Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018

Similar documents
Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2

Fluvial Driven Alluvial Fans

HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE

Flood and Stream Restoration

Appendix F Channel Grade Control Structures

Stream Geomorphology. Leslie A. Morrissey UVM July 25, 2012

GEOMORPHIC CHANGES IN LOWER CACHE CREEK 2012

Dolores River Watershed Study

RAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION

Why Stabilizing the Stream As-Is is Not Enough

APPENDIX A REACH DECRIPTIONS. Quantico Creek Watershed Assessment April 2011

Assessment. Assessment

Appendix G. Riverbank Stabilization Techniques

Vegetation effects on river hydraulics. Johannes J. (Joe) DeVries David Ford Consulting Engineers, Inc. Sacramento, CA

Upper Mississippi River Basin Environmental Management Program Workshop

Geomorphic Importance of Winter Peak Flows and Annual Snowmelt Hydrographs in a Sierra Nevada Boulder-Bedrock River

Rapid Geomorphic Assessments: RGA s

Ways To Identify Background Verses Accelerated Erosion

CR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District

Implementing a Project with 319 Funds: The Spring Brook Meander Project. Leslie A. Berns

Stream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)

Limitation to qualitative stability indicators. the real world is a continuum, not a dichotomy ~ 100 % 30 % ~ 100 % ~ 40 %

Field Observations and One-Dimensional Flow Modeling of Summit Creek in Mack Park, Smithfield, Utah

Long Valley Meadow Restoration Project

CASE STUDIES. Introduction

Do you think sediment transport is a concern?

Aquifer an underground zone or layer of sand, gravel, or porous rock that is saturated with water.

Why Geomorphology for Fish Passage

Hydraulics of bendway weirs

DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.

The last three sections of the main body of this report consist of:

The how, why, and lessons learned

Riparian Assessment. Steps in the right direction... Drainage Basin/Watershed: Start by Thinking Big. Riparian Assessment vs.

Garner State Park Pavilion Preservation Study

GEOL 652. Poudre River Fieldtrip

Summary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,

GENERAL SUMMARY BIG WOOD RIVER GEOMORPHIC ASSESSMENT BLAINE COUNTY, IDAHO

Probabilistic Evaluation of a Meandering Low-Flow Channel. February 24 th, UMSRS

Best Management Practices for Coldwater Fisheries Enhancement and Restoration

Upper Truckee River Restoration Lake Tahoe, California Presented by Brendan Belby Sacramento, California

NATURE OF RIVERS B-1. Channel Function... ALLUVIAL FEATURES. ... to successfully carry sediment and water from the watershed. ...dissipate energy.

Dam Removal Analysis Guidelines for Sediment

Bank stabilization by redirective structures on the Santa Clara River, Ventura County, CA

June 9, R. D. Cook, P.Eng. Soils Engineer Special Services Western Region PUBLIC WORKS CANADA WESTERN REGION REPORT ON

PolyMet NorthMet Project

DESCHUTES RIVER BANK STABILIZATION PROJECTS ASSESSMENT

SELBY CREEK STREAM HABITAT RESTORATION AND RIPARIAN REVEGETATION PROJECT: GEOMORPHIC ANALYSIS AND REVIEW

May Creek Canyon LWD Stream Restoration Project. Helicopter Placement of LWD in an Urban Stream. By Kathryn Neal, P.E.

1 INTRODUCTION AND MAJOR FINDINGS... 1

Instream Erosion Control General

Perspectives on river restoration science, geomorphic processes, and channel stability

NEWS RELEASE UNDER SECTION 404 OF THE CLEAN WATER ACT (33 USC 1344) ACTION NUMBER SPA ABQ

STABILIZATION OF THE H&CT RAILWAY STONE DAM WALTER E. SKIPWITH, PE, JOYCE CRUM, AIA AND JOHN BAUMGARTNER, PE. Introduction.

Rock Sizing for Waterway & Gully Chutes

Field Trip Number One. By: Pat Dryer. Geography 360

Analysis of Cost-Effective Rehabilitation: Principles and Tools for Reducing Uncertainty in Design

Restoring the Napa River:

6.11 Naas River Management Unit

Historical channel change on the Upper Gila River, Arizona and New Mexico in response to anthropogenic modifications and extreme floods

SCOPE OF PRESENTATION STREAM DYNAMICS, CHANNEL RESTORATION PLANS, & SEDIMENT TRANSPORT ANALYSES IN RELATION TO RESTORATION PLANS

3.12 Geology and Topography Affected Environment

Fluvial Geomorphic Guidelines

Fish Passage at Road Crossings

Shoreline and Climate Change Adaptation Alternatives for The Letter Parcel, Bolinas Lagoon

Countermeasure Calculations and Design

Technical Memorandum. To: From: Copies: Date: 10/19/2017. Subject: Project No.: Greg Laird, Courtney Moore. Kevin Pilgrim and Travis Stroth

MEMORANDUM 1. INTRODUCTION

MEANDER MIGRATION MODEL ASSESSMENT FOR THE JANUARY 2005 STORM, WHITMAN PROPERTY, SAN ANTONIO CREEK, VENTURA COUNTY, CALIFORNIA

Birch Creek Geomorphic Assessment and Action Plan

Black Gore Creek 2013 Sediment Source Monitoring and TMDL Sediment Budget

3. MARINE HABITAT RESTORATION

Sessom Creek Sand Bar Removal HCP Task 5.4.6

Rock Sizing for Bank Stabilisation

Geomorphology Geology 450/750 Spring Fluvial Processes Project Analysis of Redwood Creek Field Data Due Wednesday, May 26

Case Study 14. Rocky Creek Vented Box Culvert Ford

Chapter 3 Erosion in the Las Vegas Wash

Materials. Use materials meeting the following.

Four Mile Run Levee Corridor Stream Restoration

River Response. Sediment Water Wood. Confinement. Bank material. Channel morphology. Valley slope. Riparian vegetation.

Wetland & Floodplain Functional Assessments and Mapping To Protect and Restore Riverine Systems in Vermont. Mike Kline and Laura Lapierre Vermont DEC

SECTION G SEDIMENT BUDGET

How Do Human Impacts and Geomorphological Responses Vary with Spatial Scale in the Streams and Rivers of the Illinois Basin?

Bank Erosion and Morphology of the Kaskaskia River

A GEOMORPHOLOGICAL APPROACH TO RESTORATION OF INCISED RIVERS. David L. Rosgen 1

Stream Simulation: A Simple Example

TSEGI WASH 50% DESIGN REPORT

HYDROLOGY AND HYDRAULICS MUSKEG RIVER BRIDGE

Frequently Asked Questions about River Corridors

Sediment Transport Mechanism and Grain Size Distributions in Stony Bed Rivers. S.FUKUOKA 1 and K.OSADA 2

Session C1 - Applying the Stream Functions Pyramid to Geomorphic Assessments and Restoration Design

Defining the Limit of Regulated Areas. C.1 Defining the River or Stream Flood Hazard 138. C.2 Defining the River or Stream Erosion Hazard 139

60 PERCENT DESIGN REPORT HABITAT RESTORATION OF THE CHELAN RIVER REACH 4 AND TAILRACE

Upper Drac River restoration project

Design and Construction

Assignment 1. Measuring River Characteristics- Vernon Creek. Applied Fluvial Geomorphology Field Techniques EESc 435

An environmentally sensitive erosion control technique in the Mekong River Delta: 10 years on

Case Study 2: Twenty-mile Creek Rock Fords

A STUDY OF LOCAL SCOUR AT BRIDGE PIERS OF EL-MINIA

White River Update. Jeanne Stypula, Supervising Engineer. Advisory Committee Meeting April 26, 2016

Rosgen Classification Unnamed Creek South of Dunka Road

Transcription:

Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018 EXISTING CONDITION The proposed Carmel River Bank Stabilization at Rancho San Carlos Road Project (RSC Project) is located at River Mile 3.8 (measured from the Pacific Ocean) just downstream of the Rancho San Carlos Road Bridge (Figure 1). The project area contains two eroding stream banks almost opposite from each other. Concern for the stability of the right bank (looking downstream) on APN 015-251-027, Moratz Property started in 2011 and interim measures such as jute netting, willow planting, and irrigation were carried out in an effort to stabilize the bank. In February of 2017, during a high flow event of 9,570 cubic feet per second at the U.S.G.S Near Carmel gage, the left bank along APN 157-121-027, Quail Lodge Property experienced significant erosion and up to about 55 feet of streambank was eroded along 300 lineal feet (Figure 2). During the high flows, numerous large cottonwood trees toppled out of the river bank and culturally significant Santa Barbara Sedge beds were lost. Currently, the left bank is vulnerable to erosion from high flows because it has lost its protective vegetative cover and is on the outside of a meander bend in an area that can erode during high flows. Because these vulnerable streambanks are so close together, work on one bank can impact the other. Therefore, a comprehensive project addressing both banks is being proposed (Figure 3). PROJECT DESCRIPTION On June 21, 2017, the District contracted with Balance Hydrologics, Inc. (Balance) to provide a design for the RSC Project. Based on investigations of the site, a log crib wall (approximately 160 feet in length) was recommended for stabilizing a portion of the left bank with a smaller boulder log structure (approximately 60 feet long) for the right bank. Balance chose this design because: The riparian corridor is a source of large wood debris to the channel; a log-based structure would be appropriate for the project site. Long-term stability of the site will be enhanced by successful vegetation growth and the development of root networks through the structure by woody vegetation. Banks should be reassembled with a mix of sand, gravel, and cobble for the lower bank; finer material would only be appropriate on the upper bank.

Regulatory agencies prefer projects that incorporate large wood and revegetation versus banks covered in rip rap only. A log crib wall will protect the most severely damaged portion of the left bank. Other options for treating the left bank were considered for instance, boulder barbs and log/boulder toe protection but the crib wall was chosen for a number of reasons. The 2D hydraulic model indicated that shear stress is relatively low at the 10-year design event (at most 1.0 lb./ft. 2 on the left bank) and velocity is at most 8.1 ft/sec. According to stability thresholds for stream restoration materials summarized by Fischenich (2001), a number of treatments would be capable of withstanding these conditions. A purely vegetation based treatment was not selected because the long-term stability of the treatment depends on the successful establishment of vegetation. Moreover, there is high risk for failure of vegetative treatments during the establishment period, which could be as much as four to five years. For example, the probability of a 10-year event which would be expected to cause a vegetative treatment to fail during a 5-year establishment period is approximately 41 percent. On the opposite end of the spectrum from a purely vegetative treatment are hard surfacing options such as rip rap. A hard-surfacing option was not selected because large clasts are not geomorphically appropriate for the project reach. Furthermore, hard surfacing options are predisposed to offsetting a bank erosion problem to downstream reaches. Riprap and similar hard surfacing schemes are not favored by regulatory agencies for similar reasons. Lastly, these types of treatments tend to detract from the aesthetic quality of a system. The log crib wall will provide immediate protection up to the design event, and the plantings within the crib wall will provide long-term protection after the logs have decomposed (anticipated to occur over several decades). Visually, the crib wall will have wood, rock and vegetation elements immediately after construction, with vegetation becoming more dominant as it grows in. The bank roughness introduced by the crib wall will control velocities around the bend and not deflect flow to the next downstream bend, as would a hard-surfacing option. The log structure resembles a wood debris jam, which is geomorphically appropriate for the reach given abundant sources of large woody material along the riparian corridor and in the upper watershed. Large boulders have been used in the past with bank stabilization projects and providing a non-biodegradable means of scour protection was necessary to support the crib wall. The boulders are designed in a staggered pattern to maintain roughness around the bend should the channel continue to incise. The design attempts to maintain the channel width so as to not oppose the prevailing process of meander belt widening, nor adversely affect flood hydraulics. The ballast of the log structure is sufficient for stability, and it does not require extensive keying into the bank that would result in a larger construction footprint. The rootwads in the lower portion of the crib wall will provide benefits to aquatic habitat, as will vegetation in the crib wall once it matures. 2 P a g e

CONSTRUCTION ACTIVITIES Access into the riverbed for equipment would either be from the south riverbank near the Rancho San Carlos Road Bridge or over a ramp downstream at the Cal-Am San Carlos Well site (about a The crib wall begins at the end of the concrete debris on the left bank, and extends for approximately 160 feet downstream. The crib wall was designed to be this length not only to protect the most vulnerable portion of the bank, but also to reshape the bank in a way that will eliminate the scalloped shape that formed after the major failure during winter 2017. The 2D hydraulic model indicated flow eddying within the scalloped area and flow accelerating as it leaves the scalloped area, which suggests that the bank irregularity is susceptible to ongoing erosion. The modest narrowing of the channel mentioned earlier is related to addressing the scalloped bank in order to avoid hydraulic patterns that would increase the risk of further bank erosion. Construction of the left bank crib wall involves excavating below the river bed approximately 6 feet to place 1.5-ton boulders. Logs are then placed on top of these boulders and are back filled with half ton rock and then smaller channel material such as cobbles and gravels as you go up in elevation. Log sizes will be 15 feet long and vary in diameter from 9 to 15 inches in diameter. A final set of boulders are placed at the back of the crib wall structure to anchor the logs. These boulders are eventually buried after the project is complete with a slope of 2:1. The final slope is covered with an erosion control blanket and the whole structure and finished slope is heavily planted with willows, black cottonwoods (Figure 4). The right bank stabilization structure also incorporates boulders, logs with rootwads, and river bed material such as gravel and cobble. The basic design uses 1.5-ton boulders as footers to help support the logs and footer log. Log sizes will be 18 feet by 18 inches in diameter. Log anchors will also be incorporated to secure them to the site. The area will also be revegetated with willows and black cottonwoods (Figure 5). Once vegetation starts to mature at both the crib wall and the right bank structure many of the elements of the design will start to blend in with the surrounding environment. A picture of a previously constructed crib wall with vegetation was provided by Balance Hydrologics (Figure 6). Table 1 Approximate Quantities Cut 280 cubic yards (CY) Fill 680 CY Rock Import 476 CY (approximately 950 tons) Log import 123 3 P a g e

4 P a g e Figure 1. Project located just downstream of Rancho San Carlos Road Bridge

Figure 2. Left streambank after winter of 2017 erosion event (note lack of protective vegetation) Figure 3. Aerial image showing locations of erosion just downstream of Rancho San Carlos Road Bridge 5 P a g e

6 P a g e Carmel River at Rancho San Carlos Road Bridge, March 31, 2017

Figure 4. Example section view of log crib wall Figure 5. Example section view of right bank stabilization structure 7 P a g e

Figure 6. Example of completed log crib wall U:\Larry\Carmel River\2018 Rancho San Carlos Project\Permits\MoCo\Application\3-proj-desc-March 2018.docx 8 P a g e