Cornell Caltech Atacama Telescope Project Status. Simon Radford 2005 October 10. Study Status
|
|
- Cordelia Doyle
- 5 years ago
- Views:
Transcription
1 Cornell Caltech Atacama Telescope Project Status Simon Radford 2005 October 10 Study Status Now concluding Concept and Feasibility Study MOU between Cornell and Caltech JPL participation as part of Caltech Study budget: $2 million Study completion Report publication mid December 2005 Review presentation mid January 2006 Peer review panel Formal report for administrations and partners Detailed and accurate cost estimate Major objectives of this phase Identify a telescope concept Investigate feasibility and assess probable cost Identify critical risks Propose plan for entire project 2005 October 10 Surveys with a 25 m Submm Telescope 2
2 Project Principals Riccardo Giovanelli Project Director, Cornell Terry Herter Project Scientist, Cornell Jonas Zmuidinas Project Scientist, Caltech Tom Sebring Project Manager, Cornell Simon Radford Deputy Proj. Mgr., Caltech Paul Goldsmith JPL lead Not meant to devalue other participants! 2005 October 10 Surveys with a 25 m Submm Telescope 3 Committees Study Tasks Overall leadership by Project Scientists Science: Overall Science Objectives and Requirements Instrumentation: Defines Instrument Suite Operations: Operations Plans and Cost Est. Internal Studies Technical Tasks Undertaken by JPL, Caltech, Cornell Provide Specific Design, Analysis, and Reports to Study Contracts Seven Industrial Study Contracts in Place Facility, Dome, Mount, Mirror Panels (3), M2/M3 mechanisms Detailed Reports, Presentations, and Cost Estimates We Are On Course to Complete the Feasibility Concept Study as Planned 2005 October 10 Surveys with a 25 m Submm Telescope 4
3 Chajnantor Plateau (5000 m) CBI APEX ALMA CCAT 5590 m 2005 October 10 Surveys with a 25 m Submm Telescope Dietrich/Caltech 5 Site selection status Chajnantor plateau (5050 m) better than Mauna Kea CBI, APEX, ALMA; twice as much time for 350 m Sairecabur (5500 m) better than Chajnantor plateau 30% more 350 m; 1 km from Bolivia, outside science preserve Expect Cerro Chajnantor (5590 m) similar to Sairecabur Radiosonde measurements of water vapor profiles Permission to deploy characterization equipment pending Japanese planning to deploy equipment for IR telescope Baseline plan: Cerro Chajnantor (5590 m) Fallback: Chajnantor plateau, near APEX Option: Sairecabur (5500 m) Quantify relative costs, benefits Continue quantitative measurements of other sites 2005 October 10 Surveys with a 25 m Submm Telescope 6
4 Facilities M3 Engineering & Technology, Tucson Have designed facilities for most recent US observatories Familiar with Atacama region through work on the ALMA project Mountain top facility Minimum size for functions Use Chilean construction methods & materials Includes oxygen enrichment Base facility Near San Pedro de Atacama Similar to APEX base 2005 October 10 Surveys with a 25 m Submm Telescope 7 Dome AMEC Dynamic Structures, Vancouver Designer of largest astronomical domes Experience with large moving structures Calotte Design Unique motions Structurally efficient lowest cost Highest reliability Very Large 50 m diameter! Study results Structure, shutter, mechanisms Concepts developed and designed Cost estimate ~$13 million, consistent with allocation Next Phase Anticipate cost reduction by integration of commercial systems and structures Central Mount Normal Pivot Bearing Steel Normal and Uplift Rollers Bogie Frame Polyurethane Radial Roller 2005 October 10 Surveys with a 25 m Submm Telescope 8
5 Telescope Mount Vertex RSI (General Dynamics) Built many radars, radiotelescopes, and optical telescopes Particular expertise in servo control for pointing and tracking CCAT mount challenges Precision pointing and tracking required High acceleration for scanning motions Large 25 m primary mirror Study results CAD model, mass estimate Includes primary mirror truss Control analysis Mount will probably meet scanning and pointing requirements Cost estimate due this week 2005 October 10 Surveys with a 25 m Submm Telescope 9 Primary Mirror Mirror divided into annular groups of segments Only six different segment types Suggests replication from masters Supported by bolted steel truss 2005 October 10 Surveys with a 25 m Submm Telescope 10
6 Three Approaches to Segment Fabrication CFRP-Al Sandwich CMA, Tucson, AZ Used successfully in SMT Very lightweight and stiff SiC with nanolaminates Xinetics, Devens, MA Doesn t meet cost, weight, or schedule Formed borosilicate glass ITT, Rochester, NY Lightweight core Emerging technology Glass and CFRP merit further development 0.56 m diameter glass panel 5.3 kg m October 10 Surveys with a 25 m Submm Telescope 11 Initial Instrumentation Suite Other Study Areas Large format bolometer array imager Medium resolution spectrometer Sensors for telescope Calibration sensor for initial segment and M1/M2 alignment (JPL) Operations sensors to maintain segment alignment Hybrid approach: opto-electronic and laser metrology (JPL/Cornell) Optical guider for precision pointing and tracking (Cornell) Operations planning Logistics, shipping, staffing High altitude risk mitigation Systems engineering Error budgets, analysis, simulations (Caltech & Cornell) 2005 October 10 Surveys with a 25 m Submm Telescope 12
7 Project Schedule More detailed schedule being developed as part of current study Schedule is controlled by partnership and funding development Critical path analysis and optimization are part of the next phase, Engineering Concept Design 2005 October 10 Surveys with a 25 m Submm Telescope 13 Program Funding Target: $100 M Two science instruments Contingency: 10% Rates notional probably correct 2005 October 10 Surveys with a 25 m Submm Telescope 14
8 Summary The current Feasiblity and Concept Study is well along in meeting the objectives of the Cornell Caltech MOU Investigation to date shows that CCAT is technically feasible and can be built for a cost of $100 million Efforts underway to secure funding for the next, Engineering Concept Design phase ($3 million) Development of full partnership and strategy to get to full funding should have the highest priority Identification of forefront science indicates CCAT will be an extremely significant asset in astronomical research 2005 October 10 Surveys with a 25 m Submm Telescope 15
Princeton Astrophysics Community Meeting
Princeton Astrophysics Community Meeting Michael Moore Program Executive Astrophysics Division Science Mission Directorate September 4, 2012 Timeline 2011 2012 10 January: Identification of hardware availability
More informationReport of the Review Committee Cornell Caltech Atacama Telescope Feasibility/Concept Design Study
Report of the Review Committee Cornell Caltech Atacama Telescope Feasibility/Concept Design Study Overview: Cornell University, the California Institute of Technology, and the Jet Propulsion Laboratory
More informationGEMINI 8-M Telescopes Project
GEMINI 8-M Telescopes Project RPT-PS-G0065 The Gemini Instrumentation Program F. C. Gillett, D. A. Simons March 25, 1996 GEMINI PROJECT OFFICE 950 N. Cherry Ave. Tucson, Arizona 85719 Phone: (520) 318-8545
More informationTeam X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team
Team X Study Summary for ASMCS Theia Jet Propulsion Laboratory, California Institute of Technology with contributions from the Theia Team P. Douglas Lisman, NASA Jet Propulsion Laboratory David Spergel,
More informationThe Advanced Technology Solar Telescope and NSO. Jim Ulvestad Craig Foltz March 7, 2013
The Advanced Technology Solar Telescope and NSO Jim Ulvestad Craig Foltz March 7, 2013 The ATST Science Case ATST s relevance re-affirmed by recent NRC Solar and Space Physics and Astronomy & Astrophysics
More informationTelescope Project Development Seminar
Telescope Project Development Seminar Session 1a: The Project Matt Johns 1/20/2017 U. Tokyo 2/9/2017 Telescope Project Development 1 Information regarding the course Hi, my name is Matt Johns I am a Project
More informationScience at ESO. Mark Casali
Science at ESO Mark Casali La Silla Paranal ALMA Visual/infrared light La Silla telescopes incl. 3.6m and NTT VLT, VLTI, VISTA and VST on Paranal E-ELT construction on Armazones Instrumentation development
More informationOverview of Thirty Meter Telescope Project
Overview of Thirty Meter Telescope Project L. Stepp November 16, 2010 TMT.TEL.PRE.10.016.REL02 1 Outline Introduction to TMT TMT site selection TMT partners Summary of TMT design TMT requirements for segments
More informationOBSERVATORIO DEL ROQUE
ALTERNATE SITE: OBSERVATORIO DEL ROQUE DE LOS MUCHACHOS December 2016 www.tmt.org Table of Contents 1. Executive summary... 3 2. Introduction... 5 3. Considerations for alternate sites... 6 4. The Selection
More informationan NSF Facility Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array
an NSF Facility Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array ALMA s Contributions to Outflows, Winds and Jets Al Wootten
More informationInternational Facilities
International Facilities A report to the National Committee for Astronomy for the Australian Astronomy Decadal Plan 2006-2015 By Working Group 3.1 September 2005 Executive Summary Over the past decade
More informationCredit: ESO/B. Tafreshi (twanight.org) Operating the Very Large Telescope
Credit: ESO/B. Tafreshi (twanight.org) Operating the Very Large Telescope Introduction: From scientific idea to data legacy Credit: ESO/B. Tafreshi (twanight.org) The Very Large Telescope (VLT) was built
More informationDevelopments in Sub/Millimeter Astronomy in Chile. Mónica Rubio Universidad de Chile
Developments in Sub/Millimeter Astronomy in Chile Mónica Rubio Universidad de Chile Llama Workshop, FAPESP, 9 aug 2011 The start 1.2 m Columbia radio telescope @ CTIO in 1984 Collaboration between Columbia
More informationCCAT-prime: CCAT-p. 01 July 2016 CCAT-p Overview 1
CCAT-prime: CCAT-p 01 July 2016 CCAT-p Overview 1 6-meter off-axis submm telescope located at CCAT site at 5600 meters on Cerro Chajnantor Surface accuracy of
More informationInternational Projects at ASIAA
International Projects at ASIAA ASIAA in 2011 EACOA at Kyoto 11.07.11 Hualin 10.24.11 19 ALMA Telescopes ALMA at AOS at 5000m Galaxy Merger Workshop 10.24.11 1 Masato Convincing Another Donor? It is great
More informationAsia-Pacific ground-base Optical Satellite Observation System APOSOS
Asia-Pacific ground-base Optical Satellite Observation System APOSOS Center for Research and Application of Space Debris National Astronomical Observatories, CAS GUO Xiaozhong Oct 2011 Outline Space debris
More informationx Contents Segmented Mirror Telescopes Metal and Lightweight Mirrors Mirror Polishing
Contents 1 Fundamentals of Optical Telescopes... 1 1.1 A Brief History of Optical Telescopes.................... 1 1.2 General Astronomical Requirements..................... 6 1.2.1 Angular Resolution.............................
More informationGiant Segmented Mirror Telescope Science Working Group
Giant Segmented Mirror Telescope Science Working Group Rolf-Peter Kudritzki 1 for the GSMT Science Working Group 1 Chair, GSMT Science Working Group Institute for Astronomy, University of Hawaii http://www.aura-nio.noao.edu/gsmt_swg/
More informationGEMINI 8-M Telescopes Project
GEMINI 8-M Telescopes Project RPT-I-G0057 Principles Behind the Gemini Instrumentation Program M. Mountain, F. Gillett, D. Robertson, D. Simons GEMINI PROJECT OFFICE 950 N. Cherry Ave. Tucson, Arizona
More informationThe CCAT 25 m diameter submillimeter-wave telescope
The CCAT 25 m diameter submillimeter-wave telescope David Woody *a, Steve Padin b, Eric Chauvin c, Bruno Clavel c, German Cortes d, Andy Kissil e, John Lou e, Paul Rasmussen a, David Redding e and Jeff
More informationOutline HST HST. HST& JWST CARMA and ALMA SOFIA Chandra Blackbodies. Doppler Effect. Homework #5 was due today.
Outline Homework #5 was due today. Next homework is #6 due next Friday at 11:50 am. There will be another make-up nighttime observing session in November. Stay tuned. I will be teaching Paul s class on
More information1 Naval Research Laboratory Remote Sensing Division, Code Aberdeen Ave SE Kirtland AFB, NM 87117
Carbon Fiber Reinforced Polymer (CFRP) Telescope Program at the Naval Research Laboratory Sergio R. Restaino 1, Ty Martinez 1, Jonathan R. Andrews 1, Christopher C. Wilcox 1, S. Teare 2, Robert Romeo 3,
More informationSOFIA Science Highlights Cycle 4 Progress Cycle 5 Call for Proposals
SOFIA Science Highlights Cycle 4 Progress Cycle 5 Call for Proposals Erick Young SOFIA Science Center Executive Summary Since Last SUG Completed Cycle 3 319 GI Time 122 GTO Time 5 DDT Horsehead Nebula
More informationPhoto: Sean Goebel, IfA CFHT status update
CFHT status update CFHT status update Staff changes CFHT status update CFHT status update Current instrumentation Partner status Publications Science Highlights Development update Current instrumentation
More informationThe Principles of Astronomical Telescope Design
The Principles of Astronomical Telescope Design Jingquan Cheng National Radio Astronomy Observatory Charlottesville, Virginia,.USA " 4y Springer Fundamentals of Optical Telescopes 1 1.1 A Brief History
More informationUniversity of California Santa Cruz, CA, USA Contents
University of California Santa Cruz, CA, 95064 USA jnelson@ucolick.org Contents 1. Introduction 1.1. Organization 1.2. Site Selection 1.3. Schedule 1.4. Cost 2. Telescope Overview 3. Key Features of TMT
More informationThe Future of Cosmology
The Future of Cosmology Ay21, March 10, 2010 Announcements: final exams available beginning 9am on March 12 (Friday), from Swarnima (note that the final will not be distributed electronically). finals
More informationStefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017
James Webb Space Telescope Stefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017 JWST Vital Stats General Observatory: 5 years required; 10 years goal Primary mirror:
More informationThe Large Atacama Submillimeter Telescope
The Large Atacama Submillimeter Telescope Terry Herter, a Robert Brown, a Riccardo Giovanelli, a Gordon Stacey, a Jonas Zmuidzinas, b David Woody, c Sunil Golwala, b and Andrew Blain b a Department of
More informationThe Stratospheric Observatory for Infrared Astronomy (SOFIA)
The Stratospheric Observatory for Infrared Astronomy (SOFIA) a and E. E. Becklin b a University of Minnesota b Universities Space Research Association This talk is at: http://www.sofia.usra.edu/science/speakers/index.html
More informationKitt Peak Nightly Observing Program
Kitt Peak Nightly Observing Program Splendors of the Universe on YOUR Night! Many pictures are links to larger versions. Click here for the Best images of the OTOP Gallery and more information. Clouds
More informationNIST: Promoting U.S. Innovation and Industrial Competitiveness. George W. Arnold, Eng. Sc.D. Deputy Director, Technology Services
NIST: Promoting U.S. Innovation and Industrial Competitiveness George W. Arnold, Eng. Sc.D. Deputy Director, Technology Services NIST Today: Mission To promote U.S. innovation and industrial competitiveness
More informationTelescopes. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. Key Ideas:
Telescopes A Warm Up Exercise If we measure the wavelengths of emission lines and absorption lines from the same gas, we find that (ignoring any Doppler shifts) a) Some emission lines shift to the red
More informationPlanning for the 2020 Decadal Survey An Astrophysics Division White Paper
Planning for the 2020 Decadal Survey An Astrophysics Division White Paper POC: Paul Hertz, Astrophysics Division Director (paul.hertz@nasa.gov) January 4, 2015 Background The next Decadal Survey in Astronomy
More informationPERFORMANCE. 1 Scheduled and successfully completed observing time
PERFORMANCE INDICATORS The ATNF assesses its performance through key performance indicators, based on those used generally by CSIRO but adapted to be appropriate for a National Facility. Unless otherwise
More informationLessons learned from the TMT site testing campaign
Lessons learned from the TMT site testing campaign T. Travouillon* a, S.G. Els b, R.L. Riddle c, M. Schöck a, A.W. Skidmore a, a TMT Observatory Corporation, 2632 E. Washington Blvd, Pasadena, CA 91107,
More informationQUIET-I and QUIET-II:
QUIET-I and QUIET-II: HEMT-based coherent CMB polarimetry Great Lakes Cosmology Workshop X June 14, 2010 Immanuel Buder (for the QUIET Collaboration) Department of Physics, U. of Chicago Outline Science
More informationCCAT. Gordon Stacey. Cornell University. Gull
CCAT Gordon Stacey Cornell University Gull CCAT Scientific Inspiration Measure the star and characterize the history of star formation in galaxies through cosmic time Photometric surveys to resolve the
More informationThe Quantum Sensor Challenge Designing a System for a Space Mission. Astrid Heske European Space Agency The Netherlands
The Quantum Sensor Challenge Designing a System for a Space Mission Astrid Heske European Space Agency The Netherlands Rencontres de Moriond - Gravitation, La Thuile, 2017 Quantum Sensors in Lab Experiments
More informationScience with a Wide-Field Telescope in Space. NASA HQ Perspective. Richard Griffiths. Astrophysics Division Science Mission Directorate
Science with a Wide-Field Telescope in Space NASA HQ Perspective Richard Griffiths Astrophysics Division Science Mission Directorate February 13, 2012 1 Mission Timeline Last updated: January 4, 2012 ORION
More informationNotes: Reference: Merline, W. J. and S. B. Howell (1995). "A Realistic Model for Point-sources Imaged on Array Detectors: The Model and Initial
Notes: Notes: Notes: Reference: Merline, W. J. and S. B. Howell (1995). "A Realistic Model for Point-sources Imaged on Array Detectors: The Model and Initial Results." Experimental Astronomy 6: 163-210.
More informationCCAT: Key Science Goals. Jonas Zmuidzinas and the CCAT Science Steering Committee
CCAT: Key Science Goals Jonas Zmuidzinas and the CCAT Science Steering Committee Science reports in CCAT Study Co-Chairs Terry Herter (Cornell) and Jonas Zmuidzinas (CIT) Science Theme Lead Distant Galaxies
More informationGBO Call for Proposals: Semester 2017A
GBO Call for Proposals: Semester 2017A 30 June 2016 The Green Bank Observatory (GBO) invites scientists to participate in the GBO's Semester 2017A Call for Proposals for the Green Bank Telescope (GBT).
More informationESO and the ELT project. Robert Pfab Abingdon, 24. Nov 2010
ESO and the ELT project. A 1bn opportunity Robert Pfab Abingdon, 24. Nov 2010 Contents Introduction to the European Southern Observatory Large telescopes enabling science The European Extremely Large Telescope
More informationUltra-High Angular Resolution VLBI
Ultra-High Angular Resolution VLBI Rusen Lu ( 路如森 ) rslu@haystack.mit.edu MIT Haystack Observatory Ultra-High Angular Resolution VLBI enabled by mm-vlbi Rusen Lu ( 路如森 ) rslu@haystack.mit.edu MIT Haystack
More informationMAJOR SCIENTIFIC INSTRUMENTATION
MAJOR SCIENTIFIC INSTRUMENTATION APPLICATION OF OPERATING RESOURCES FY 2005 ACTUAL FY 2006 ESTIMATE FY 2007 ESTIMATE FEDERAL APPROPRIATIONS GENERAL TRUST DONOR/SPONSOR DESIGNATED GOV T GRANTS & CONTRACTS
More informationHimawari-8 BUFR Development for Winds Processing and Radiances - Packaging for Algorithm Integration Team (AIT)
Sandy Supplemental Grant Recipient Quarterly Progress Report Himawari-8 BUFR Development for Winds Processing and Radiances - Packaging for Algorithm Integration Team (AIT) Award Number: NA14NWS4830052
More informationThe Atacama Large Millimeter/submillimeter Array
The Atacama Large Millimeter/submillimeter Array Richard E. Hills a and Anthony J. Beasley a a ALMA, Av El Golf 40, Piso 18, Santiago, Chile ABSTRACT The Atacama Large Millimeter/submillimeter Array (ALMA)
More informationCollecting Light. In a dark-adapted eye, the iris is fully open and the pupil has a diameter of about 7 mm. pupil
Telescopes Collecting Light The simplest means of observing the Universe is the eye. The human eye is sensitive to light with a wavelength of about 400 and 700 nanometers. In a dark-adapted eye, the iris
More informationSOFIA Stratospheric Observatory For Infrared Astronomy
1 SOFIA Stratospheric Observatory For Infrared Astronomy E.E. Becklin SOFIA Chief Scientist ISSTT 2008 April 28, 2008 2 Outline of Material Overview of SOFIA Progress to Date Science Schedule and Future
More informationStatus of Interferometry Planning in Europe
Status of Interferometry Planning in Europe Andreas Glindemann November 13, 2006 with input from V. Foresto, Ch. Haniff, T. Herbst, G. Perrin, J. Surdej Future Directions for Interferometry Tucson Arizona,
More informationEuropean Southern Observatory ELT. The Extremely Large Telescope. The World s Biggest Eye on the Sky
European Southern Observatory ELT The Extremely Large The World s Biggest Eye on the Sky Building a Giant On a mountain in the Atacama Desert in northern Chile, ESO, the European Southern Observatory,
More informationThe Giant Magellan Telescope ( GMT Statement )
The Giant Magellan Telescope ( GMT Statement ) Yes We Can! Wendy Freedman Carnegie Observatories Chair, GMT Board Science with Giant Telescopes: Public Participation in TMT and GMT, Chicago June 16, 2008
More informationNovember 3, 2014 Eric P. Smith JWST Program Office
November 3, 014 Eric P. Smith JWST Program Office 1 SINCE LAST CAA MEETING... Completed of 3 recommended GAO schedule risk analyses for this year. Mutually agreed to drop 3 rd. Will perform cost-risk study
More informationInstrumentation: Enabling Science in the Ground- Based O/IR System
Instrumentation: Enabling Science in the Ground- Based O/IR System For: The 2 nd Community Workshop on the Ground-Based O/IR System Taft Armandroff (NOAO Gemini Science Center) Elements of the Observing
More informationDISCUSSION ITEM DEVELOPMENTS REGARDING THE THIRTY METER TELESCOPE AND THE PARTICIPATION OF THE UNIVERSITY OF CALIFORNIA EXECUTIVE SUMMARY
Office of the President E2 TO MEMBERS OF THE COMMITTEE ON EDUCATION POLICY: For Meeting of DISCUSSION ITEM DEVELOPMENTS REGARDING THE THIRTY METER TELESCOPE AND THE PARTICIPATION OF THE UNIVERSITY OF CALIFORNIA
More informationProject Scientist Status Report Al Wootten Interim Project Scientist JAO/NRAO
Project Scientist Status Report Al Wootten Interim Project Scientist JAO/NRAO Report ASAC Considering Charges from Board Ch 4: The ASAC should read and discuss the Operations Plan. Depending on the questions
More informationLight and Telescopes
Light and Telescopes The key thing to note is that light and matter interact. This can happen in four principal ways: 1) emission a hot object such as the filament in a light bulb emits visible light 2)
More informationSITE selection for a m telescope (ELT)
SITE selection for a 30-100m telescope (ELT) Interim Report, June 19 2001 Alistair R. Walker (awalker@noao.edu) Sites WWW site: http://www.ctio.noao.edu/sitetests/ NIO WWW site: http://www.aura-nio.noao.edu/
More informationOWL: Further steps in designing the telescope mechanical structure and in assessing its performance
OWL: Further steps in designing the telescope mechanical structure and in assessing its performance Enzo Brunetto, Franz Koch, Marco Quattri European Southern Observatory ABSTRACT The baseline concept
More informationFrom the VLT to ALMA and to the E-ELT
From the VLT to ALMA and to the E-ELT Mission Develop and operate world-class observing facilities for astronomical research Organize collaborations in astronomy Intergovernmental treaty-level organization
More informationThe Navy Precision Optical Interferometer for SSA applications: an update
The Navy Precision Optical Interferometer for SSA applications: an update Sergio R. Restaino, Naval Research Laboratory, Remote Sensing Division J.R. Andrews, J.T. Armstrong, E. Baines, J.C. Clark and
More informationGemini Telescopes Update
U S G P U.S. GEMINI PROGRAM Gemini Telescopes Update The progress on the Gemini telescope project has been significant in the last few months, both in commissioning efforts and in science productivity.
More informationMemo 106 Composite Applications for Radio Telescopes (CART): The Mk2 Reflector Results.
Memo 106 Composite Applications for Radio Telescopes (CART): The Mk2 Reflector Results. D. Chalmers G. Lacy 01/09 www.skatelescope.org/pages/page_memos.htm 1 SKA Memo 106 Composite Applications for Radio
More informationOverview of TMT origins
Canada and the Thirty Meter Telescope Project Prepared by Prof. Ray Carlberg, Director, TMT Canada 23 August 2005 The choice of Canadians to join with Caltech, the University of California and AURA (the
More informationTechnology Developments for ESO at the IAC
Jornada ESO 2011, Granada, 10-11/02/2011 Technology Developments for ESO at the IAC Head of Technology Division 1 Technology involvement in ESO Instruments: Espresso for the VLT CODEX and HARMONI for the
More informationAPPENDIX 4.4.A STRAWMAN STRUCTURAL DESIGN OF A 30-M GSMT
APPENDIX 4.4.A STRAWMAN STRUCTURAL DESIGN OF A 30-M GSMT Report prepared for the New Initiatives Office by Simpson Gumpertz & Heger Inc., January 2001. Strawman Structural Design of a 30-m Giant Segmented
More informationNight Comes to the Cumberlands and It s Awesome: Promoting Night Sky Conservation and Development in the Upper Cumberland
Night Comes to the Cumberlands and It s Awesome: Promoting Night Sky Conservation and Development in the Upper Cumberland Jean Mercer Assistant Vice Chancellor for Research Office of Sponsored Programs
More informationEducational Product Teachers Grades K-12 EG MSFC
Educational Product Teachers Grades K-12 NASA Spacelink Optics: An Educators Guide With Activities In Science and Mathematics is available in electronic format through NASA Spacelink one of the Agency
More informationScientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument
Scientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument Oliver Krause (Max Planck Institute for Astronomy, Heidelberg) on behalf of Gillian Wright (Royal Observatory Edinburgh)
More informationHighlights of the program of. The European Southern Observatory
Highlights of the program of The European Southern Observatory ESO, the European Southern Observatory Established in1962, with the main mission of providing its member states with world-class facilities
More informationNRAO Call for Proposals: Semester 2015B
NRAO Call for Proposals: Semester 2015B 2 January 2015 NRAO Call for Proposals: Semester 2015B The National Radio Astronomy Observatory (NRAO) invites scientists to participate in the NRAO Semester 2015B
More informationMadawaska Highlands Observatory 1m f/7 Ritcher-Chrétien Nasmyth Telescope
Madawaska Highlands Observatory 1m f/7 Ritcher-Chrétien Nasmyth Telescope Technical Specifications WFT One-Meter f/7 Ritchey-Chrétien Nasmyth Science Telescope Madawaska Highlands Observatory Corp. in
More informationDevelopment of surface metrology for the Giant Magellan Telescope primary mirror
Development of surface metrology for the Giant Magellan Telescope primary mirror J. H. Burge a,b, W. Davison a, H. M. Martin a, C. Zhao b a Steward Observatory, University of Arizona, Tucson, AZ 85721,
More informationAustralian Membership of the Giant Magellan Telescope Project Charles Jenkins, ANU Deputy Australian ELT Project Scientist
Australian Membership of the Giant Magellan Telescope Project Charles Jenkins, ANU Deputy Australian ELT Project Scientist Introduction This proposal argues that the astronomical community should strategically
More information1mm VLBI Call for Proposals: Cycle 4
1mm VLBI Call for Proposals: Cycle 4 22 March 2016 Introduction The National Radio Astronomy Observatory (NRAO) invites proposals for 1mm Very Long Baseline Interferometry (VLBI) using the phased output
More informationSUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)
SUBPART 217.1--MULTIYEAR CONTRACTING (Revised December 19, 2006) 217.103 Definitions. As used in this subpart-- Advance procurement means an exception to the full funding policy that allows acquisition
More informationCollaborating on Mega Science Facilities
Collaborating on Mega Science Facilities Barry Barish Caltech LIGO Livingston, Louisiana NEON Workshop Tucson 13-April-09 Big Science at NSF? Advancements in science» Individual Investigators The heart
More informationCCAT. Riccardo Giovanelli, John Carpenter, Simon Radford, Thomas Sebring, Thomas Soifer, Gordon Stacey, Jonas Zmuidzinas & the CCAT Collaboration
CCAT Riccardo Giovanelli, John Carpenter, Simon Radford, Thomas Sebring, Thomas Soifer, Gordon Stacey, Jonas Zmuidzinas & the CCAT Collaboration Summary Star formation drives the evolution of baryonic
More informationSUBARU Telescope Damages and Recovery from the Earthquake
1 N a t io na l SUBARU A s t r o n o m ic a l J a p an of O b s e r v a t o r y SUBARU Telescope Damages and Recovery from the Earthquake Tomonori USUDA (SUBARU Telescope) Contents: 1. Brief Overview of
More informationFujiwara, H., et al. 2009, ApJL, 695, L88 Hot debris dust around HD
Recent Japanese Publications Using Gemini Tanaka, M., Lidman, C., Bower, R.~G., Demarco, R., Finoguenov, A., Kodama, T., Nakata, F., & Rosati, P. 2009, A&A, 507, 671 Star formation activities i i of galaxies
More informationCoursework Booklet 2
Level 3 Applied Science UNIT 16: Astronomy and Space Science PHYSICS SECTION Coursework Booklet 2 1 P a g e Astronomy and space science Learning aim B Undertake measurement and observation of astronomical
More informationJanuary Jennifer Lotz Director
Gemini Observatory AAS 233 Open House January 8 2019 Jennifer Lotz Director Gemini Observatory Overview & Strategic Vision Jennifer Lotz, Gemini Observatory (this talk) Gemini Planet Imager Science and
More informationMax-Planck-Institut für Radioastronomie, Bonn Istituto di Radioastronomia - INAF, Bologna
RadioNet3 & SKA Franco Mantovani Project Scientist RadioNet3 Max-Planck-Institut für Radioastronomie, Bonn Istituto di Radioastronomia - INAF, Bologna RadioNet3 Advanced Radio Astronomy in Europe www.radionet-eu.org
More informationMAJOR SCIENTIFIC INSTRUMENTATION
MAJOR SCIENTIFIC INSTRUMENTATION APPLICATION OF OPERATING RESOURCES FEDERAL APPROPRIATIONS GENERAL TRUST DONOR/SPONSOR DESIGNATED GOV T GRANTS & CONTRACTS FY 2006 ACTUAL FY 2007 ESTIMATE FY 2008 ESTIMATE
More informationWelcome and Introduction
Welcome and Introduction Ninth International Symposium on Space Terahertz Technology Carl Kukkonen Director, Center for Space Microelectronics Technology JPL March 17-19, 1998.,.; 1 SUBMILLIMETER AND THz
More informationDevelopment of breakthrough technology for building next generation ground based telescopes
Development of breakthrough technology for building next generation ground based telescopes SUMMARY Mass production and control technology now exists to build telescope primary mirrors out of panels consisting
More informationThe Cassegrain ADC for Keck I Preliminary Design Review Process and Charter September 15, 2003 By Sean Adkins
CALIFORNIA ASSOCIATION FOR RESEARCH IN ASTRONOMY By Sean Adkins INTRODUCTION The Technical Facilities group of the UCO/Lick Observatory located on the Santa Cruz campus of the University of California
More informationASTE Status. Shin ichiro Asayama, Daisuke Iono and the ASTE team
ASTE Status Shin ichiro Asayama, Daisuke Iono and the ASTE team 1 Atacama Submillimeter Telescope Experiment (ASTE) Specifications 10-m sub-mm telescope located at Pampla La Bola within Chajnantor area
More informationDistortion mapping correction in aspheric null testing
Distortion mapping correction in aspheric null testing M. Novak, C. Zhao, J. H. Burge College of Optical Sciences, 1630 East University Boulevard, Tucson, AZ, 85721 ABSTRACT We describe methods to correct
More informationFundamental Limits to Wavefront Sensing in the Submillimeter
Fundamental Limits to Wavefront Sensing in the Submillimeter E. Serabyn Jet Propulsion Laboratory, California Institute of Technology, 4800 Oak Grove Drive, Pasadena, CA, USA 91109 Copyright 2006 Society
More informationAbout ESO. ESO. Astronomy made in Europe
About ESO ESO is the foremost intergovernmental European Science and Technology organisation in the field of ground-based astrophysics. It is supported by 12 countries: Belgium, Denmark, France, Finland,
More informationTable of Contents and Executive Summary Final Report, ReSTAR Committee Renewing Small Telescopes for Astronomical Research (ReSTAR)
For the complete report, see http://www.noao.edu/system/restar 1 TableofContentsandExecutiveSummary FinalReport,ReSTARCommittee RenewingSmallTelescopesforAstronomical Research(ReSTAR) ForthecompletereportandmoreinformationabouttheReSTARcommittee,
More informationSite Characterization
OWL Phase A Review - Garching - 2 nd to 4 th Nov 2005 Site Characterization (Presented by M. Sarazin) 1 Site Characterization: Parameter Space Cloudiness; Humidity, Precipitable Water Vapour; Atmospheric
More informationSOFIA Science Metrics Update
SOFIA Science Metrics Update Bill Reach SOFIA Deputy SMO Director WReach@usra.edu Astrophysics Advisory Committee NASA Headquarters July 2017 Kimberly Ennico Smith NASA SOFIA Project Scientist Kimberly.Ennico@nasa.gov
More informationSouth Bay Coastal Ocean Observing System California Clean Beaches Initiative
South Bay Coastal Ocean Observing System California Clean Beaches Initiative Second Quarterly Report January, 2003 to City of Imperial Beach Eric Terrill 1 1 Scripps Institution of Oceanography, University
More informationThe Soar Telescope Project: A Four-Meter Telescope Focused on Image Quality
Header for SPIE use The Soar Telescope Project: A Four-Meter Telescope Focused on Image Quality Thomas A. Sebring, Gerald Cecil, & Gilberto Moretto SOAR Telescope Project, National Optical Astronomy Observatories
More informationThe Characterization and Minimization. of Noise in a Charge Coupled Device for. the Magellan Telescopes
The Characterization and Minimization of Noise in a Charge Coupled Device for the Magellan Telescopes by Jennifer J. Yu Submitted to the Department of Electrical Engineering and Computer Science in Partial
More informationSpace Telescopes Asteroid Mining Space Manufacturing. Wefunder.com/SpaceFab
Space Telescopes Asteroid Mining Space Manufacturing Wefunder.com/SpaceFab Business Road Map Cost efficient high value space telescopes Unique business model Deployable optics technology Asteroid mining
More informationHimawari-8 BUFR Development for Winds Processing and Radiances Cloud Mask, Cloud Phase, Cloud Height
Sandy Supplemental Grant Recipient Quarterly Progress Report Himawari-8 BUFR Development for Winds Processing and Radiances Award Number: NA14NES4830006 The National Oceanic and Atmospheric Administration
More information