Experiences with Superconducting Cable & Fault Current Limiter in a German City Center Mark Stemmle

Similar documents
Combined HTS Cable and Fault Current Limiter Project in Germany

Cryogenic and Electrical Test Results of a 30 M HTS Power Cable

Superconducting Cables

Hydra Fault Current Limiting HTS Cable to be Installed in the Consolidated Edison Grid

Status and Progress of a Fault Current Limiting HTS Cable To Be Installed In The Consolidated Edison Grid

Feasibility of HTS DC Cables on Board a Ship

Superconducting cables Development status at Ultera

Latest Status of High Temperature Superconducting Cable Projects

Commissioning testing of a 1 MVA Superconducting transformer featuring 2G HTS Roebel cable

Gesellschaft für Schwerionenforschung mbh (GSI), Planckstrasse 1, D Darmstadt, Germany

Fault Current Limiters

R&D of 22.9kV/50MVA HTS Transmission Power Cable in Korea

KIT-ENERGY CENTRE. KIT The research University in the Helmholtz Association

The development of a Roebel cable based 1 MVA HTS transformer

Fault Current Limiter Based on Coated Conductor

EPRI Technology Watch 2010 Superconducting Cables Fault Current Limiters

Progress in Scale-up of 2G HTS Wire at SuperPower Part III

Superconducting Fault Current Limiters

Superconducting Fault Current Limiters

The Present Status and Prospective of the power transmission by Superconductors in China

Symposium VV: Future Directions in HTS

Grid Issues and Challenges Addressed by High Temperature Superconductor (HTS) Technology

Fault Calculation Methods

Applications Using SuperPower 2G HTS Conductor

TRANSFORMERS. Pascal Tixador. Grenoble INP - Institut Néel / G2Elab. Introduction

High-temperature superconducting magnet for use in Saturated core FCL

TYPE TESTING OF A 13.2 KV, 69 MVA TRIAX HTS CABLE

Status and Future Direction of HTS Power Application in KEPCO

Investigation on the Dielectric Material Parameters and the Electric Conductivity of Syntactic Foam at the Liquid Nitrogen Temperature Range

Experience in manufacturing a large HTS magnet for a SMES

High-Performance 2G HTS Wire for an Efficient and Reliable Electricity Supply

HTS Roadmap for Electric Power Systems October 2015

INSTALLATION AND COMMISSIONING OF TRIAX HTS CABLE

Risk mitigation in the development of a Roebel cable based 1 MVA HTS transformer

Current Lead Optimization for Cryogenic Operation at Intermediate Temperatures. L. Bromberg, P.C. Michael, J.V. Minervini and C.

Opus: University of Bath Online Publication Store

Russian Development Program on HTS Power Cables

Railway Research. Study of Superconducting Fault Current Limiter Device in a AC Railway System. 1. Introduction. International Journal of

Superconductivity project at IASS

2 nd Generation High-Temperature Superconducting Wires for Fault Current Limiter Applications

Superconductivity for Electric Systems DOE 2006 Wire Development Workshop

Keywords: Superconducting Fault Current Limiter (SFCL), Resistive Type SFCL, MATLAB/SIMULINK. Introductions A rapid growth in the power generation

Conductor Requirements for Superconducting Fault Current Limiters

System Technology and Test of CURL 10, a 10 kv, 10 MVA Resistive High-Tc Superconducting Fault Current Limiter

Yeon Suk Choi \ Steven W. Van Sciver \ and Ho-Myung Chang u

Critical Current Properties of HTS Twisted Stacked-Tape Cable in Subcooled- and Pressurized-Liquid Nitrogen

Electrical Power Cables Part 2 Cable Rating Calculations

KINGS COLLEGE OF ENGINEERING Punalkulam

New Transmission Options Case Study Superconductor Cables. Transmission Policy Institute Sheraton Downtown Denver, Colorado April 20-21, 2011

Overhead lines. 110 kv wood tower with guy wires

HTS Cable Integration into Rural Networks with Renewable Energy Resources

Superconducting power cables in Denmark - a case study

SSC-JE EE POWER SYSTEMS: GENERATION, TRANSMISSION & DISTRIBUTION SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL

Independent, accredited testing station Member laboratory of STL and LOVAG TEST CONFIRMATION. on the given range of performed tests

Grounding and Shielding

HiLumi LHC FP7 High Luminosity Large Hadron Collider Design Study. Milestone Report. Cryogenic Scenarios for the Cold Powering System

ECEN 460 Exam 1 Fall 2018

Transient Analysis of a 150 kv Fault Current Limiting High Temperature Superconducting Cable

Module 3 : Sequence Components and Fault Analysis

SHORT QUESTIONS AND ANSWERS. Year/ Semester/ Class : III/ V/ EEE Academic Year: Subject Code/ Name: EE6501/ Power System Analysis

Lecture (5) Power Factor,threephase circuits, and Per Unit Calculations

Chapter 8: Unsymmetrical Faults

DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK

The influence of thermal properties on power transmission characteristics of HVDC cables a factor analysis

Future long distance electricity transmission using HTS HVDC cables

Development of 2 MVA Class Superconducting Fault Current Limiting Transformer (SFCLT) with YBCO Coated Conductors

Three Core XLPE/LSF/SWA/LSF Power Cable

Selecting the current rating for equipment

Materials in high-temperature superconducting cables Dag Willén nkt cables

An Investigation of the Current Distribution in an HTS Triaxial Power Cable and its Operational Impacts on a Power System

PH213 Chapter 24 Solutions

The Booster has three magnet systems for extraction: Kicker Ke, comprising two identical magnets and power supplies Septum Se

Inductance and Current Distribution Analysis of a Prototype HTS Cable

Independent, accredited testing station Member laboratory of STL and LOVAG TEST CONFIRMATION. on the given range of performed tests

Status and outlook on superconducting fault current limiter development in Europe

TRANSMISSION LINES. All aluminum alloy conductor (AAAC) Aluminum conductor alloy reinforced (ACAR)

Coil in Coil Components for the High Voltage Superconducting Resistive Current Limiter CULT 110

Short-circuit protection to a fault: Superconducting fault current limiters

Comparison of the Ecoprofiles of Superconducting and Conventional 25 MVA Transformers using the LCA Methodology

RECENT DEVELOPMENT OF HIGH-TEMPERATURE SUPERCONDUCTING (HTS) CABLE IN SUMITOMO ELECTRIC INDUSTRIES, LTD.

Analysis of DC Power Transmission Using High T c Superconducting Cables

URD Cable Fault Prediction Model

Two examples of efficient superconducting cable applications

CEA Saclay Seminar. Cryogenic Research for HTS Transmission Cables in Korea

15 - Development of HTS High Current Cables and Joints for DC Power and High Field Magnet Applications

New Generation of DC Power Transmission Technology Using HTS Cables

PHY3901 PHY3905. Hall effect and semiconductors Laboratory protocol

Fatima Michael College of Engineering & Technology

Innovative fabrication method of superconducting magnets using high T c superconductors with joints

EE 6501 POWER SYSTEMS UNIT I INTRODUCTION

ELECTRICAL AND THERMAL DESIGN OF UMBILICAL CABLE

An Optimised High Current Impulse Source

HTS versus LTS: physics, technology, and application prospects

NR/RR. Set No. 2 CODE NO: NR/RR210204

RESULTS OF ON-GRID OPERATION OF SUPERCONDUCTOR DYNAMIC SYNCHRONOUS CONDENSER

Single Core XLPE/LSF/AWA/LSF Power Cable

Technische Universität Dresden Lehrstuhl für Kälte- und Kryotechnik Dresden, 01062, Germany

Second Generation HTS Wire for Electric Power Applications

An Introduction to Insulation Resistance Testing

Development of high-efficiency Stirling cryocoolers for high temperature superconducting motors

Transcription:

Experiences with Superconducting Cable & Fault Current Limiter in a German City Center Mark Stemmle mark.stemmle@nexans.com i-pcgrid Workshop San Francisco, CA March 30 th, 2017

Agenda Introduction - Basics of Superconductivity - Cable Design for MV Applications - Advantages of Superconducting Cables AmpaCity Project - Motivation - Installation - Operation Experience - Short Circuit Current Testing What s Next? Conclusions 2 I i-pcgrid Workshop 2017 I 2017-03-30

Electrical resistance Voltage Superconductivity Basics Superconductor Metallic conductor Metallic conductor Superconductor T c Temperature I c Current Electrical resistance drops to zero below critical temperature (T c ) Practical definition of critical current density (I c ) with 1 µv/cm criterion 3 I i-pcgrid Workshop 2017 I 2017-03-30

Concentric Cable Design for MV Applications Inner LN 2 Cooling Phase 1 Phase 2 Phase 3 Screen Former Dielectric 4 I i-pcgrid Workshop 2017 I 2017-03-30 Outer LN 2 Cooling Cable Cryostat

Advantages of HTS Cable Technology > Increased power density through application of HTS cables Avoiding higher voltage levels for power transmission and distribution > Negligible thermal impact on the environment No drying out of soil, no thermal backfill required No maximum laying depth, no bottlenecks at cable crossings > No outer magnetic field during normal operation > Reduced space for substations and for cable installation Simplified cable installation, less civil works Space-savings in urban areas > Increased operating safety due to fault current limitation 5 I i-pcgrid Workshop 2017 I 2017-03-30

Motivation for AmpaCity Project Substation in suburban area HV Substation in suburban area HV Conventional HV cable system MV HV Superconducting MV cable system MV Substation in Substation in MV city center city center 6 I i-pcgrid Workshop 2017 I 2017-03-30

AmpaCity Installation in Essen, Germany Technical specification - 1 km distance between substations - 10 kv system voltage - 2.3 ka operating current (40 MVA) Substation Herkules Cable Joint Substation Dellbrügge System in continuous operation since March 10 th, 2014 Luftbild: "Darstellung aus HK Luftbilder / Karten Lizenz Nr. 197 / 2012 mit Genehmigung vom Amt für Geoinformation, Vermessung und Kataster der Stadt Essen vom 13.02.2012" 7 I i-pcgrid Workshop 2017 I 2017-03-30

Cable Pulling First Length 8 I i-pcgrid Workshop 2017 I 2017-03-30

Installation in Substation Dellbrügge 9 I i-pcgrid Workshop 2017 I 2017-03-30

System Installation in Substation Herkules 10 I i-pcgrid Workshop 2017 I 2017-03-30

Operation Experience > Balancing earth capacitance Compensation of unsymmetrical cable earth capacitances by installing capacitors > Cooling system optimization Modification of vacuum pumps after freezing of humidity and other smaller optimizations > Control system optimization Increase of response time after automatic reclosing for continuous operation after HV faults System operation since commissioning without problems, only few minor optimizations of cooling and control system during operation 11 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Current in A Voltage and Current 900 9 800 8 700 7 600 6 500 5 400 300 4 3 Voltage in kv 200 2 100 1 0 0 12 I i-pcgrid Workshop 2017 I 2017-03-30

Current (ka) Cooling System Design > 4 kw cold power at 67 K > Subcooled pressurized nitrogen 80 60 40 > Forced flow in closed circuit Limited Current Prospective Current Nominal Current > High availability and reliability LN 2 storage tank vacuum pump sub cooler circulation pump 20 0-20 -40 pressure build-up SFCL 0 20 40 60 80 100 120 140 Time (ms) HTS cable 13 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Temperature in K Temperatures 77 76 75 Temperature Substation Dellbrügge 74 73 72 71 70 69 Outlet Temperature Substation Herkules 68 67 Inlet Temperature Substation Herkules 14 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Pressure in bar Pressures 10.0 9.5 Inlet Pressure Substation Herkules 9.0 8.5 8.0 Pressure Substation Dellbrügge 7.5 7.0 6.5 6.0 5.5 Outlet Pressure Substation Herkules 5.0 15 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Mass Flow in g/s Liquid Nitrogen Mass Flow 530 520 510 500 490 480 470 460 450 440 430 420 410 400 16 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Losses in W System Losses at Operating Temperature 2100 2000 1900 1800 1700 1600 1500 1400 1300 17 I i-pcgrid Workshop 2017 I 2017-03-30

17-02-01 17-02-02 17-02-03 17-02-04 17-02-05 17-02-06 17-02-07 17-02-08 17-02-09 17-02-10 17-02-11 17-02-12 17-02-13 17-02-14 17-02-15 17-02-16 17-02-17 17-02-18 17-02-19 17-02-20 17-02-21 17-02-22 17-02-23 17-02-24 17-02-25 17-02-26 17-02-27 17-02-28 17-03-01 17-03-02 17-03-03 17-03-04 17-03-05 17-03-06 17-03-07 17-03-08 17-03-09 17-03-10 17-03-11 17-03-12 Level in % Liquid Nitrogen Storage Tank Level 100 90 80 70 60 50 40 30 20 10 0 18 I i-pcgrid Workshop 2017 I 2017-03-30

Short Circuit Testing in Live Grid Operation Two short circuit tests, three phase short circuit current without earth contact One short circuit test, two phase short circuit current without earth contact One ground fault test, single phase with 5 minutes duration (isolated neutral) One short circuit test, single phase with neutral impedance (< 2 ka) 19 I i-pcgrid Workshop 2017 I 2017-03-30

Current Strom in in ka ka 3-Phase Short Circuit Current 10 9 i_l1 8 7 i_l2 6 5 i_l3 4 3 2 1 0-1200 210 220 230 240 250 260 270 280 290 300 310 320-2 -3-4 -5-6 -7-8 -9 Time Zeit in in ms ms 20 I i-pcgrid Workshop 2017 I 2017-03-30

Current in ka Strom in ka 2-Phase Short Circuit Current 9 8 i_l1 7 i_l2 6 i_l3 5 4 3 2 1 0-1200 210 220 230 240 250 260 270 280 290 300 310 320-2 -3-4 -5-6 -7-8 -9 Time Zeit in ms 21 I i-pcgrid Workshop 2017 I 2017-03-30

Current in ka Strom in ka 1-Phase Short Circuit Current 2,4 2,0 1,6 1,2 0,8 0,4 0,0 200 210 220 230 240 250 260 270 280 290 300 310 320-0,4-0,8-1,2-1,6-2,0 i_l1 i_l2 i_l3-2,4 Time Zeit in in ms ms 22 I i-pcgrid Workshop 2017 I 2017-03-30

Short Circuit Testing Results All tests conducted gave expected results Protokollierung von Strom und Spannung Betriebsparameter des Strombegrenzers AmpaCity system operates exactly as designed, including fault current limitation Tests prove maturity of technology under real grid operating conditions Betriebsbereitschaft nach kurzer Erholzeit Temperaturverlauf Strombegrenzer während wieder einsatzbereit Kurzschluss 23 I i-pcgrid Workshop 2017 I 2017-03-30

ComEd Project (Chicago) In 2015 Nexans was chosen supplier for the project! 24 I i-pcgrid Workshop 2017 I 2017-03-30

Conclusions Superconducting cable and fault current limiter technology has been successfully proven in real grid application AmpaCity system in operation for more than three years Performance during normal operation as expected Short circuit current behavior was verified in grid First commercial projects in progress (Chicago) 25 I i-pcgrid Workshop 2017 I 2017-03-30

Thank you very much for your attention! Dr. Mark Stemmle Nexans Deutschland GmbH Kabelkamp 20 30179 Hannover mark.stemmle@nexans.com 26 I i-pcgrid Workshop 2017 I 2017-03-30