 Meters True Width at the Red Mountain Gold Project

PRESS RELEASE. Banro Increases Oxide and Free-milling Ounces of Gold by 45%

KIRKLAND LAKE GOLD REPORTS WIDE, HIGH-VALUE GOLD INTERCEPTS AT SWAN ZONE UP TO 200 METRES FROM CURRENT MINERAL RESERVES

FALCO PACIFIC COMPLETES INITIAL MODEL FOR THE HORNE 5 GOLD/SILVER/ZINC/COPPER DEPOSIT

NEWS RELEASE. Foran Mining Intersects High Grade Zinc at McIlvenna Bay. Results expand area of known mineralization

Details of the NI compliant mineral resource estimate are as follows. Total Inferred 7,603,

BGM ANNOUNCES MINERAL RESOURCE UPDATE AT BARKERVILLE MOUNTAIN TO SUPPORT BONANZA LEDGE OPERATIONS

NEWS RELEASE. Mountain Province Diamonds Reports Additional Kimberlite Identified in Gahcho Kué Exploration Program

October 8, 2015 News Release Brucejack Regional Drilling Intersects Over 8,000 Grams Per Tonne Gold

North American Palladium Announces Positive Exploration Results from Lac des Iles Mine

LUNA GOLD INCREASES MEASURED AND INDICATED RESOURCES TO 3.63 MILLION OUNCES AND INFERRED RESOURCES TO 1.04 MILLION OUNCES AT AURIZONA

MONETA INTERCEPTS g/t GOLD INCLUDING g/t GOLD AND g/t GOLD INCLUDING g/t GOLD AT SOUTH WEST

Tahoe Resources Mineral Reserves as of January 1, 2018

Plateau Extends Falchani East Lithium Deposit Community Agreements Executed and Three Drill Rigs Active at Falchani West

Probe Metals Confirms Continuity of Gold Mineralization on its Val-d Or East Project And Increases 2017 Drill Program to 75,000 metres

QMX GOLD CONTINUES TO INTERSECT STRONG MINERALIZATION AT BONNEFOND, INTERSECTING 39.5 g/t Au OVER 2.4 METRES AND 31.5 g/t Au OVER 1.

June 4, 2014 News Release Valley of the Kings Exploration Program Underway; Project Update

SABINA GOLD &SILVER REPORTS COMPLETION OF DRILLING AT ECHO DEPOSIT, BACK RIVER, NUNAVUT.

Fission s Initial Resource Totals at PLS: 79.6M lbs Indicated and 25.9M lbs Inferred

Fortuna Updates Reserves and Resources

Sept 20, 2012 TSX Venture Exchange Tier 1 Trading Symbol: OK

Fura Gems Inc. FURA ANNOUNCES MAIDEN MINERAL RESOURCE ESTIMATE FOR THE COSCUEZ EMERALD MINE, A FIRST FOR THE COLOMBIAN EMERALD SECTOR

MILLENNIUM MINERALS LIMITED

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C Form 6-K

INFILL DRILLING EXPANDS MINERALIZATION IN HIGH-GRADE GOLD-COPPER CORE AT SOUTHWEST DISCOVERY ZONE TURQUOISE HILL PROJECT, MONGOLIA

SALAZAR ANNOUNCES AN UPDATED RESOURCE REPORT OF 5.53 MT INDICATED AND 1.46 MT INFERRED AT ITS HIGH GRADE VMS EL DOMO DEPOSIT

BALMORAL INTERSECTS g/t GOLD OVER 7.99 METRES, BUG LAKE SOUTH, DETOUR GOLD TREND PROJECT, QUEBEC

Skeena Intersects g/t AuEq over metres at Eskay Creek

MEDIA RELEASE OCEANAGOLD ANNOUNCES FURTHER DOWN DIP EXTENSIONS OF MINERALISATION AT PANEL 2: FRASERS UNDERGROUND MINE

Mineral Resource Estimate Comparison at 3 g/t Au cut-off

MONETA INTERCEPTS g/t GOLD INCLUDING g/t GOLD AT SOUTH WEST

August 20, 2018 SBB NR SBB TSX

KIRKLAND LAKE GOLD EXTENDS HIGH-GRADE GOLD MINERALIZATION AT MACASSA, NEW GOLD SYSTEM DISCOVERED AT DEPTH

Change +492, , , ,000 Note: (1) Values are rounded to nearest thousand which may cause apparent discrepancies.

OSISKO METALS INTERSECTS 10.49% ZINC+LEAD OVER METRES AND 12.15% ZINC+LEAD OVER METRES AT PINE POINT

Probe Metals Discovers New High Grade Gold Zone on Val-d Or East Project: Intersects 12.6 g/t Gold Over 7.3 Metres

V Sample from C.O.D vein 15 metres southwest of V

A B C PAD A HIGHLIGHTS

MANN SILVER-COBALT MINE. PORE: TSXV PowerOre.com

PRESS RELEASE. DUBUISSON NORTH DRILLING CUTS g/t AU OVER 5.0 METRES NEW S50 EAST DISCOVERY, 3.39 g/t AU OVER 25.9 METRES

NEWS RELEASE November 5, 2018

NEWS RELEASE. Foran Intersects Over 28 Metres of Copper Mineralization

KIRKLAND LAKE GOLD EXPANDS NEW HIGH-GRADE ZONE BELOW TAYLOR MINE, REPORTS MINERALIZED EXTENSIONS ALONG STRIKE AND AT DEPTH

NEWS RELEASE. Tigray Intersects 28.2 metres at 8.50 grams per tonne gold at Mato Bula, Adyabo Project, Northern Ethiopia

Goldplay President and CEO Marcio Fonseca commented

Lalor Project Disclaimer

555 Burrard Street, Suite 375, Vancouver, B.C. V7X 1M June 13, 2017 SBB NR SBB TSX

First Cobalt Extends Iron Creek 100 Metres Downdip in Central Area

BELO SUN RELEASES RESULTS FROM 65 DRILL HOLES FURTHER EXTENDING THE OURO VERDE DEPOSIT ALONG STRIKE NORTHWEST AND DOWN DIP

Transcription:

News Release Rubicon Updates Mineral Resource Statement for the Phoenix Gold Project And Evaluates Strategic Alternatives January 11, 2016 TORONTO, Ontario Rubicon Minerals Corporation (TSX: RMX NYSE-MKT: RBY) ( Rubicon or the Company ) provides a revised geological model and updated mineral resource statement 1 for the F2 Gold Deposit at the Phoenix Gold Project (the Project ). A technical report documenting the new mineral resource statement will be filed on SEDAR within 45 days in accordance with the requirements of National Instrument 43-101 Standards of Disclosure for Mineral Projects ( NI 43-101 ). In addition, the Rubicon Board of Directors (the Board ) has retained BMO Capital Markets and TD Securities as financial advisors to assist the Board in evaluating strategic alternatives available to the Company, including merger and divestiture opportunities either at the corporate or asset level, obtaining new financing, and capital restructurings to maximize shareholder value. There can be no assurances that any transaction will result from these matters and the Company will make updates when circumstances warrant. News Release Summary: The 2016 revised geological model ( 2016 SRK Geological Model ) and updated mineral resource statement ( 2016 SRK Resource Estimate ) (see Table 1 below) prepared by SRK Consulting (Canada) Inc. ("SRK") and reviewed by other independent consultants, considers information from of 94,600 metres ( m ) of core drilling, from mineralized underground workings, and trial stoping that were not previously available; Table 1: 2016 Mineral Resource Statement, Phoenix Gold Project, Ontario, SRK, January 6, 2016 2 at 4.0 grams per tonne of gold ( g/t Au ) cut-off grade Resource Category Quantity (000'tonnes) Contained Gold (000' ounces ( oz. )) Indicated 492 6.73 106 Inferred 1,519 6.28 307 Mineral resources are not mineral reserves and have not demonstrated economic viability. All figures are rounded to reflect the relative accuracy of the estimate. Samples have been capped where appropriate. Underground mineral resources reported at a cut-off grade of 4.0 g/t Au of gold per tonne assuming a gold price of US$1,125/oz. and a gold recovery of 92.5%. The 2016 SRK Resource Estimate represents a significant decrease in tonnes and ounces compared to the 2013 mineral resource estimate 3 ( 2013 SRK Resource Estimate )(see Table 2 below); 1 There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the updated mineral resource statement will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. 2 This news release should be read in conjunction with the tables and figures included in the body and presented at the end of the release. The Company plans to file a Technical Report for the updated mineral resource estimate within 45 days from today. 3 All references to the 2013 SRK Resource Estimate are reported in the Company s Preliminary Economic Assessment with an effective date of June 25, 2013 and with an issue date of February 28, 2014, available on SEDAR (www.sedar.com) and EDGAR (www.sec.gov/edgar.shtml), which is no longer considered to be correct.

Page 2 of 11 Table 2: Comparison between 2013 and 2016 Quantities and s Reported at 4.0 g/t Au 4 Classification Quantity (000 t) Contained Gold (000 oz) 2013 2016 Change 2013 2016 Change 2013 2016 Change Indicated 4,120 492-88% 8.52 6.73-21% 1,129 106-91% Inferred 7,452 1,519-80% 9.26 6.28-32% 2,219 307-86% The 2016 SRK Geological Model demonstrates that the F2 Gold Deposit is more geologically complex and the high-grade gold mineralization is less continuous than previously understood; The new drilling and recent trial stoping information has significantly changed the understanding of the variable spatial distribution of the gold mineralization. East-west (mine grid) trending cross-cutting shear structures ( D2 structures ) have been interpreted as the main control on the distribution of later stage highergrade gold mineralization. This is the key factor contributing to the limited continuity of the gold mineralization compared to previous understanding; The decrease in reported mineral resources are mainly the result of the new drilling information, changes in modelling approach and restrictions to the depth of the interpreted extent of the gold mineralization; Rubicon has suspended activities related to the Phoenix Project Implementation Plan ( PPIP ) A technical report will be filed within 45 days of this news release to support the technical disclosure herein; Rubicon remains engaged in ongoing discussions with its lenders; In 2015, the Company produced 4,906 ounces of gold from 57,793 tonnes of mineralized material; and Estimated cash and cash equivalents as of December 31, 2015 was approximately C$22.4 million (excluding C$4.5 million in restricted cash). The revised geological model prepared by SRK indicates that the gold mineralization in the upper-levels of the F2 Gold Deposit is less continuous compared to the geological model for the 2013 mineral resource estimate, stated Michael Winship, interim President and Chief Executive Officer of Rubicon. The revised model has significantly decreased the tonnes, grade and ounces in the F2 Gold Deposit. The revised model suggests that more exploration is required at depth and along strike in order to develop an economic mining operation at the Phoenix Gold Project. The Board has retained financial advisors to evaluate strategic alternatives with the goal to maximize shareholder value. 2016 SRK Geological Model Rubicon conducted trial stoping throughout 2015, allowing the Company to develop the F2 Gold Deposit and process mineralized material. As reported in the Company s November 3, 2015 news release, Rubicon suspended underground activities to enable SRK, the Company, and its other independent consultants to conduct further analysis on a revised geological model. The geology was more complex than previous understandings, as revealed though trial stoping. The 2016 SRK Geological Model benefits from information that was not previously available, including approximately 94,600 m of infill core drilling within a concentrated shallow area of the deposit, and a considerable amount of underground development and limited trial stoping, which exposed the gold mineralization. The new geological information has highlighted the complexity of controls on the distribution of the gold mineralization, its grade, and its continuity. In particular, the distribution of the higher-grade mineralization is controlled by the intersection between 4 There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the updated mineral resource statement will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.

Page 3 of 11 the east-west trending D2 structures and the north-trending high-titanium basalt unit. The new data shows that the high-grade gold mineralization is less continuous than indicated in the 2013 SRK Resource Estimate, which was based upon less widely-spaced drilling data that was drilled sub-parallel to the D2 structures. See Figure 2 at the end of this news release for a conceptual diagram of the revised geological understanding of the high-grade mineralization compared to 2013. The 2016 SRK Geological Model is more restrictive, reducing the volume of gold mineralization. Therefore, this resulted in a significant decrease in tonnes, grade, and ounces in the upper-levels of the deposit. SRK s geological modelling approach limited the depth and strike extensions of the modelled gold mineralization, further reducing the mineral resources. The Company believes additional exploration (drilling, development, sampling, trial stoping, etc.) is required to better understand the geology of the F2 Gold Deposit. 2016 SRK Resource Estimate The 2016 SRK Resource Estimate 5 is based on a total of 450,175 m of core drilling in 1,381 drill holes carried out from February 2008 to November 2015. The mineral resource model covers a strike length of approximately 1,200 m and depths of 1,350 m and remains open along strike and at depth. At the reporting cut-off grade of 4.0 g/t Au, the indicated mineral resource is 0.492 million tonnes, grading 6.73 g/t Au, and contains 0.106 million ounces of gold and the inferred mineral resource is 1.519 million tonnes, grading 6.28 g/t Au, and contains 0.307 million ounces of gold. The mineral resources were evaluated using a geostatistical block modelling approach constrained by gold mineralization domains interpreted from the drilling information. Block gold grade was interpolated using ordinary kriging. The block model was classified in accordance with CIM Definition Standards for Mineral Resources and Mineral Reserves (May 2014). The mineral resources are sensitive to the selection of reporting assumptions. The sensitivity of the global quantities and grade estimates to the selection of cut-off grade is summarized as grade tonnage data in Table 5 and classified mineral resources reported by underground level are tabulated in Table 6, at the end of this news release. Reconciliation to the 2013 SRK Resource Estimate 6 It is difficult to reconcile the 2016 SRK Resource Estimate with the 2013 SRK Resource Estimate disclosed on June 25, 2013 because the two models differ. The 2016 SRK Resource Estimate considers an additional 94,600 m of core drilling and underground exposures of the gold mineralization that were not available for the 2013 SRK Resource Estimate. The 2016 SRK Resource Estimate also excludes the crown pillar and isolated gold intersections and interpretations outside the main domains modelled. At the reporting cut-off grade of 4.0 g/t Au, the 2016 indicated mineral resource decreased 91% compared to 1.13 million ounces of gold in the 2013 SRK Resource Estimate. The 2016 inferred mineral resource decreased 86% relative to 2.22 million ounces of gold in the 2013 SRK Resource Estimate. The primary causes for the significant change in indicated and inferred mineral resources compared to the 2013 SRK Resource Estimate are summarized in Table 3 and Figure 1 below. 5 There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the updated mineral resource statement will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. 6 All references to the 2013 SRK Resource Estimate are reported in the Company s Preliminary Economic Assessment with an effective date of June 25, 2013 and with an issue date of February 28, 2014, available on SEDAR (www.sedar.com) and EDGAR (www.sec.gov/edgar.shtml), which is no longer considered to be correct.

Page 4 of 11 Table 3: Key Parameters that Contributed to the Significant Variance in Mineral Resources between 2013 and 2016 Parameter 2013 SRK Resource Estimate 2016 SRK Resource Estimate Material Impact Informing Data Drilling data Underground workings Geological Modelling Wireframe/volumetrics High- Treatment Strategy Capping grade (domains) HG limited radii Exclusions from the 2016 SRK Resource Estimate 820 core drill holes 355,611 m Minimal gold mineral exposed Continuity modelled based on available information Main zone domain: 200 g/t Au HW domain: 150 g/t Au External domain: 30 g/t Au Not applied 1,381 core drill holes 450,175 m >9,000 m of underground development and exposure of gold mineralization in trial stoping New data shows limited highgrade continuity modelled high-grade domains represent 17% of that in 2013 High- ( HG ): 10.0 120.0 g/t Au (71 domains) Low- ( LG ): 5.0 45.0 g/t Au (19 domains) HG composites limited to 10-20 m Reveals the complexity and limited grade continuity Demonstrates significant complexity and limited grade continuity Reduced tonnes due to significantly narrower domains Reduced grade Reduced grade None Crown pillar Reduced ounces Material external to wireframes Reduced ounces Material below 1,220-metre level Reduced ounces

Page 5 of 11 Figure 1: Change in Mineral Resource Ounces between 2013 and 2016 Indicated and Inferred Mineral Resources Informing Data: The 2016 SRK Geological Model includes additional information from 94,600 m of infill drilling, underground workings that expose the gold mineralization, and trial stoping, none of which were available in 2013. Geological Modelling: SRK revised the assumptions underlying the 2016 SRK Resource Estimate to reflect the trial stoping results, which exposed the mineralization, suggesting that the continuity of the high-grade gold mineralization may be more limited than had been assumed in the 2013 SRK Resource Estimate. As a result, the wireframe models of the high-grade gold domains are now volumetrically smaller, but better defined, than those considered in 2013. The volumes of the new high-grade domains in the core area of the F2 Gold Deposit now represent about 17% of what they were in 2013, resulting in a material decrease in tonnage and contained gold in the updated mineral resource estimate.

Page 6 of 11 High- Treatment Strategy: A more representative estimation strategy for high-grade samples was also adopted to better reflect the recent stoping information. Considering the new interpretation and the new sampling data, more detailed capping levels were applied. In addition, a spatial restriction was applied to high-grade samples in 2016 to further limit their influence during grade estimation and to more accurately reflect their distribution as demonstrated by new infill drilling and underground excavation samplings. This restriction contributes further to the lower tonnage, grade and contained metal of the high grade mineralization. Table 7 summarizes the impact of grade capping compared to an uncapped scenario. Exclusions from the 2016 SRK Resource Estimate: Locally, significant gold mineralization exists outside the 2016 modelled domains. In 2013, to account for this mineralization, the areas located outside the modelled domains were also evaluated as a separate unconstrained domain (External domain) and the resultant mineralization was assigned an inferred classification. In 2016, based on observed gold mineralization continuity noted from the new data, the areas in the 2013 inferred mineral resource estimate were excluded as follows (see Figure 1): Evaluations External domain: 355,000 oz. of gold in the inferred category; Crown pillar: 267,000 oz. of gold in the inferred category; and Area below the 1,220-metre level: 728,000 oz. of gold in the inferred category. Based on the new geological model and the 2016 SRK Resource Estimate, Rubicon believes that at current gold prices, there are inadequate tonnage and grade to economically support stand-alone trial stoping above the 305-metre level. The Company believes that further exploration work is required, particularly at depth and along strike, to develop a potential mineable resource. As a result, Rubicon has suspended activities related to the PPIP and will evaluate further exploration activities to advance the Phoenix Gold Project. Trial Stoping Activities to the End of December 31, 2015 In 2015, the Company produced 4,906 ounces of gold from 57,793 tonnes of mineralized material grading at 2.89 g/t Au. Operations have now been suspended. Table 4 summarizes the results from the commissioning and trial stoping period, below. Table 4: Trial Stoping Metrics to the end of December 30, 2015 Commissioning and trial stoping period (May-December 2015) Operating Metrics Total Mineralized material milled (tonnes) 57,793 to the mill 2.89 Average mill recovery (%) 91.5 Gold produced (ounces) 4,906 Gold poured (ounces) 4,412

Page 7 of 11 Environment The Company continues to comply with its environmental obligations using the staff on site. The Company has completed the following environmental measures at the Project: Construction of the coffer dam, northeast dam, spillway, and runoff collection measures around the perimeter of the site; Installation and commissioning of the ammonia treatment system; Met all treated effluent discharge requirements; Implementation of an operating strategy for the tailings management facility; and Submission of monitoring, reports, and technical studies. Balance Sheet and Discussions with Lenders Estimated cash and cash equivalents at December 31, 2015 was approximately C$22.4 million (excluding restricted cash of C$4.5 million). The Company continues to hold ongoing discussions with its lenders. Impairment Charge In conjunction with the update of the 2016 SRK Resource Estimate and the suspension of the PPIP, the Company is reviewing the carrying value of its assets, in accordance with International Financial Reporting Standards, and anticipates that it will incur a significant impairment charge in its quarterly financial results for the period ending December 31, 2015. Strategic Review The Board has retained BMO Capital Markets, TD Securities, and Stikeman Elliott LLP as advisors to assist in evaluating strategic alternatives available to the Company, including merger and divestiture opportunities either at the corporate or asset level, obtaining new financing, and capital restructurings to maximize shareholder value. There can be no assurances that any transaction will result from these matters. During the strategic review, the Company will undertake the next steps with regard to the Phoenix Gold Project: Continue to review the revised geological model; Complete a technical report documenting the 2016 SRK Resource Estimate that will be filed on SEDAR within 45 days in accordance with the requirements of NI 43-101; Evaluate further follow-up exploration to better understand the geology of the F2 Gold Deposit, which may include: o Evaluate areas that contain significant isolated gold intersections excluded from the mineral resource model; o Drilling targeting the D2 structures along north-south azimuth; o Infill drilling below the 305-metre level; o Diamond drilling along strike and at depth; Continue to protect the Project assets and the surrounding environment. The Company will make updates when circumstances warrant.

Page 8 of 11 Conference Call Details The Company's senior management team will host a conference call today, Monday, January 11, 2016 at 10:30 am ET (7:30 am PT) to discuss the news release. Participants in Canada and the United States may join the conference call by dialing toll free +1 (800) 319-4610 or +1 (416) 915-3239 for calls outside Canada and the United States or via webcast http://services.choruscall.ca/links/rm20160111.html. A recorded playback of the conference call can be accessed on the Company s website at www.rubiconminerals.com. RUBICON MINERALS CORPORATION Michael Winship Interim President and Chief Executive Officer Cautionary Statement regarding Forward-Looking Statements and other Cautionary Notes Forward-Looking Statements This news release contains statements that constitute forward-looking statements and forward looking information (collectively, forward-looking statements ) within the meaning of applicable Canadian and United States securities legislation. Forward-looking statements include, but are not limited to statements regarding the further exploration of the F2 Gold Deposit. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management s best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others, that: the demand for gold and base metal deposits will develop as anticipated; the price of gold will remain at levels that would render the Phoenix Gold Project potentially economic; that any proposed operating and capital plans will not be disrupted by operational issues, power supply, labour disturbances, or adverse weather conditions; Rubicon will continue to have the ability to attract and retain skilled staff; and there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the PEA. Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: possible variations in mineralization, grade or recovery or throughput rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents and other risks of the mining industry; delays and other risks related to construction activities and operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions, programs and working capital requirements on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; market conditions and general business, economic, competitive, political and social conditions. It is important to note that the information provided in this news release is preliminary in nature. There is no certainty that a potential mine will be realized. A mine production decision that is not based on a feasibility study demonstrating economic and technical viability does not provide adequate disclosure of the increased uncertainty and specific risks of failure associated with such a production decision. It is important to note that there is no guarantee of the success of the strategic review process being undertaken by the Company. Forward-looking statements contained herein are made as of the date of this release and Rubicon disclaims any obligation to update any forwardlooking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Cautionary Note to U.S. Readers Regarding Estimates of Indicated and Inferred Resources This news release uses the terms measured and indicated mineral resources and inferred mineral resources. The Company advises U.S. investors that while these terms are recognized and required by Canadian securities administrators, they are not recognized by the SEC. The estimation of measured, indicated and inferred mineral resources involves greater uncertainty as to their existence and economic feasibility than the estimation of proven and probable reserves. The estimation of inferred resources involves far greater uncertainty as to their existence and economic

Page 9 of 11 viability than the estimation of other categories of resources. It cannot be assumed that all or any part of a measured, indicated or inferred mineral resource will ever be upgraded to a higher category. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility studies, pre-feasibility studies or other economic studies, except in prescribed cases, such as in a preliminary economic assessment under certain circumstances. The SEC normally only permits issuers to report mineralization that does not constitute reserves as in-place tonnage and grade without reference to unit measures. Under U.S. standards, mineralization may not be classified as a reserve unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any part or all of a measured, indicated or inferred mineral resource exists or is economically or legally mineable. Information concerning descriptions of mineralization and resources contained herein may not be comparable to information made public by U.S. companies subject to the reporting and disclosure requirements of the SEC. Mineral Resources Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured mineral resource category. The mineral resources in this press release were reported using CIM Standards. QA/QC Drill core assays were conducted on sawn half core sections. All assays were conducted by independent laboratory SGS Mineral Services of Red Lake, Ontario using fire assay with AA finish or using gravimetric finish for values over 10.0 g/t Au. Rubicon's quality control checks include insertion of blanks, standards and duplicates included at regular intervals in each sample batch to ensure laboratory accuracy. Check assays on 5% of samples are carried out at a third party independent laboratory. Qualified Persons The construction of the geology and mineral resource model was a collaborative effort between SRK and Rubicon personnel. The construction of the geology model was completed by Dr. Jean-François Ravenelle, P.Geo (APGO#2159). The resource estimation work was completed by Sébastien Bernier, P.Geo (APGO#1847) and Dr. Oy Leuangthong, P.Eng (PEO#90563867) under the supervision of Glen Cole, P.Geo (APGO #1416). By virtue of their education, membership to a recognized professional association and relevant work experience Mr. Sébastien Bernier, Dr. Leuangthong, Dr. Ravenelle and Mr. Cole are all independent Qualified Persons as defined by NI 43-101. They have reviewed drafts of this news release and have approved its content. The content of this news release has been read and approved by Howard Bird, B.Sc. (Hons.), P. Geo., Vice President, Exploration and is a Qualified Person as defined by NI 43-101.

Source Page 10 of 11 Figure 2 Rubicon Conceptual Diagram of the Revised Geological Understanding of the F2 Gold Deposit Compared to 2013 Plan View (Diagram not to Scale) Source: Rubicon Table 5: The 2016 Global Block Model Quantities and Estimates at Various Cut-off grades 7 Indicated Classification Inferred Classification Cut-off Quantity (000 t) Contained Gold (000 oz.) Quantity (000 t) Contained Gold (000 oz.) 3.0 719 5.71 132 2,491 5.18 415 3.5 601 6.19 120 1,959 5.71 360 4.0 492 6.73 107 1,519 6.28 307 4.5 399 7.31 94 1,171 6.88 259 5.0 319 7.95 82 959 7.36 227 The reader is cautioned that the figures in this table should not be misconstrued with a Mineral Resource Statement. The figures are only presented to show the sensitivity of the block model estimates to the selection of a cut-off grade. 7 There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the updated mineral resource statement will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.

Page 11 of 11 Table 6: Classified Mineral Resources by Underground Level 8 Level (metres below surface) Tonnes (000s) Indicated Classification Contained Oz. Au (000) Tonnes (000s) Inferred Classification Contained Oz. Au (000) 122 5 5.74 1 12 7.70 3 183 59 6.59 13 71 5.30 12 244 122 6.16 24 66 5.82 12 305 128 6.63 27 82 6.24 17 366 125 7.22 29 120 6.31 24 427 52 7.37 12 136 6.53 29 488 1 4.17 0 186 5.73 34 549 90 5.61 16 610 88 5.98 17 671 112 5.78 21 732 88 5.25 15 793 79 5.42 14 854 75 6.17 15 915 84 7.25 20 976 56 8.06 15 1,037 60 8.13 16 1,098 48 8.32 13 1,159 36 8.20 9 1,220 30 6.26 6 1,281 1 4.65 0.21 Table 7: Sensitivity of 2016 mineral resource model to high-grade treatment strategies, at 4.0 g/t Au cut-off 8 Resource category Uncapped/ No limited radii Contained Gold (000 oz) Capped/ No limited radii Capped/ With limited radii Applying capping Variation Applying capping + limited radii Indicated 168 113 106 (55) -33% (62) -37% Inferred 1,167 479 307 (688) -59% (860) -74% 8 There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the updated mineral resource statement will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.