Cornell Caltech Atacama Telescope Project Status. Simon Radford 2005 October 10. Study Status

Size: px
Start display at page:

Download "Cornell Caltech Atacama Telescope Project Status. Simon Radford 2005 October 10. Study Status"

Transcription

1 Cornell Caltech Atacama Telescope Project Status Simon Radford 2005 October 10 Study Status Now concluding Concept and Feasibility Study MOU between Cornell and Caltech JPL participation as part of Caltech Study budget: $2 million Study completion Report publication mid December 2005 Review presentation mid January 2006 Peer review panel Formal report for administrations and partners Detailed and accurate cost estimate Major objectives of this phase Identify a telescope concept Investigate feasibility and assess probable cost Identify critical risks Propose plan for entire project 2005 October 10 Surveys with a 25 m Submm Telescope 2

2 Project Principals Riccardo Giovanelli Project Director, Cornell Terry Herter Project Scientist, Cornell Jonas Zmuidinas Project Scientist, Caltech Tom Sebring Project Manager, Cornell Simon Radford Deputy Proj. Mgr., Caltech Paul Goldsmith JPL lead Not meant to devalue other participants! 2005 October 10 Surveys with a 25 m Submm Telescope 3 Committees Study Tasks Overall leadership by Project Scientists Science: Overall Science Objectives and Requirements Instrumentation: Defines Instrument Suite Operations: Operations Plans and Cost Est. Internal Studies Technical Tasks Undertaken by JPL, Caltech, Cornell Provide Specific Design, Analysis, and Reports to Study Contracts Seven Industrial Study Contracts in Place Facility, Dome, Mount, Mirror Panels (3), M2/M3 mechanisms Detailed Reports, Presentations, and Cost Estimates We Are On Course to Complete the Feasibility Concept Study as Planned 2005 October 10 Surveys with a 25 m Submm Telescope 4

3 Chajnantor Plateau (5000 m) CBI APEX ALMA CCAT 5590 m 2005 October 10 Surveys with a 25 m Submm Telescope Dietrich/Caltech 5 Site selection status Chajnantor plateau (5050 m) better than Mauna Kea CBI, APEX, ALMA; twice as much time for 350 m Sairecabur (5500 m) better than Chajnantor plateau 30% more 350 m; 1 km from Bolivia, outside science preserve Expect Cerro Chajnantor (5590 m) similar to Sairecabur Radiosonde measurements of water vapor profiles Permission to deploy characterization equipment pending Japanese planning to deploy equipment for IR telescope Baseline plan: Cerro Chajnantor (5590 m) Fallback: Chajnantor plateau, near APEX Option: Sairecabur (5500 m) Quantify relative costs, benefits Continue quantitative measurements of other sites 2005 October 10 Surveys with a 25 m Submm Telescope 6

4 Facilities M3 Engineering & Technology, Tucson Have designed facilities for most recent US observatories Familiar with Atacama region through work on the ALMA project Mountain top facility Minimum size for functions Use Chilean construction methods & materials Includes oxygen enrichment Base facility Near San Pedro de Atacama Similar to APEX base 2005 October 10 Surveys with a 25 m Submm Telescope 7 Dome AMEC Dynamic Structures, Vancouver Designer of largest astronomical domes Experience with large moving structures Calotte Design Unique motions Structurally efficient lowest cost Highest reliability Very Large 50 m diameter! Study results Structure, shutter, mechanisms Concepts developed and designed Cost estimate ~$13 million, consistent with allocation Next Phase Anticipate cost reduction by integration of commercial systems and structures Central Mount Normal Pivot Bearing Steel Normal and Uplift Rollers Bogie Frame Polyurethane Radial Roller 2005 October 10 Surveys with a 25 m Submm Telescope 8

5 Telescope Mount Vertex RSI (General Dynamics) Built many radars, radiotelescopes, and optical telescopes Particular expertise in servo control for pointing and tracking CCAT mount challenges Precision pointing and tracking required High acceleration for scanning motions Large 25 m primary mirror Study results CAD model, mass estimate Includes primary mirror truss Control analysis Mount will probably meet scanning and pointing requirements Cost estimate due this week 2005 October 10 Surveys with a 25 m Submm Telescope 9 Primary Mirror Mirror divided into annular groups of segments Only six different segment types Suggests replication from masters Supported by bolted steel truss 2005 October 10 Surveys with a 25 m Submm Telescope 10

6 Three Approaches to Segment Fabrication CFRP-Al Sandwich CMA, Tucson, AZ Used successfully in SMT Very lightweight and stiff SiC with nanolaminates Xinetics, Devens, MA Doesn t meet cost, weight, or schedule Formed borosilicate glass ITT, Rochester, NY Lightweight core Emerging technology Glass and CFRP merit further development 0.56 m diameter glass panel 5.3 kg m October 10 Surveys with a 25 m Submm Telescope 11 Initial Instrumentation Suite Other Study Areas Large format bolometer array imager Medium resolution spectrometer Sensors for telescope Calibration sensor for initial segment and M1/M2 alignment (JPL) Operations sensors to maintain segment alignment Hybrid approach: opto-electronic and laser metrology (JPL/Cornell) Optical guider for precision pointing and tracking (Cornell) Operations planning Logistics, shipping, staffing High altitude risk mitigation Systems engineering Error budgets, analysis, simulations (Caltech & Cornell) 2005 October 10 Surveys with a 25 m Submm Telescope 12

7 Project Schedule More detailed schedule being developed as part of current study Schedule is controlled by partnership and funding development Critical path analysis and optimization are part of the next phase, Engineering Concept Design 2005 October 10 Surveys with a 25 m Submm Telescope 13 Program Funding Target: $100 M Two science instruments Contingency: 10% Rates notional probably correct 2005 October 10 Surveys with a 25 m Submm Telescope 14

8 Summary The current Feasiblity and Concept Study is well along in meeting the objectives of the Cornell Caltech MOU Investigation to date shows that CCAT is technically feasible and can be built for a cost of $100 million Efforts underway to secure funding for the next, Engineering Concept Design phase ($3 million) Development of full partnership and strategy to get to full funding should have the highest priority Identification of forefront science indicates CCAT will be an extremely significant asset in astronomical research 2005 October 10 Surveys with a 25 m Submm Telescope 15

Princeton Astrophysics Community Meeting

Princeton Astrophysics Community Meeting Princeton Astrophysics Community Meeting Michael Moore Program Executive Astrophysics Division Science Mission Directorate September 4, 2012 Timeline 2011 2012 10 January: Identification of hardware availability

More information

Report of the Review Committee Cornell Caltech Atacama Telescope Feasibility/Concept Design Study

Report of the Review Committee Cornell Caltech Atacama Telescope Feasibility/Concept Design Study Report of the Review Committee Cornell Caltech Atacama Telescope Feasibility/Concept Design Study Overview: Cornell University, the California Institute of Technology, and the Jet Propulsion Laboratory

More information

GEMINI 8-M Telescopes Project

GEMINI 8-M Telescopes Project GEMINI 8-M Telescopes Project RPT-PS-G0065 The Gemini Instrumentation Program F. C. Gillett, D. A. Simons March 25, 1996 GEMINI PROJECT OFFICE 950 N. Cherry Ave. Tucson, Arizona 85719 Phone: (520) 318-8545

More information

Team X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team

Team X Study Summary for ASMCS Theia. Jet Propulsion Laboratory, California Institute of Technology. with contributions from the Theia Team Team X Study Summary for ASMCS Theia Jet Propulsion Laboratory, California Institute of Technology with contributions from the Theia Team P. Douglas Lisman, NASA Jet Propulsion Laboratory David Spergel,

More information

The Advanced Technology Solar Telescope and NSO. Jim Ulvestad Craig Foltz March 7, 2013

The Advanced Technology Solar Telescope and NSO. Jim Ulvestad Craig Foltz March 7, 2013 The Advanced Technology Solar Telescope and NSO Jim Ulvestad Craig Foltz March 7, 2013 The ATST Science Case ATST s relevance re-affirmed by recent NRC Solar and Space Physics and Astronomy & Astrophysics

More information

Telescope Project Development Seminar

Telescope Project Development Seminar Telescope Project Development Seminar Session 1a: The Project Matt Johns 1/20/2017 U. Tokyo 2/9/2017 Telescope Project Development 1 Information regarding the course Hi, my name is Matt Johns I am a Project

More information

Science at ESO. Mark Casali

Science at ESO. Mark Casali Science at ESO Mark Casali La Silla Paranal ALMA Visual/infrared light La Silla telescopes incl. 3.6m and NTT VLT, VLTI, VISTA and VST on Paranal E-ELT construction on Armazones Instrumentation development

More information

Overview of Thirty Meter Telescope Project

Overview of Thirty Meter Telescope Project Overview of Thirty Meter Telescope Project L. Stepp November 16, 2010 TMT.TEL.PRE.10.016.REL02 1 Outline Introduction to TMT TMT site selection TMT partners Summary of TMT design TMT requirements for segments

More information

OBSERVATORIO DEL ROQUE

OBSERVATORIO DEL ROQUE ALTERNATE SITE: OBSERVATORIO DEL ROQUE DE LOS MUCHACHOS December 2016 www.tmt.org Table of Contents 1. Executive summary... 3 2. Introduction... 5 3. Considerations for alternate sites... 6 4. The Selection

More information

an NSF Facility Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array

an NSF Facility Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array an NSF Facility Atacama Large Millimeter/submillimeter Array Expanded Very Large Array Robert C. Byrd Green Bank Telescope Very Long Baseline Array ALMA s Contributions to Outflows, Winds and Jets Al Wootten

More information

International Facilities

International Facilities International Facilities A report to the National Committee for Astronomy for the Australian Astronomy Decadal Plan 2006-2015 By Working Group 3.1 September 2005 Executive Summary Over the past decade

More information

Credit: ESO/B. Tafreshi (twanight.org) Operating the Very Large Telescope

Credit: ESO/B. Tafreshi (twanight.org) Operating the Very Large Telescope Credit: ESO/B. Tafreshi (twanight.org) Operating the Very Large Telescope Introduction: From scientific idea to data legacy Credit: ESO/B. Tafreshi (twanight.org) The Very Large Telescope (VLT) was built

More information

Developments in Sub/Millimeter Astronomy in Chile. Mónica Rubio Universidad de Chile

Developments in Sub/Millimeter Astronomy in Chile. Mónica Rubio Universidad de Chile Developments in Sub/Millimeter Astronomy in Chile Mónica Rubio Universidad de Chile Llama Workshop, FAPESP, 9 aug 2011 The start 1.2 m Columbia radio telescope @ CTIO in 1984 Collaboration between Columbia

More information

CCAT-prime: CCAT-p. 01 July 2016 CCAT-p Overview 1

CCAT-prime: CCAT-p. 01 July 2016 CCAT-p Overview 1 CCAT-prime: CCAT-p 01 July 2016 CCAT-p Overview 1 6-meter off-axis submm telescope located at CCAT site at 5600 meters on Cerro Chajnantor Surface accuracy of

More information

International Projects at ASIAA

International Projects at ASIAA International Projects at ASIAA ASIAA in 2011 EACOA at Kyoto 11.07.11 Hualin 10.24.11 19 ALMA Telescopes ALMA at AOS at 5000m Galaxy Merger Workshop 10.24.11 1 Masato Convincing Another Donor? It is great

More information

Asia-Pacific ground-base Optical Satellite Observation System APOSOS

Asia-Pacific ground-base Optical Satellite Observation System APOSOS Asia-Pacific ground-base Optical Satellite Observation System APOSOS Center for Research and Application of Space Debris National Astronomical Observatories, CAS GUO Xiaozhong Oct 2011 Outline Space debris

More information

x Contents Segmented Mirror Telescopes Metal and Lightweight Mirrors Mirror Polishing

x Contents Segmented Mirror Telescopes Metal and Lightweight Mirrors Mirror Polishing Contents 1 Fundamentals of Optical Telescopes... 1 1.1 A Brief History of Optical Telescopes.................... 1 1.2 General Astronomical Requirements..................... 6 1.2.1 Angular Resolution.............................

More information

Giant Segmented Mirror Telescope Science Working Group

Giant Segmented Mirror Telescope Science Working Group Giant Segmented Mirror Telescope Science Working Group Rolf-Peter Kudritzki 1 for the GSMT Science Working Group 1 Chair, GSMT Science Working Group Institute for Astronomy, University of Hawaii http://www.aura-nio.noao.edu/gsmt_swg/

More information

GEMINI 8-M Telescopes Project

GEMINI 8-M Telescopes Project GEMINI 8-M Telescopes Project RPT-I-G0057 Principles Behind the Gemini Instrumentation Program M. Mountain, F. Gillett, D. Robertson, D. Simons GEMINI PROJECT OFFICE 950 N. Cherry Ave. Tucson, Arizona

More information

The CCAT 25 m diameter submillimeter-wave telescope

The CCAT 25 m diameter submillimeter-wave telescope The CCAT 25 m diameter submillimeter-wave telescope David Woody *a, Steve Padin b, Eric Chauvin c, Bruno Clavel c, German Cortes d, Andy Kissil e, John Lou e, Paul Rasmussen a, David Redding e and Jeff

More information

Outline HST HST. HST& JWST CARMA and ALMA SOFIA Chandra Blackbodies. Doppler Effect. Homework #5 was due today.

Outline HST HST. HST& JWST CARMA and ALMA SOFIA Chandra Blackbodies. Doppler Effect. Homework #5 was due today. Outline Homework #5 was due today. Next homework is #6 due next Friday at 11:50 am. There will be another make-up nighttime observing session in November. Stay tuned. I will be teaching Paul s class on

More information

1 Naval Research Laboratory Remote Sensing Division, Code Aberdeen Ave SE Kirtland AFB, NM 87117

1 Naval Research Laboratory Remote Sensing Division, Code Aberdeen Ave SE Kirtland AFB, NM 87117 Carbon Fiber Reinforced Polymer (CFRP) Telescope Program at the Naval Research Laboratory Sergio R. Restaino 1, Ty Martinez 1, Jonathan R. Andrews 1, Christopher C. Wilcox 1, S. Teare 2, Robert Romeo 3,

More information

SOFIA Science Highlights Cycle 4 Progress Cycle 5 Call for Proposals

SOFIA Science Highlights Cycle 4 Progress Cycle 5 Call for Proposals SOFIA Science Highlights Cycle 4 Progress Cycle 5 Call for Proposals Erick Young SOFIA Science Center Executive Summary Since Last SUG Completed Cycle 3 319 GI Time 122 GTO Time 5 DDT Horsehead Nebula

More information

Photo: Sean Goebel, IfA CFHT status update

Photo: Sean Goebel, IfA CFHT status update CFHT status update CFHT status update Staff changes CFHT status update CFHT status update Current instrumentation Partner status Publications Science Highlights Development update Current instrumentation

More information

The Principles of Astronomical Telescope Design

The Principles of Astronomical Telescope Design The Principles of Astronomical Telescope Design Jingquan Cheng National Radio Astronomy Observatory Charlottesville, Virginia,.USA " 4y Springer Fundamentals of Optical Telescopes 1 1.1 A Brief History

More information

University of California Santa Cruz, CA, USA Contents

University of California Santa Cruz, CA, USA Contents University of California Santa Cruz, CA, 95064 USA jnelson@ucolick.org Contents 1. Introduction 1.1. Organization 1.2. Site Selection 1.3. Schedule 1.4. Cost 2. Telescope Overview 3. Key Features of TMT

More information

The Future of Cosmology

The Future of Cosmology The Future of Cosmology Ay21, March 10, 2010 Announcements: final exams available beginning 9am on March 12 (Friday), from Swarnima (note that the final will not be distributed electronically). finals

More information

Stefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017

Stefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017 James Webb Space Telescope Stefanie Milam Deputy Project Scientist for Planetary Science NASA GSFC January 12, 2017 JWST Vital Stats General Observatory: 5 years required; 10 years goal Primary mirror:

More information

The Large Atacama Submillimeter Telescope

The Large Atacama Submillimeter Telescope The Large Atacama Submillimeter Telescope Terry Herter, a Robert Brown, a Riccardo Giovanelli, a Gordon Stacey, a Jonas Zmuidzinas, b David Woody, c Sunil Golwala, b and Andrew Blain b a Department of

More information

The Stratospheric Observatory for Infrared Astronomy (SOFIA)

The Stratospheric Observatory for Infrared Astronomy (SOFIA) The Stratospheric Observatory for Infrared Astronomy (SOFIA) a and E. E. Becklin b a University of Minnesota b Universities Space Research Association This talk is at: http://www.sofia.usra.edu/science/speakers/index.html

More information

Kitt Peak Nightly Observing Program

Kitt Peak Nightly Observing Program Kitt Peak Nightly Observing Program Splendors of the Universe on YOUR Night! Many pictures are links to larger versions. Click here for the Best images of the OTOP Gallery and more information. Clouds

More information

NIST: Promoting U.S. Innovation and Industrial Competitiveness. George W. Arnold, Eng. Sc.D. Deputy Director, Technology Services

NIST: Promoting U.S. Innovation and Industrial Competitiveness. George W. Arnold, Eng. Sc.D. Deputy Director, Technology Services NIST: Promoting U.S. Innovation and Industrial Competitiveness George W. Arnold, Eng. Sc.D. Deputy Director, Technology Services NIST Today: Mission To promote U.S. innovation and industrial competitiveness

More information

Telescopes. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. Key Ideas:

Telescopes. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. A Warm Up Exercise. Key Ideas: Telescopes A Warm Up Exercise If we measure the wavelengths of emission lines and absorption lines from the same gas, we find that (ignoring any Doppler shifts) a) Some emission lines shift to the red

More information

Planning for the 2020 Decadal Survey An Astrophysics Division White Paper

Planning for the 2020 Decadal Survey An Astrophysics Division White Paper Planning for the 2020 Decadal Survey An Astrophysics Division White Paper POC: Paul Hertz, Astrophysics Division Director (paul.hertz@nasa.gov) January 4, 2015 Background The next Decadal Survey in Astronomy

More information

PERFORMANCE. 1 Scheduled and successfully completed observing time

PERFORMANCE. 1 Scheduled and successfully completed observing time PERFORMANCE INDICATORS The ATNF assesses its performance through key performance indicators, based on those used generally by CSIRO but adapted to be appropriate for a National Facility. Unless otherwise

More information

Lessons learned from the TMT site testing campaign

Lessons learned from the TMT site testing campaign Lessons learned from the TMT site testing campaign T. Travouillon* a, S.G. Els b, R.L. Riddle c, M. Schöck a, A.W. Skidmore a, a TMT Observatory Corporation, 2632 E. Washington Blvd, Pasadena, CA 91107,

More information

QUIET-I and QUIET-II:

QUIET-I and QUIET-II: QUIET-I and QUIET-II: HEMT-based coherent CMB polarimetry Great Lakes Cosmology Workshop X June 14, 2010 Immanuel Buder (for the QUIET Collaboration) Department of Physics, U. of Chicago Outline Science

More information

CCAT. Gordon Stacey. Cornell University. Gull

CCAT. Gordon Stacey. Cornell University. Gull CCAT Gordon Stacey Cornell University Gull CCAT Scientific Inspiration Measure the star and characterize the history of star formation in galaxies through cosmic time Photometric surveys to resolve the

More information

The Quantum Sensor Challenge Designing a System for a Space Mission. Astrid Heske European Space Agency The Netherlands

The Quantum Sensor Challenge Designing a System for a Space Mission. Astrid Heske European Space Agency The Netherlands The Quantum Sensor Challenge Designing a System for a Space Mission Astrid Heske European Space Agency The Netherlands Rencontres de Moriond - Gravitation, La Thuile, 2017 Quantum Sensors in Lab Experiments

More information

Science with a Wide-Field Telescope in Space. NASA HQ Perspective. Richard Griffiths. Astrophysics Division Science Mission Directorate

Science with a Wide-Field Telescope in Space. NASA HQ Perspective. Richard Griffiths. Astrophysics Division Science Mission Directorate Science with a Wide-Field Telescope in Space NASA HQ Perspective Richard Griffiths Astrophysics Division Science Mission Directorate February 13, 2012 1 Mission Timeline Last updated: January 4, 2012 ORION

More information

Notes: Reference: Merline, W. J. and S. B. Howell (1995). "A Realistic Model for Point-sources Imaged on Array Detectors: The Model and Initial

Notes: Reference: Merline, W. J. and S. B. Howell (1995). A Realistic Model for Point-sources Imaged on Array Detectors: The Model and Initial Notes: Notes: Notes: Reference: Merline, W. J. and S. B. Howell (1995). "A Realistic Model for Point-sources Imaged on Array Detectors: The Model and Initial Results." Experimental Astronomy 6: 163-210.

More information

CCAT: Key Science Goals. Jonas Zmuidzinas and the CCAT Science Steering Committee

CCAT: Key Science Goals. Jonas Zmuidzinas and the CCAT Science Steering Committee CCAT: Key Science Goals Jonas Zmuidzinas and the CCAT Science Steering Committee Science reports in CCAT Study Co-Chairs Terry Herter (Cornell) and Jonas Zmuidzinas (CIT) Science Theme Lead Distant Galaxies

More information

GBO Call for Proposals: Semester 2017A

GBO Call for Proposals: Semester 2017A GBO Call for Proposals: Semester 2017A 30 June 2016 The Green Bank Observatory (GBO) invites scientists to participate in the GBO's Semester 2017A Call for Proposals for the Green Bank Telescope (GBT).

More information

ESO and the ELT project. Robert Pfab Abingdon, 24. Nov 2010

ESO and the ELT project. Robert Pfab Abingdon, 24. Nov 2010 ESO and the ELT project. A 1bn opportunity Robert Pfab Abingdon, 24. Nov 2010 Contents Introduction to the European Southern Observatory Large telescopes enabling science The European Extremely Large Telescope

More information

Ultra-High Angular Resolution VLBI

Ultra-High Angular Resolution VLBI Ultra-High Angular Resolution VLBI Rusen Lu ( 路如森 ) rslu@haystack.mit.edu MIT Haystack Observatory Ultra-High Angular Resolution VLBI enabled by mm-vlbi Rusen Lu ( 路如森 ) rslu@haystack.mit.edu MIT Haystack

More information

MAJOR SCIENTIFIC INSTRUMENTATION

MAJOR SCIENTIFIC INSTRUMENTATION MAJOR SCIENTIFIC INSTRUMENTATION APPLICATION OF OPERATING RESOURCES FY 2005 ACTUAL FY 2006 ESTIMATE FY 2007 ESTIMATE FEDERAL APPROPRIATIONS GENERAL TRUST DONOR/SPONSOR DESIGNATED GOV T GRANTS & CONTRACTS

More information

Himawari-8 BUFR Development for Winds Processing and Radiances - Packaging for Algorithm Integration Team (AIT)

Himawari-8 BUFR Development for Winds Processing and Radiances - Packaging for Algorithm Integration Team (AIT) Sandy Supplemental Grant Recipient Quarterly Progress Report Himawari-8 BUFR Development for Winds Processing and Radiances - Packaging for Algorithm Integration Team (AIT) Award Number: NA14NWS4830052

More information

The Atacama Large Millimeter/submillimeter Array

The Atacama Large Millimeter/submillimeter Array The Atacama Large Millimeter/submillimeter Array Richard E. Hills a and Anthony J. Beasley a a ALMA, Av El Golf 40, Piso 18, Santiago, Chile ABSTRACT The Atacama Large Millimeter/submillimeter Array (ALMA)

More information

Collecting Light. In a dark-adapted eye, the iris is fully open and the pupil has a diameter of about 7 mm. pupil

Collecting Light. In a dark-adapted eye, the iris is fully open and the pupil has a diameter of about 7 mm. pupil Telescopes Collecting Light The simplest means of observing the Universe is the eye. The human eye is sensitive to light with a wavelength of about 400 and 700 nanometers. In a dark-adapted eye, the iris

More information

SOFIA Stratospheric Observatory For Infrared Astronomy

SOFIA Stratospheric Observatory For Infrared Astronomy 1 SOFIA Stratospheric Observatory For Infrared Astronomy E.E. Becklin SOFIA Chief Scientist ISSTT 2008 April 28, 2008 2 Outline of Material Overview of SOFIA Progress to Date Science Schedule and Future

More information

Status of Interferometry Planning in Europe

Status of Interferometry Planning in Europe Status of Interferometry Planning in Europe Andreas Glindemann November 13, 2006 with input from V. Foresto, Ch. Haniff, T. Herbst, G. Perrin, J. Surdej Future Directions for Interferometry Tucson Arizona,

More information

European Southern Observatory ELT. The Extremely Large Telescope. The World s Biggest Eye on the Sky

European Southern Observatory ELT. The Extremely Large Telescope. The World s Biggest Eye on the Sky European Southern Observatory ELT The Extremely Large The World s Biggest Eye on the Sky Building a Giant On a mountain in the Atacama Desert in northern Chile, ESO, the European Southern Observatory,

More information

The Giant Magellan Telescope ( GMT Statement )

The Giant Magellan Telescope ( GMT Statement ) The Giant Magellan Telescope ( GMT Statement ) Yes We Can! Wendy Freedman Carnegie Observatories Chair, GMT Board Science with Giant Telescopes: Public Participation in TMT and GMT, Chicago June 16, 2008

More information

November 3, 2014 Eric P. Smith JWST Program Office

November 3, 2014 Eric P. Smith JWST Program Office November 3, 014 Eric P. Smith JWST Program Office 1 SINCE LAST CAA MEETING... Completed of 3 recommended GAO schedule risk analyses for this year. Mutually agreed to drop 3 rd. Will perform cost-risk study

More information

Instrumentation: Enabling Science in the Ground- Based O/IR System

Instrumentation: Enabling Science in the Ground- Based O/IR System Instrumentation: Enabling Science in the Ground- Based O/IR System For: The 2 nd Community Workshop on the Ground-Based O/IR System Taft Armandroff (NOAO Gemini Science Center) Elements of the Observing

More information

DISCUSSION ITEM DEVELOPMENTS REGARDING THE THIRTY METER TELESCOPE AND THE PARTICIPATION OF THE UNIVERSITY OF CALIFORNIA EXECUTIVE SUMMARY

DISCUSSION ITEM DEVELOPMENTS REGARDING THE THIRTY METER TELESCOPE AND THE PARTICIPATION OF THE UNIVERSITY OF CALIFORNIA EXECUTIVE SUMMARY Office of the President E2 TO MEMBERS OF THE COMMITTEE ON EDUCATION POLICY: For Meeting of DISCUSSION ITEM DEVELOPMENTS REGARDING THE THIRTY METER TELESCOPE AND THE PARTICIPATION OF THE UNIVERSITY OF CALIFORNIA

More information

Project Scientist Status Report Al Wootten Interim Project Scientist JAO/NRAO

Project Scientist Status Report Al Wootten Interim Project Scientist JAO/NRAO Project Scientist Status Report Al Wootten Interim Project Scientist JAO/NRAO Report ASAC Considering Charges from Board Ch 4: The ASAC should read and discuss the Operations Plan. Depending on the questions

More information

Light and Telescopes

Light and Telescopes Light and Telescopes The key thing to note is that light and matter interact. This can happen in four principal ways: 1) emission a hot object such as the filament in a light bulb emits visible light 2)

More information

SITE selection for a m telescope (ELT)

SITE selection for a m telescope (ELT) SITE selection for a 30-100m telescope (ELT) Interim Report, June 19 2001 Alistair R. Walker (awalker@noao.edu) Sites WWW site: http://www.ctio.noao.edu/sitetests/ NIO WWW site: http://www.aura-nio.noao.edu/

More information

OWL: Further steps in designing the telescope mechanical structure and in assessing its performance

OWL: Further steps in designing the telescope mechanical structure and in assessing its performance OWL: Further steps in designing the telescope mechanical structure and in assessing its performance Enzo Brunetto, Franz Koch, Marco Quattri European Southern Observatory ABSTRACT The baseline concept

More information

From the VLT to ALMA and to the E-ELT

From the VLT to ALMA and to the E-ELT From the VLT to ALMA and to the E-ELT Mission Develop and operate world-class observing facilities for astronomical research Organize collaborations in astronomy Intergovernmental treaty-level organization

More information

The Navy Precision Optical Interferometer for SSA applications: an update

The Navy Precision Optical Interferometer for SSA applications: an update The Navy Precision Optical Interferometer for SSA applications: an update Sergio R. Restaino, Naval Research Laboratory, Remote Sensing Division J.R. Andrews, J.T. Armstrong, E. Baines, J.C. Clark and

More information

Gemini Telescopes Update

Gemini Telescopes Update U S G P U.S. GEMINI PROGRAM Gemini Telescopes Update The progress on the Gemini telescope project has been significant in the last few months, both in commissioning efforts and in science productivity.

More information

Memo 106 Composite Applications for Radio Telescopes (CART): The Mk2 Reflector Results.

Memo 106 Composite Applications for Radio Telescopes (CART): The Mk2 Reflector Results. Memo 106 Composite Applications for Radio Telescopes (CART): The Mk2 Reflector Results. D. Chalmers G. Lacy 01/09 www.skatelescope.org/pages/page_memos.htm 1 SKA Memo 106 Composite Applications for Radio

More information

Overview of TMT origins

Overview of TMT origins Canada and the Thirty Meter Telescope Project Prepared by Prof. Ray Carlberg, Director, TMT Canada 23 August 2005 The choice of Canadians to join with Caltech, the University of California and AURA (the

More information

Technology Developments for ESO at the IAC

Technology Developments for ESO at the IAC Jornada ESO 2011, Granada, 10-11/02/2011 Technology Developments for ESO at the IAC Head of Technology Division 1 Technology involvement in ESO Instruments: Espresso for the VLT CODEX and HARMONI for the

More information

APPENDIX 4.4.A STRAWMAN STRUCTURAL DESIGN OF A 30-M GSMT

APPENDIX 4.4.A STRAWMAN STRUCTURAL DESIGN OF A 30-M GSMT APPENDIX 4.4.A STRAWMAN STRUCTURAL DESIGN OF A 30-M GSMT Report prepared for the New Initiatives Office by Simpson Gumpertz & Heger Inc., January 2001. Strawman Structural Design of a 30-m Giant Segmented

More information

Night Comes to the Cumberlands and It s Awesome: Promoting Night Sky Conservation and Development in the Upper Cumberland

Night Comes to the Cumberlands and It s Awesome: Promoting Night Sky Conservation and Development in the Upper Cumberland Night Comes to the Cumberlands and It s Awesome: Promoting Night Sky Conservation and Development in the Upper Cumberland Jean Mercer Assistant Vice Chancellor for Research Office of Sponsored Programs

More information

Educational Product Teachers Grades K-12 EG MSFC

Educational Product Teachers Grades K-12 EG MSFC Educational Product Teachers Grades K-12 NASA Spacelink Optics: An Educators Guide With Activities In Science and Mathematics is available in electronic format through NASA Spacelink one of the Agency

More information

Scientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument

Scientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument Scientific Capability of the James Webb Space Telescope and the Mid-InfraRed Instrument Oliver Krause (Max Planck Institute for Astronomy, Heidelberg) on behalf of Gillian Wright (Royal Observatory Edinburgh)

More information

Highlights of the program of. The European Southern Observatory

Highlights of the program of. The European Southern Observatory Highlights of the program of The European Southern Observatory ESO, the European Southern Observatory Established in1962, with the main mission of providing its member states with world-class facilities

More information

NRAO Call for Proposals: Semester 2015B

NRAO Call for Proposals: Semester 2015B NRAO Call for Proposals: Semester 2015B 2 January 2015 NRAO Call for Proposals: Semester 2015B The National Radio Astronomy Observatory (NRAO) invites scientists to participate in the NRAO Semester 2015B

More information

Madawaska Highlands Observatory 1m f/7 Ritcher-Chrétien Nasmyth Telescope

Madawaska Highlands Observatory 1m f/7 Ritcher-Chrétien Nasmyth Telescope Madawaska Highlands Observatory 1m f/7 Ritcher-Chrétien Nasmyth Telescope Technical Specifications WFT One-Meter f/7 Ritchey-Chrétien Nasmyth Science Telescope Madawaska Highlands Observatory Corp. in

More information

Development of surface metrology for the Giant Magellan Telescope primary mirror

Development of surface metrology for the Giant Magellan Telescope primary mirror Development of surface metrology for the Giant Magellan Telescope primary mirror J. H. Burge a,b, W. Davison a, H. M. Martin a, C. Zhao b a Steward Observatory, University of Arizona, Tucson, AZ 85721,

More information

Australian Membership of the Giant Magellan Telescope Project Charles Jenkins, ANU Deputy Australian ELT Project Scientist

Australian Membership of the Giant Magellan Telescope Project Charles Jenkins, ANU Deputy Australian ELT Project Scientist Australian Membership of the Giant Magellan Telescope Project Charles Jenkins, ANU Deputy Australian ELT Project Scientist Introduction This proposal argues that the astronomical community should strategically

More information

1mm VLBI Call for Proposals: Cycle 4

1mm VLBI Call for Proposals: Cycle 4 1mm VLBI Call for Proposals: Cycle 4 22 March 2016 Introduction The National Radio Astronomy Observatory (NRAO) invites proposals for 1mm Very Long Baseline Interferometry (VLBI) using the phased output

More information

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006)

SUBPART MULTIYEAR CONTRACTING (Revised December 19, 2006) SUBPART 217.1--MULTIYEAR CONTRACTING (Revised December 19, 2006) 217.103 Definitions. As used in this subpart-- Advance procurement means an exception to the full funding policy that allows acquisition

More information

Collaborating on Mega Science Facilities

Collaborating on Mega Science Facilities Collaborating on Mega Science Facilities Barry Barish Caltech LIGO Livingston, Louisiana NEON Workshop Tucson 13-April-09 Big Science at NSF? Advancements in science» Individual Investigators The heart

More information

CCAT. Riccardo Giovanelli, John Carpenter, Simon Radford, Thomas Sebring, Thomas Soifer, Gordon Stacey, Jonas Zmuidzinas & the CCAT Collaboration

CCAT. Riccardo Giovanelli, John Carpenter, Simon Radford, Thomas Sebring, Thomas Soifer, Gordon Stacey, Jonas Zmuidzinas & the CCAT Collaboration CCAT Riccardo Giovanelli, John Carpenter, Simon Radford, Thomas Sebring, Thomas Soifer, Gordon Stacey, Jonas Zmuidzinas & the CCAT Collaboration Summary Star formation drives the evolution of baryonic

More information

SUBARU Telescope Damages and Recovery from the Earthquake

SUBARU Telescope Damages and Recovery from the Earthquake 1 N a t io na l SUBARU A s t r o n o m ic a l J a p an of O b s e r v a t o r y SUBARU Telescope Damages and Recovery from the Earthquake Tomonori USUDA (SUBARU Telescope) Contents: 1. Brief Overview of

More information

Fujiwara, H., et al. 2009, ApJL, 695, L88 Hot debris dust around HD

Fujiwara, H., et al. 2009, ApJL, 695, L88 Hot debris dust around HD Recent Japanese Publications Using Gemini Tanaka, M., Lidman, C., Bower, R.~G., Demarco, R., Finoguenov, A., Kodama, T., Nakata, F., & Rosati, P. 2009, A&A, 507, 671 Star formation activities i i of galaxies

More information

Coursework Booklet 2

Coursework Booklet 2 Level 3 Applied Science UNIT 16: Astronomy and Space Science PHYSICS SECTION Coursework Booklet 2 1 P a g e Astronomy and space science Learning aim B Undertake measurement and observation of astronomical

More information

January Jennifer Lotz Director

January Jennifer Lotz Director Gemini Observatory AAS 233 Open House January 8 2019 Jennifer Lotz Director Gemini Observatory Overview & Strategic Vision Jennifer Lotz, Gemini Observatory (this talk) Gemini Planet Imager Science and

More information

Max-Planck-Institut für Radioastronomie, Bonn Istituto di Radioastronomia - INAF, Bologna

Max-Planck-Institut für Radioastronomie, Bonn Istituto di Radioastronomia - INAF, Bologna RadioNet3 & SKA Franco Mantovani Project Scientist RadioNet3 Max-Planck-Institut für Radioastronomie, Bonn Istituto di Radioastronomia - INAF, Bologna RadioNet3 Advanced Radio Astronomy in Europe www.radionet-eu.org

More information

MAJOR SCIENTIFIC INSTRUMENTATION

MAJOR SCIENTIFIC INSTRUMENTATION MAJOR SCIENTIFIC INSTRUMENTATION APPLICATION OF OPERATING RESOURCES FEDERAL APPROPRIATIONS GENERAL TRUST DONOR/SPONSOR DESIGNATED GOV T GRANTS & CONTRACTS FY 2006 ACTUAL FY 2007 ESTIMATE FY 2008 ESTIMATE

More information

Welcome and Introduction

Welcome and Introduction Welcome and Introduction Ninth International Symposium on Space Terahertz Technology Carl Kukkonen Director, Center for Space Microelectronics Technology JPL March 17-19, 1998.,.; 1 SUBMILLIMETER AND THz

More information

Development of breakthrough technology for building next generation ground based telescopes

Development of breakthrough technology for building next generation ground based telescopes Development of breakthrough technology for building next generation ground based telescopes SUMMARY Mass production and control technology now exists to build telescope primary mirrors out of panels consisting

More information

The Cassegrain ADC for Keck I Preliminary Design Review Process and Charter September 15, 2003 By Sean Adkins

The Cassegrain ADC for Keck I Preliminary Design Review Process and Charter September 15, 2003 By Sean Adkins CALIFORNIA ASSOCIATION FOR RESEARCH IN ASTRONOMY By Sean Adkins INTRODUCTION The Technical Facilities group of the UCO/Lick Observatory located on the Santa Cruz campus of the University of California

More information

ASTE Status. Shin ichiro Asayama, Daisuke Iono and the ASTE team

ASTE Status. Shin ichiro Asayama, Daisuke Iono and the ASTE team ASTE Status Shin ichiro Asayama, Daisuke Iono and the ASTE team 1 Atacama Submillimeter Telescope Experiment (ASTE) Specifications 10-m sub-mm telescope located at Pampla La Bola within Chajnantor area

More information

Distortion mapping correction in aspheric null testing

Distortion mapping correction in aspheric null testing Distortion mapping correction in aspheric null testing M. Novak, C. Zhao, J. H. Burge College of Optical Sciences, 1630 East University Boulevard, Tucson, AZ, 85721 ABSTRACT We describe methods to correct

More information

Fundamental Limits to Wavefront Sensing in the Submillimeter

Fundamental Limits to Wavefront Sensing in the Submillimeter Fundamental Limits to Wavefront Sensing in the Submillimeter E. Serabyn Jet Propulsion Laboratory, California Institute of Technology, 4800 Oak Grove Drive, Pasadena, CA, USA 91109 Copyright 2006 Society

More information

About ESO. ESO. Astronomy made in Europe

About ESO. ESO. Astronomy made in Europe About ESO ESO is the foremost intergovernmental European Science and Technology organisation in the field of ground-based astrophysics. It is supported by 12 countries: Belgium, Denmark, France, Finland,

More information

Table of Contents and Executive Summary Final Report, ReSTAR Committee Renewing Small Telescopes for Astronomical Research (ReSTAR)

Table of Contents and Executive Summary Final Report, ReSTAR Committee Renewing Small Telescopes for Astronomical Research (ReSTAR) For the complete report, see http://www.noao.edu/system/restar 1 TableofContentsandExecutiveSummary FinalReport,ReSTARCommittee RenewingSmallTelescopesforAstronomical Research(ReSTAR) ForthecompletereportandmoreinformationabouttheReSTARcommittee,

More information

Site Characterization

Site Characterization OWL Phase A Review - Garching - 2 nd to 4 th Nov 2005 Site Characterization (Presented by M. Sarazin) 1 Site Characterization: Parameter Space Cloudiness; Humidity, Precipitable Water Vapour; Atmospheric

More information

SOFIA Science Metrics Update

SOFIA Science Metrics Update SOFIA Science Metrics Update Bill Reach SOFIA Deputy SMO Director WReach@usra.edu Astrophysics Advisory Committee NASA Headquarters July 2017 Kimberly Ennico Smith NASA SOFIA Project Scientist Kimberly.Ennico@nasa.gov

More information

South Bay Coastal Ocean Observing System California Clean Beaches Initiative

South Bay Coastal Ocean Observing System California Clean Beaches Initiative South Bay Coastal Ocean Observing System California Clean Beaches Initiative Second Quarterly Report January, 2003 to City of Imperial Beach Eric Terrill 1 1 Scripps Institution of Oceanography, University

More information

The Soar Telescope Project: A Four-Meter Telescope Focused on Image Quality

The Soar Telescope Project: A Four-Meter Telescope Focused on Image Quality Header for SPIE use The Soar Telescope Project: A Four-Meter Telescope Focused on Image Quality Thomas A. Sebring, Gerald Cecil, & Gilberto Moretto SOAR Telescope Project, National Optical Astronomy Observatories

More information

The Characterization and Minimization. of Noise in a Charge Coupled Device for. the Magellan Telescopes

The Characterization and Minimization. of Noise in a Charge Coupled Device for. the Magellan Telescopes The Characterization and Minimization of Noise in a Charge Coupled Device for the Magellan Telescopes by Jennifer J. Yu Submitted to the Department of Electrical Engineering and Computer Science in Partial

More information

Space Telescopes Asteroid Mining Space Manufacturing. Wefunder.com/SpaceFab

Space Telescopes Asteroid Mining Space Manufacturing. Wefunder.com/SpaceFab Space Telescopes Asteroid Mining Space Manufacturing Wefunder.com/SpaceFab Business Road Map Cost efficient high value space telescopes Unique business model Deployable optics technology Asteroid mining

More information

Himawari-8 BUFR Development for Winds Processing and Radiances Cloud Mask, Cloud Phase, Cloud Height

Himawari-8 BUFR Development for Winds Processing and Radiances Cloud Mask, Cloud Phase, Cloud Height Sandy Supplemental Grant Recipient Quarterly Progress Report Himawari-8 BUFR Development for Winds Processing and Radiances Award Number: NA14NES4830006 The National Oceanic and Atmospheric Administration

More information