4. Network Calculations
|
|
- Julie Baker
- 5 years ago
- Views:
Transcription
1 Construction Project Management (CE ) 4. Network Calculations Dr. Khaled Hyari Department of Civil Engineering Hashemite University Calculations On a Precedence Network I Early Activity Start (ES): Earliest time an activity can start as determined by the latest of the early finish times of all immediate preceding activities (IPAs) Early Activity Finish (EF): Earliest time an activity can finish determined by adding the duration of the activity to the early start time Late Activity Start (LS): Latest time an activity can start without delaying the project completion Late Activity Finish (LF): Latest time an activity can be finished without delaying project completion ١
2 Calculations On a Precedence Network II Early Event Occurrence Time: Earliest an event can occur determined by the latest early finish Late Event Occurrence Time: Latest an event can occur Calculations On a Precedence Network III Step 1: Perform Forward Pass Calculations to determine: Early Start (ES) and Early Finish (EF) of each activity. ES (initial activities) = S ES (x) = Latest (EF (all predecessors of x)) EF (x) = ES(x) + D(x) Where, S= Project start time. D(x) = Duration of activity x. ES(x)= Earliest start time of activity x. EF(x) = Earliest finish time of activity x. ٢
3 Calculations On a Precedence Network IV Illustrating computations on a precedence diagram All relationships are assumed to be Finish-to-Start Early Times (Early Start [ES] and Early Finish [EF]) Calculations On a Precedence Network V 1. Assign 1 as the early start date of the first activity 2. Calculate the early finish time for the activity 3. The early start of activities will be determined by the early finish times of preceding activities Other than the first activity or activities 4. Repeat steps 2 and 3 for each network activity until ES & EF are determined for the last activity ٣
4 Calculations On a Precedence Network VI Step 2: Perform Backward Pass Calculations to determine: Late Start (LS) and Late Finish (LF) of each activity. LF (end activities) = T LF (x) = Earliest (LS (all successors of x)) LS (x) = LF(x) - D(x) Where, T = Project completion time. D(x) = Duration of activity x. LS(x) = Latest start time of activity x. LF(x) = Latest finish time of activity x. Calculations On a Precedence Network VII ٤
5 Calculations On a Precedence Network VIII Activity TF FF IF Mobilize Remove old Cabinets Buy materials Install new flooring Hang wallpaper Install new cabinets Touch-up paint Demobilize Calculations On a Arrow Network ٥
6 Identify the Critical Path When an activity start date is fixed in this way, the activity is said to have no float Such activities are said to be critical If the activity starts later than the assigned date, or takes longer to complete than the assigned duration, the project completion date will be extended by the same amount of time Activity Floats I Total Float (TF): maximum amount of time that the activity can be delayed without delaying the completion time of the project. Free Float (FF): maximum amount of time that the activity can be delayed without delaying the early start of any of its successors, assuming its predecessors were completed early. Free Float: Amount of time an activity can be delayed before it impacts the start of any succeeding activity ٦
7 Activity Floats II Independent Float (IF): maximum amount of time that the activity can be delayed without delaying the early start of any of its successors, assuming its predecessors were completed late. Activity Floats III Successors Started Early Late Predecessors Completed Early Free Float Total Float Late Independent Float ٧
8 Activity Floats IV Float Type Total Float Free Float Independent Float TF = LS ES TF = LF EF Calculation FF = Min (ES of all successors ) EF IF = Min (ES of all successors) Max (LF of all predecessors) D Calculations On a Precedence Network IX Once the early and late start times, early and late finish times, free float, and total float of all activities are determined, the calculations are completed ٨
9 Calculations On a Precedence Network X LAG: The amount of time that exists between the early finish of an activity and the early start of a specified succeeding activity Example 2: Network Calculations I Activity Description Predecessors Duration A Preliminary design - 6 B Evaluation of design A 1 C Contract negotiation - 8 D Preparation of fabrication plant C 5 E Final design B, C 9 F Fabrication of Product D, E 12 G Shipment of Product to owner F 3 ٩
10 Example 2: Network Calculations II Example 2: Network Calculations III Activity Duration ES EF LS LF A 6 B 1 C 8 D 5 E 9 F 12 G 3 ١٠
11 Example 2: Network Calculations III Activity Duration ES EF LS LF A B C D E F G Example 2: Network Calculations IV Activity Duration ES EF LS LF TF FF IF A B C D E F G ١١
12 Example 2: Network Calculations IV Activity Duration ES EF LS LF TF FF IF A B C D E F G Example 3: Network Calculations I ١٢
13 Example 3: Network Calculations II Example 3: Network Calculations III Activity Duration A 4 Early Start Early Finish Late Start Late Finish B 3 C 8 D 7 E 9 F 12 G 2 H 5 I 6 ١٣
14 Example 3: Network Calculations III Early Early Late Late Activity Duration Start Finish Start Finish A B C D E F G H I Example 3: Network Calculations IV Activity Duration ES EF LS LF TF FF IF A B C D E F G H I ١٤
15 Example 3: Network Calculations IV Activity Duration ES EF LS LF TF FF IF A B C D E F G H I Precedence Diagram Relationships I Types of Logical Precedence Relationships in PDM Finish to Start (with or without lag): Each activity depends on the completion of its preceding activity ١٥
16 Precedence Diagram Relationships II Typical Sequence of Finish-to- Start Relationships Finish-to-Start Relationship with a 28-Day Delay (lag) Precedence Diagram Relationships III Types of Logical Precedence Relationships in PDM Start to Start (with or without lag). ١٦
17 Precedence Diagram Relationships IV Activities with Start-to-Start Relationships Precedence Diagram Relationships V Activities with Start-to-Start with a Delay Relationships ١٧
18 Precedence Diagram Relationships VI Activities with Start-to-Start with a Delay Relationships Precedence Diagram Relationships VII Types of Logical Precedence Relationships in PDM Finish to Finish (with or without lag). ١٨
19 Precedence Diagram Relationships VIII Finish-to-Finish (FF) Precedence Diagram Relationships IX Finish-to-Finish (FF) with Delay Finish-to-Start Relationship for Window Installation ١٩
20 Precedence Diagram Relationships X Activities with Finish-to-Finish with a Delay (lag) Relationships Precedence Diagram Relationships XI Types of Logical Precedence Relationships in PDM Start to Finish (with or without lag). ٢٠
21 Precedence Diagram Relationships XII Start-to-Finish with a Delay Relationships Precedence Diagram Relationships XIII Start-to-Finish with a Delay Relationships ٢١
22 Precedence Diagram Relationships XIV Start-to-Finish with a Delay Relationships Precedence Diagram Method Advantages of PDM Over CPM: Easier to construct & modify network. No need for dummies. Less activities in presentation. Precedence relationships with lag times are more effective in modeling project activities. ٢٢
23 Types of Activities Milestones: are points in time that are identified as important intermediate dates. Example: a weather-imposed date to finish exterior activities. Schedule Milestone : A significant event in the project schedule, such as an event restraining future work or marking the completion of a major deliverable A schedule milestone has zero durations Types of Activities II Hammock Activity: an activity that extends from one activity to another but has no duration of its own. Example: Dewatering activity. ٢٣
PROGRAMMING CPM. Network Analysis. Goal:
PROGRAMMING CPM 5/21/13 Network Analysis Goal: Calculate completion time Calculate start and finish date for each activity Identify critical activities Identify requirements and flows of resources (materials,
More informationA scheme developed by Du Pont to figure out
CPM Project Management scheme. A scheme developed by Du Pont to figure out Length of a normal project schedule given task durations and their precedence in a network type layout (or Gantt chart) Two examples
More information11/8/2018. Overview. PERT / CPM Part 2
/8/08 PERT / CPM Part BSAD 0 Dave Novak Fall 08 Source: Anderson et al., 0 Quantitative Methods for Business th edition some slides are directly from J. Loucks 0 Cengage Learning Overview Last class introduce
More information. Introduction to CPM / PERT Techniques. Applications of CPM / PERT. Basic Steps in PERT / CPM. Frame work of PERT/CPM. Network Diagram Representation. Rules for Drawing Network Diagrams. Common Errors
More informationSAMPLE STUDY MATERIAL. GATE, IES & PSUs Civil Engineering
SAMPLE STUDY MATERIAL Postal Correspondence Course GATE, IES & PSUs Civil Engineering CPM & CONSTRUCTION EQUIPMENT C O N T E N T 1. CPM AND PERT... 03-16 2. CRASHING OF NETWORK... 17-20 3. ENGINEERING
More informationProject Time Planning. Ahmed Elyamany, PhD
Project Time Planning Ahmed Elyamany, PhD 1 What is Planning The Development of a workable program of operations to accomplish established objectives when put into action. Done before project starts Planning
More informationNetwork Techniques - I. t 5 4
Performance:Slide.doc Network Techniques - I. t s v u PRT time/cost : ( Program valuation & Review Technique ) vent-on-node typed project-model with probabilistic (stochastic) data set as weights (inp)
More informationTime Planning and Control
Time Planning and ontrol Precedence iagram G44 NGINRING MNGMNT 1 Precedence iagramming S ctivity I LS T L n important extension to the original activity-on-node concept appeared around 14. The sole relationship
More informationTime allowed: 1.5 hours
Student name College of ngineering Civil ngineering Department G 404: NGINRING MNGMNT Second Semester 1438/1439H (MODL NSWR) FIRST MIDTRM XM Monday 24/6/1439H (12/3/2018G) from 7:00 to 8:30 PM Time allowed:
More informationMEI Decision Mathematics 1
Chapter assessment MEI Decision Mathematics Critical Path Analysis. The diagram below shows a precedence network for a particular project. 9 A() D(4) I(8) Durations are in days B() E() H(5) J(4) L() 5
More informationST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1
ST. JOSEPH S COLLEGE OF ARTS & SCIENCE (AUTONOMOUS) CUDDALORE-1 SUB:OPERATION RESEARCH CLASS: III B.SC SUB CODE:EMT617S SUB INCHARGE:S.JOHNSON SAVARIMUTHU 2 MARKS QUESTIONS 1. Write the general model of
More informationBenefits of PERT/CPM. 2018, Jayant Rajgopal
Project: ny set of complex, interrelated activities aimed at some specific goal. Typically, characterized by a clear starting point and a clear end point. Examples: onstruction (buildings, roads, bridges,
More informationCHAPTER 12. (The interpretation of the symbols used in the equations is given in page 3)
CHAPTER 12 The equations needed: (The interpretation of the symbols used in the equations is given in page 3) 1. ATI = t D 35 4. ws = I average weekly CU 2. I turn = CU I average 5. ds = I average daily
More information(1) The starting point is the precedence table (aka dependence table) Immediately preceding activities
Critical Path Analysis (10 pages; 1/5/16) fmng.uk (1) The starting point is the precedence table (aka dependence table) Example Activity Duration Immediately preceding activities A 4 - B 5 - C 6 A,B D
More informationNetwork analysis. A project is a temporary endeavor undertaken to create a "unique" product or service
Network analysis Introduction Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects. One definition of a project
More informationQi Jian-xun,Sun Dedong
Physics Procedia 24 (2012) 1530 1540 2012 International Conference on Applied Physics and Industrial Engineering One Improvement Method of Reducing Duration Directly to Solve Time-Cost Tradeoff Problem
More information07/09/2011. A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux1. These products specific management
A.AMRANI-ZOUGGAR IMS-Lab, University Bordeaux These products specific management What leads the industrialist to start projects? BENEFITS Ageing of the range Benchmarking, comparing the market and industrial
More informationTime Planning and Control. Time-Scaled Network
Time Planning and Control Time-Scaled Network Processes of Time Planning and Control 1.Visualize and define the activities..sequence the activities (Job Logic). 3.stimate the activity duration. 4.Schedule
More informationProject Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras
Project Planning & Control Prof. Koshy Varghese Department of Civil Engineering Indian Institute of Technology, Madras (Refer Slide Time: 00:16) Lecture - 52 PERT Background and Assumptions, Step wise
More informationSample Chapter. Basic Hard Systems. Engineering: Part I
Basic Hard Systems 10 Engineering: Part I 10.1 Introduction: Hard Systems Analysis In Chapter 1 we dealt briefly with the rudiments of the systems approach to problem solving. In this chapter, we begin
More informationMSA 640 Homework #2 Due September 17, points total / 20 points per question Show all work leading to your answers
Name MSA 640 Homework #2 Due September 17, 2010 100 points total / 20 points per question Show all work leading to your answers 1. The annual demand for a particular type of valve is 3,500 units. The cost
More informationThe WhatPower Function à An Introduction to Logarithms
Classwork Work with your partner or group to solve each of the following equations for x. a. 2 # = 2 % b. 2 # = 2 c. 2 # = 6 d. 2 # 64 = 0 e. 2 # = 0 f. 2 %# = 64 Exploring the WhatPower Function with
More informationNetwork Techniques - II.
erformance:lide1.doc Network Techniques - II. CM time - CM time+ : Overlapping, open network and non-broken activity keep being problematic ( chedules for roduction Management?! ) MM time : ( METRA otentials'
More informationStatistics 349(02) Review Questions
Statistics 349(0) Review Questions I. Suppose that for N = 80 observations on the time series { : t T} the following statistics were calculated: _ x = 10.54 C(0) = 4.99 In addition the sample autocorrelation
More informationM.SC. MATHEMATICS - II YEAR
MANONMANIAM SUNDARANAR UNIVERSITY DIRECTORATE OF DISTANCE & CONTINUING EDUCATION TIRUNELVELI 627012, TAMIL NADU M.SC. MATHEMATICS - II YEAR DKM24 - OPERATIONS RESEARCH (From the academic year 2016-17)
More information6. MESH ANALYSIS 6.1 INTRODUCTION
6. MESH ANALYSIS INTRODUCTION PASSIVE SIGN CONVENTION PLANAR CIRCUITS FORMATION OF MESHES ANALYSIS OF A SIMPLE CIRCUIT DETERMINANT OF A MATRIX CRAMER S RULE GAUSSIAN ELIMINATION METHOD EXAMPLES FOR MESH
More informationA Critical Path Problem in Neutrosophic Environment
A Critical Path Problem in Neutrosophic Environment Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou. Foreword
More informationS2 (2.2) Equations.notebook November 24, 2015
Daily Practice 7.10.2015 Q1. Multiply out and simplify 7(x - 3) + 2(x + 1) Q2. Simplify the ratio 14:21 Q3. Find 17% of 5000 Today we will be learning to solve equations. Homework Due tomorrow. Q4. Given
More informationProject management model for constructing a renewable energy plant
Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 74 (207 ) 45 54 206 Global Congress on Manufacturing and Management Project management model for constructing a renewable energy
More informationAP Exercise 1. This material is created by and is for your personal and non-commercial use only.
1 AP Exercise 1 Question 1 In which of the following situations, does the list of numbers involved make an arithmetic progression, and why? (i) The taxi fare after each km when the fare is Rs 15 for the
More informationA Critical Path Problem Using Triangular Neutrosophic Number
A Critical Path Problem Using Triangular Neutrosophic Number Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset, Dr. Yongquan Zhou.
More informationITEC2620 Introduction to Data Structures
ITEC2620 Introduction to Data Structures Lecture 6a Complexity Analysis Recursive Algorithms Complexity Analysis Determine how the processing time of an algorithm grows with input size What if the algorithm
More informationARITHMETIC PROGRESSIONS
ARITHMETIC PROGRESSIONS 93 ARITHMETIC PROGRESSIONS 5 5.1 Introduction You must have observed that in nature, many things follow a certain pattern, such as the petals of a sunflower, the holes of a honeycomb,
More informationTHE NONSIMULTANEITY CONSTRAINT IN NETWORK-BASED PROJECT MANAGEMENT SYSTEMS A THESIS. The Faculty of the Graduate Division. J.
In presenting the dissertation as a partial fulfillment of the requirements for an advanced degree from the Georgia Institute of Technology, I agree that the Library of the Institute shall make it available
More information= (, ) V λ (1) λ λ ( + + ) P = [ ( ), (1)] ( ) ( ) = ( ) ( ) ( 0 ) ( 0 ) = ( 0 ) ( 0 ) 0 ( 0 ) ( ( 0 )) ( ( 0 )) = ( ( 0 )) ( ( 0 )) ( + ( 0 )) ( + ( 0 )) = ( + ( 0 )) ( ( 0 )) P V V V V V P V P V V V
More informationCook County Health and Hospital Systems. Schedule Submission Guidelines
Cook County Health and Hospital Systems Schedule Submission Guidelines 1 This document is intended to provide guidelines for submitting construction schedules for the contractors performing work in Cook
More informationSummer Review Packet. for students entering. AP Calculus BC
Summer Review Packet for students entering AP Calculus BC The problems in this packet are designed to help you review topics that are important to your success in AP Calculus. Please attempt the problems
More informationSolving Fuzzy PERT Using Gradual Real Numbers
Solving Fuzzy PERT Using Gradual Real Numbers Jérôme FORTIN a, Didier DUBOIS a, a IRIT/UPS 8 route de Narbonne, 3062, Toulouse, cedex 4, France, e-mail: {fortin, dubois}@irit.fr Abstract. From a set of
More informationFINITE DIFFERENCES. Lecture 1: (a) Operators (b) Forward Differences and their calculations. (c) Backward Differences and their calculations.
FINITE DIFFERENCES Lecture 1: (a) Operators (b) Forward Differences and their calculations. (c) Backward Differences and their calculations. 1. Introduction When a function is known explicitly, it is easy
More informationEmbedded Systems 15. REVIEW: Aperiodic scheduling. C i J i 0 a i s i f i d i
Embedded Systems 15-1 - REVIEW: Aperiodic scheduling C i J i 0 a i s i f i d i Given: A set of non-periodic tasks {J 1,, J n } with arrival times a i, deadlines d i, computation times C i precedence constraints
More informationElastic Potential Energy and Conservation of Mechanical Energy
Elastic Potential Energy and Conservation of Mechanical Energy Level : Physics I Instructor : Kim Hook s Law Springs are familiar objects that have many applications, ranging from push-button switches
More informationA comparison of sequencing formulations in a constraint generation procedure for avionics scheduling
A comparison of sequencing formulations in a constraint generation procedure for avionics scheduling Department of Mathematics, Linköping University Jessika Boberg LiTH-MAT-EX 2017/18 SE Credits: Level:
More informationEmbedded Systems - FS 2018
Institut für Technische Informatik und Kommunikationsnetze Prof. L. Thiele Embedded Systems - FS 2018 Sample solution to Exercise 3 Discussion Date: 11.4.2018 Aperiodic Scheduling Task 1: Earliest Deadline
More informationHistory and Some Latest Developments of Precedence Diagramming Method
History and Some Latest Developments of Precedence Diagramming Method Miklós Hajdu Szent István University, Gödöllő, Hungary; Department of Architecture; Facuty of Architecture and Civil Engineering; miklos.hajdu63@gmail.com
More informationSeventeen generic formulas that may generate prime-producing quadratic polynomials
Seventeen generic formulas that may generate prime-producing quadratic polynomials Marius Coman Bucuresti, Romania email: mariuscoman13@gmail.com Abstract. In one of my previous papers I listed forty-two
More informationMATHEMATICAL ANALYSIS OF LINEAR SCHEDULES Gunnar Lucko 1
MATHEMATICAL ANALYSIS OF LINEAR SCHEDULES Gunnar Lucko ABSTRACT The interplay of various managerial dimensions of construction projects requires careful control. Some criticisms have been raised regarding
More informationUsing Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management
Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Mai Mohamed 1* Department of Operations Research Faculty of Computers and Informatics Zagazig University Sharqiyah Egypt
More informationChecklist Templates for Direct Observation and Oral Assessments (AMOB)
Checklist Templates for Direct Observation and Oral Assessments (AMOB) Competency Assessment System Hong Kong Observatory Hong Kong, China Prepared By: Signed Approved By: Signed Date: 20/08/2012 Date:
More information56:171 Operations Research Midterm Exam--15 October 2002
Name 56:171 Operations Research Midterm Exam--15 October 2002 Possible Score 1. True/False 25 _ 2. LP sensitivity analysis 25 _ 3. Transportation problem 15 _ 4. LP tableaux 15 _ Total 80 _ Part I: True(+)
More informationAUTOMATE THIS: Solving the Weather Conundrum. Gui Ponce de Leon PhD, PE, PMP, LEED AP PRESENTED BY:
AUTOMATE THIS: Solving the Weather Conundrum PRESENTED BY: Gui Ponce de Leon PhD, PE, PMP, LEED AP These days, high level tasks are increasingly being handled by algorithms that can do precise work not
More informationMath 148. Polynomial Graphs
Math 148 Lab 1 Polynomial Graphs Due: Monday Wednesday, April April 10 5 Directions: Work out each problem on a separate sheet of paper, and write your answers on the answer sheet provided. Submit the
More information57:022 Principles of Design II Midterm Exam #2 Solutions
57:022 Principles of Design II Midterm Exam #2 Solutions Part: I II III IV V Total Possible Pts: 20 15 12 16 12 75 PART ONE Indicate "+" if True and "O" if False: _+_a. If a component's lifetime has exponential
More informationCompletion Time of Fuzzy GERT-type Networks with Loops
Completion Time of Fuzzy GERT-type Networks with Loops Sina Ghaffari 1, Seyed Saeid Hashemin 2 1 Department of Industrial Engineering, Ardabil Branch, Islamic Azad university, Ardabil, Iran 2 Department
More informationand C be the space of continuous and bounded real-valued functions endowed with the sup-norm 1.
1 Proof T : C C Let T be the following mapping: Tϕ = max {u (x, a)+βeϕ [f (x, a, ε)]} (1) a Γ(x) and C be the space of continuous and bounded real-valued functions endowed with the sup-norm 1. Proposition
More informationContents college 5 and 6 Branch and Bound; Beam Search (Chapter , book)! general introduction
Contents college 5 and 6 Branch and Bound; Beam Search (Chapter 3.4-3.5, book)! general introduction Job Shop Scheduling (Chapter 5.1-5.3, book) ffl branch and bound (5.2) ffl shifting bottleneck heuristic
More informationGATE Engineering Mathematics SAMPLE STUDY MATERIAL. Postal Correspondence Course GATE. Engineering. Mathematics GATE ENGINEERING MATHEMATICS
SAMPLE STUDY MATERIAL Postal Correspondence Course GATE Engineering Mathematics GATE ENGINEERING MATHEMATICS ENGINEERING MATHEMATICS GATE Syllabus CIVIL ENGINEERING CE CHEMICAL ENGINEERING CH MECHANICAL
More informationCSE101: Design and Analysis of Algorithms. Ragesh Jaiswal, CSE, UCSD
Course Overview Material that will be covered in the course: Basic graph algorithms Algorithm Design Techniques Greedy Algorithms Divide and Conquer Dynamic Programming Network Flows Computational intractability
More informationAP Calc Summer Packet #1 Non-Calculator
This packet is a review of the prerequisite concepts for AP Calculus. It is to be done NEATLY and on a SEPARATE sheet of paper. All problems are to be done WITHOUT a graphing calculator. Points will be
More information2. Project management
2. Project management In what follows, we consider production processes where only a single item of a specific product is produced in the planning horizon In this case specific instruments for planning
More informationA Critical Path Problem Using Triangular Neutrosophic Number
A ritical Path Problem Using Triangular Neutrosophic Number Mai Mohamed 1 Department of Operations Research Faculty of omputers and Informatics Zagazig University, Sharqiyah, Egypt Yongquan Zhou 2 ollege
More informationNETWORK THEORY (BEES2211)
LECTURE NOTES On NETWORK THEORY (BEES2211) 3 rd Semester ETC Engineering Prepared by, Manjushree Jena Jemimah Digal Monalisha Nayak INDIRA GANDHI INSTITUTE OF TECHNOLOGY, SARANG NETWORK THEORY Ms. Manjushree
More informationCALCULUS AB/BC SUMMER REVIEW PACKET (Answers)
Name CALCULUS AB/BC SUMMER REVIEW PACKET (Answers) I. Simplify. Identify the zeros, vertical asymptotes, horizontal asymptotes, holes and sketch each rational function. Show the work that leads to your
More informationCritical Paths Identification on Fuzzy Network Project
IOSR Journal of Mathematics (IOSR-JM) e-issn: 2278-5728, p-issn: 2319-765X. Volume 11, Issue 1 Ver. VI (Jan - Feb. 2015), PP 49-54 www.iosrjournals.org Critical Paths Identification on Fuzzy Network Project
More informationSummer Review Packet. for students entering. IB Math SL
Summer Review Packet for students entering IB Math SL The problems in this packet are designed to help you review topics that are important to your success in IB Math SL. Please attempt the problems on
More informationSession XIV. Control Charts For Attributes P-Chart
Session XIV Control Charts For Attributes P-Chart The P Chart The P Chart is used for data that consist of the proportion of the number of occurrences of an event to the total number of occurrences. It
More informationUnit Title Marks HOURS Starting Date I Basic Concepts of Chemistry April-2019 II Structure of Atom
Class 11+12, Classes Schedule & Syllabus [ CBSE ] Chemistry Class 11 Unit Title Marks HOURS Starting Date I Basic Concepts of Chemistry 11 18 1-April- II Structure of Atom III Classification of Elements
More informationA Dynamic Programming algorithm for minimizing total cost of duplication in scheduling an outtree with communication delays and duplication
A Dynamic Programming algorithm for minimizing total cost of duplication in scheduling an outtree with communication delays and duplication Claire Hanen Laboratory LIP6 4, place Jussieu F-75 252 Paris
More informationINSTITUT FÜR WIRTSCHAFTSTHEORIE UND OPERATIONS RESEARCH UNIVERSITÄT KARLSRUHE
INSTITUT FÜR WIRTSCHAFTSTHEORIE UND OPERATIONS RESEARCH UNIVERSITÄT KARLSRUHE Proects with Minimal and Maximal Time Lags: Construction of Activity-on-Node Networks and Applications Klaus Neumann Christoph
More informationProject scheduling with calendars
OR Spektrum (2001) 23: 325 334 c Springer-Verlag 2001 Project scheduling with calendars Birger Franck, Klaus Neumann, and Christoph Schwindt Institut für Wirtschaftstheorie und Operations Research, University
More informationNeutrosophic Sets, Project, Project Management, Gantt chart, CPM, PERT, Three-Time Estimate.
Using Neutrosophic Sets to Obtain PERT Three-Times Estimates in Project Management Excerpt from NEUTROSOPHIC OPERATIONAL RESEARCH, Volume I. Editors: Prof. Florentin Smarandache, Dr. Mohamed Abdel-Basset,
More information6 SQUARES AND SQUARE ROOTS
6 SQUARES AND SQUARE ROOTS Exercise 6.1 Q.1. What will be the unit digit of the squares of the following numbers? (i) 81 (ii) 272 (iii) 799 (iv) 3853 (v) 1234 (vi) 26387 (vii) 52698 (viii) 99880 (ix) 12796
More informationName :. Roll No. :... Invigilator s Signature :.. CS/B.TECH (NEW)(CSE/IT)/SEM-4/M-401/ MATHEMATICS - III
Name :. Roll No. :..... Invigilator s Signature :.. 202 MATHEMATICS - III Time Allotted : 3 Hours Full Marks : 70 The figures in the margin indicate full marks. Candidates are required to give their answers
More informationHonors Algebra II / Trigonometry
Honors Algebra II / Trigonometry 2013-2014 Instructor: Busselmaier Room: 158 Academic Support Location: Room 158 or Office 152 E-mail: cbusselmaier@regisjesuit.com (email is the best way to get in touch
More informationLessons in Estimation Theory for Signal Processing, Communications, and Control
Lessons in Estimation Theory for Signal Processing, Communications, and Control Jerry M. Mendel Department of Electrical Engineering University of Southern California Los Angeles, California PRENTICE HALL
More informationTransition Passage to Descriptive Statistics 28
viii Preface xiv chapter 1 Introduction 1 Disciplines That Use Quantitative Data 5 What Do You Mean, Statistics? 6 Statistics: A Dynamic Discipline 8 Some Terminology 9 Problems and Answers 12 Scales of
More informationLycée des arts Math Grade Algebraic expressions S.S.4
Lycée des arts Math Grade 9 015-016 lgebraic expressions S.S.4 Exercise I: Factorize each of the following algebraic expressions, and then determine its real roots. (x) = 4x (3x 1) (x + ) (3x 1) + 3x 1
More informationagree w/input bond => + sign disagree w/input bond => - sign
1 ME 344 REVIEW FOR FINAL EXAM LOCATION: CPE 2.204 M. D. BRYANT DATE: Wednesday, May 7, 2008 9-noon Finals week office hours: May 6, 4-7 pm Permitted at final exam: 1 sheet of formulas & calculator I.
More informationMathematical Reasoning. The Foundation of Algorithmics
Mathematical Reasoning The Foundation of Algorithmics The Nature of Truth In mathematics, we deal with statements that are True or False This is known as The Law of the Excluded Middle Despite the fact
More informationTHE UNITED REPUBLIC OF TANZANIA MINISTRY OF EDUCATION AND VOCATIONAL TRAINING FORM TWO SECONDARY EDUCATION EXAMINATION, 2007.
THE UNITED REPUBLIC OF TANZANIA MINISTRY OF EDUCATION AND VOCATIONAL TRAINING FORM TWO SECONDARY EDUCATION EXAMINATION, 2007 0031 PHYSICS Time: 2 Hours 1. This paper consists of sections A, B and C. 2.
More informationThirty-Ninth Annual Columbus State Invitational Mathematics Tournament
Thirty-Ninth Annual Columbus State Invitational Mathematics Tournament Sponsored by The Columbus State University Department of Mathematics and Philosophy March nd, 0 ************************* Solutions
More informationOperation management
Operation management Vigneron Loic December 3, 2008 1 Operations and productivity 1.1 Productivity Productivity = Units produced Imput used Units produced Labor productivity = Labor hours used One resource
More informationLine Of Balance. Dr. Ahmed Elyamany
Line Of Balance Dr Ahmed Elyamany Intended Learning Outcomes Define the principles of Line of Balance (LOB) Demonstrate the application of LOB Understand the importance of LOB Understand the process of
More informationSECTION H CHEMICAL WEAPONS DESTRUCTION FACILITIES REQUIRED UNDER PARTS IV(A) OF THE VERIFICATION ANNEX OF THE CONVENTION
Declarations Forms Section H SECTION H CHEMICAL WEAPONS DESTRUCTION FACILITIES REQUIRED UNDER PARTS IV(A) OF THE VERIFICATION ANNEX OF THE CONVENTION OPCW NOVEMBER 2008 Version 2008 LIST OF CONTENTS 1.
More informationVLSI System Design Part V : High-Level Synthesis(2) Oct Feb.2007
VLSI System Design Part V : High-Level Synthesis(2) Oct.2006 - Feb.2007 Lecturer : Tsuyoshi Isshiki Dept. Communications and Integrated Systems, Tokyo Institute of Technology isshiki@vlsi.ss.titech.ac.jp
More informationExercise 6.2. Q. 1. x = 3. Q. 2. y = 2. Q. 3. 2x = 8 x = 4. Q. 4. 3a = 27 a = 9. Q. 5. 3x = 3 x = 1. Q. 6. 4x = 20 x = 5. Q. 7.
Chapter Exercise. Q.. (i) (vi) 9 (ii) 7 (vii) 9 (iii) (viii) (iv) (ix) (v) (x) Q.. (i) () + ( ) = = = False (, ) is not solution (ii) + = = () + () = + = = (,) is solution (iii) ( ) () = = = False (,)
More informationSTATIC & DYNAMIC CHARACTERISTICS OF MEASUREMENT SYSTEM
STATIC & DYNAMIC CHARACTERISTICS OF MEASUREMENT SYSTEM The performance characteristics of an instrument are mainly divided into two categories: i) Static characteristics ii) Dynamic characteristics Static
More informationEmbedded Systems 14. Overview of embedded systems design
Embedded Systems 14-1 - Overview of embedded systems design - 2-1 Point of departure: Scheduling general IT systems In general IT systems, not much is known about the computational processes a priori The
More informationAlgebra I. Course Outline
Algebra I Course Outline I. The Language of Algebra A. Variables and Expressions B. Order of Operations C. Open Sentences D. Identity and Equality Properties E. The Distributive Property F. Commutative
More informationBD1. Reciprocal space and Fourier transforms. IB Mineral Sciences Module B: Reciprocal Space, Symmetry and Crystallography
Reciprocal space and Fourier transforms The aim of this practical is to give you a chance to develop your intuition about the relationship between real space and reciprocal space. There are two halves
More informationNatural Boundary Integral Method and Its Applications
Natural Boundary Integral Method and Its Applications By De-hao Yu State Key Laboratory of Scientific and Engineering Computing Institute of Computational Mathematics and Scientific/Engineering Computing
More informationScheduling with AND/OR Precedence Constraints
Scheduling with AND/OR Precedence Constraints Seminar Mathematische Optimierung - SS 2007 23th April 2007 Synthesis synthesis: transfer from the behavioral domain (e. g. system specifications, algorithms)
More informationInSchedule File Upload Definition
InSchedule File Upload Definition Jennifer Long Sr Business Analyst PJM Interconnection PJM 2012 I. Purpose This document identifies the file upload process for the InSchedule application. It will discuss
More informationPart 7 - Radiocarbon Dates
Part 7 - Radiocarbon Dates Andrew McCarthy and Thomas Guilderson with Lauren Ristvet and Harvey Weiss The radiocarbon analysis and interpretation is presented in this section. There were several contexts
More informationDiscrete Mathematics, Spring 2004 Homework 9 Sample Solutions
Discrete Mathematics, Spring 00 Homework 9 Sample Solutions. #3. A vertex v in a tree T is a center for T if the eccentricity of v is minimal; that is, if the maximum length of a simple path starting from
More information84R13 ADVERSEWEATHER
E 84R13 SA M PL PLANNI NGANDACCOUNTI NGFOR ADVERSEWEATHER AACE International Recommended Practice No. 84R-13 PLANNING AND ACCOUNTING FOR ADVERSE WEATHER TCM Framework: 7.2 Schedule Planning and Development
More information!"#$%&'(&)*$%&+",#$$-$%&+./#-+ (&)*$%&+%"-$+0!#1%&
!"#$%&'(&)*$%&",#$$-$%&./#- (&)*$%&%"-$0!#1%&23 44444444444444444444444444444444444444444444444444444444444444444444 &53.67689:5;978?58"@A9;8=B!=89C7DE,6=8FG=CD=CF(76F9C7D!)#!/($"%*$H!I"%"&1/%/.!"JK$&3
More informationMACIS documentation. a. Temporal resolution: For each month and the hole year
MACIS documentation Wind: 1. Relative frequency of mean wind speed b. Treshold values: mean wind speed greater, greater equal, less, less equal 3, 5, 10, 12, 15 20, 22, 25 kt 2. Relative frequency of gusts
More informationSYLLABUS. Departmental Syllabus. Fire Arson Investigation. Departmental Syllabus. Departmental Syllabus. Departmental Syllabus. Departmental Syllabus
SYLLABUS DATE OF LAST REVIEW : 5/2018 CIP CODE: 43.0205 SEMESTER: COURSE TITLE: COURSE NUMBER: Fire Arson Investigation FRSC-0115 CREDIT HOURS: 3 INSTRUCTOR: OFFICE LOCATION: OFFICE HOURS: TELEPHONE: EMAIL:
More informationTropical E.S. - BUDGET
Tropical E.S. - BUDGET Replace HVAC Chiller and Cooling Tower Description Budget COMMENTS GMP Design $45,90.92 Heard Construction $5,885.00 DDC Engineering Sub-Total Overhead @ 0% Profit @ 5% Contingency
More informationIntuitionistic Fuzzy Soft Matrix Theory
Mathematics and Statistics 1(2): 43-49 2013 DOI: 10.13189/ms.2013.010205 http://www.hrpub.org Intuitionistic Fuzzy Soft Matrix Theory Md.Jalilul Islam Mondal * Tapan Kumar Roy Department of Mathematics
More information