1 27 April 2010 QUARTERLY ACTIVITIES REPORT for the period ended 31 March 2010 ONGAVA POLY-METALLIC PROJECT Diamond drilling is underway at Border. Extensive geophysical surveys were completed at Border and Kaskara Border geophysical survey highlights numerous drilling targets. Known mineralisation corresponds to moderate anomalies. Stronger anomalies extend to and broaden at depth. A separate zone 200 metres south of drilled mineralisation. Copper mineralisation is associated at surface with the southern anomaly. Strong anomalies extend the 1000 metre breadth of the geophysical survey. Kaskara geophysical survey is complete and the report is pending. Preliminary data shows that the anomalies extend east and west of the first geophysical survey. Discovery of the Ondjima base metal prospect west of Kaskara.
2 ONGAVA POLY-METALLIC PROJECT, NAMIBIA Work continued on the Ongava Poly-Metallic Project during the first quarter of 2010 despite the ongoing wet season. Extended geophysical programmes at the Border lead-zinc deposit and the Kaskara and Lucas Post copperlead-zinc prospects are yielding very interesting results that will be tested by drilling. Border and Kaskara are located in the Ongava Poly-Metallic Project, northern Namibia (Figure 1). The project is at the centre of the Otavi Mountain Figure 1 Location of the Ongava Project, northern Namibia. Other base-metal projects throughout the region are shown. Land, a historic, world-renowned and highly prospective mining region that is home to the world-class Tsumeb copper-lead-zinc-silver mine (now closed). Figure 2 The Ongava Poly-Metallic Project area (EPL 3542). Major mines and prospects are labelled. Other prospects are represented by yellow dots (20km grid). BORDER DEPOSIT AND THE PAVIAN TREND Two phases of geophysical exploration were completed at the Border lead-zinc deposit in the quarter. Border is located roughly at the centre of the 15 km long Pavian Trend, a zinc, lead and copper trend of world-class potential. The Pavian Trend incorporates the Border zinclead deposit, the Nosib H and South Ridge copper-zinc-lead prospects, and the Irvington and Pavian zinc-lead prospects. Over 13 km of the trend is located within Sabre s exploration licence. 2
3 The anomalies defined by the geophysical programme extend the full 1,000 metre breadth of the programme. The programme comprised seven 2 km long lines spaced 200 m apart for an overall strike length of 1,000 m. Three techniques, induced polarisation (IP), magnetotellurics (NSAMT) and ground magnetics were used to define anomalies at Border. In particular, Chargeability Zone A (IP) (Figure 3) and Conductor A (NSAMT) (Figure 4) are considered to be the most prospective of the anomalies identified. Both are continuous throughout the programme and exceed 1,000 m in length (Figure 5). The results of the survey are considered to be highly encouraging because anomalism can already be correlated to known mineralisation at Border, and there is continuity of these drilled zones with deeper, more extensive and more intense anomalism. At surface, geophysical anomalism is directly associated with drilled mineralisation and with a newly defined zone 200 m to the south. This new zone is largely obscured by soil cover, but minor exposures of strong alteration and brecciation show localised copper sulphide and malachite (copper carbonate) mineralisation. At depth, the two anomalies identified at surface amalgamate and extend to be up to 800 m wide. Previous drilling has only intersected a small part of these extensive anomalies. The consultant geophysicist s preferred interpretation is that the coincident IP and conductive zones contain mineralisation that is as good as if not better than mineralisation intersected already. He goes on to state that this mineralisation may get better to the east as chargeability and conductivity tends to increase to the east. In order to test these extensive geophysical anomalies, drilling commenced at Border on 30 th March Three target zones extend the full 1000 m breadth of the geophysical surveys. The three targets are: 1. extensions to known mineralization; 2. strong geophysical anomalies 200m south of known mineralization; and 3. strong, broad geophysical anomalies at depth beneath known mineralization. For now, the exploration target for the Border deposit remains as previously stated, as: % Lead + Zinc 1. This represents a conservative tonnage that is substantially lower than estimates published by the Ministry of Mines and Energy, Namibia. 1 At this stage, the potential quantity and grade of the Border zinc-lead deposit is conceptual in nature, as Sabre has determined that insufficient work has been undertaken to define a mineral resource and it is uncertain if further exploration will result in the determination of a mineral resource. The exploration target size was based upon deposit calculations undertaken by Etosha Petroleum Ltd (Border). 3
4 SBR Border drilling Figure 3 IP chargeability on Line 9 (compare to Figure 4 below), showing correlation of anomalism with existing drilling (black lines with mineralisation histrograms, left of centre). Anomalism is stronger and more extensive at depth, and is defined by white outlines labelled Chargeable Zone A. This zone is open at depth and corresponds in part to Conductor A. Figure 4 NSAMT resistivity model for Line 9 (compare to Figure 3 above). Conductor A extends to a depth of over 1,000 m and coincides partly with Chargeable Zone A (white lines). Conductor B (right) differs to Conductor A in that it is stronger, shows a magnetic signature (not shown here) and corresponds to the Maieberg Formation rocks. 4
5 Figure 5 Plan view of the geophysical survey programme at Border, showing survey points. Lines 8-10 were reported on 26 February Lines 6, 7, 11, & 12 are reported here. This diagram shows IP response at 100 metres beneath surface. Note that within Chargeability Zone A the Southern Anomaly ( Conductor A ) increases in intensity to the east. Also note that the Northern Anomaly (which corresponds to drilled mineralisation) appears to end after line 10, but this is a function of the anomaly plunging below the 100m level to the east (see Figure 3). Previous Sabre drilling KASKARA DISCOVERY AND THE LUCAS POST TREND Ongoing geophysical surveys have continued at Kaskara despite rain hampering access during the quarter. The programme has been extended to cover all ground between the Kaskara and Lucas Post prospects (Figure 6). Sabre is presently awaiting the final report regarding the extended geophysical programme. Preliminary data from lines adjacent to the original survey suggests that the anomalism detected at Kaskara continues to both the east and the west of the original surveys. A total of 23 lines, each 1,000 m long, have been surveyed over a strike length of 3,000 m. It is anticipated that this dataset will provide numerous drill targets for drilling at and around Kaskara and Lucas Post. Further geological mapping has also identified galena (lead sulphide) mineralisation (Fig.7) to the northwest of Lucas Post, on the northern side of the valley (Fig.6). Mineralisation at the newly defined Ondjima prospect appears to be continuous for at least 400 m of strike. The discover of Ondjima means that the Kaskara-Lucas Post corridor of mineralisation extends for around 3600 m. As with many prospects throughout the Otavi Mountainland, it is expected that galena at Ondjima is the sole sulphide preserved at surface, but may be indicative of other sulphides below the influence of weathering. 5
6 Figure 6 The geophysical programme along the Kaskara-Lucas Post corridor. Lines 4100 to 4400 have been reported. Work is completed on the remaining lines. Each line is 1 km long The approximate location of the recent Ondjima discovery is shown to the northwest of Lucas Post prospect. Grid is 500 m. Figure 7 Extensive galena mineralisation (dark grey to silver) in outcrop from Ondjima (33S mE mN) 6
7 UPCOMING WORK Drilling is ongoing at Border, targeting the three defined target zones, each of which extend laterally for over 1,000 metres. Results will be reported as they come to hand. The two diamond drilling rigs are scheduled to drill throughout the second quarter. This is likely to be extended should mineralisation be intercepted in the new target areas. Ongoing rains and damp ground are still hampering access for heavy vehicles (such as drill rigs and their support vehicles) to the Kaskara-Lucas Post area. At and around Kaskara, targeting of drillholes will commence upon the receipt of the final report on the geophysical surveys between Kaskara and Lucas Post, which is due shortly. Preliminary data suggests that the anomalies present at Kaskara extend beyond the initial survey area. Given the rugged terrain, defining the location of suitably accessible drill sites above the most prospective targets will enable quicker drilling mobilisation. Access to the more rugged sites will require a different, more manoeuvrable type of drill rig. Mapping is continuing at the Ondjima discovery west of Kaskara. The full extent of outcropping mineralisation is presently being defined and will be reported as results are finalised. Licence renewal Sabre has submitted the application for renewal of licence EPL3542 and is awaiting confirmation by the Ministry of Mines and Energy in Namibia of the renewal. The required expenditure commitments have been exceeded, and more than the requisite 25% has been excised from the licence area (Figure 14). The excised area contains no known prospects or mines. Long delays are reported by other companies seeking licence renewals in Namibia at present. Data from the Ministry s website (Figure 15) shows that the reduced size for EPL3542 has been accepted and that, as of the most recent listing of the status of EPLs on 7 April 2010, its status is officially Pending. Sabre has full confidence that the licence will be renewed, and is not aware of any factors that would deny renewal. Consequently, exploration at Kaskara and Border will continue. Figure 8 Reduction of exploration licence EPL3542 (Ongava). The reduction amounts to over 25% and does not include any known prospects or mines. The total area of the reduced licence is around 600 km 2. 7
8 Figure 9 Excerpt from the most recent Current Minerals Licences Map from the Ministry of Mines and Energy, Namibia (7 April 2010). The reduced EPL3542 is shown at centre, indicating that the Ministry is in the process of renewing the licence. Note that the area dropped by Sabre as part of the renewal procedure has since been pegged by Namibia East China Non-ferrous Lorelei Dev (Pty) (EPL4363), which is also pending. The full map can be obtained from Yours faithfully, Norman Grafton Company Secretary Sabre Resources Ltd For further information please contact: Dr Matthew Painter, General Manager - Exploration Phone (08) Or consult our website: Competent Person Declaration The information in this report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by Dr Matthew Painter, who is a member of The Australasian Institute of Geoscientists. Dr Painter has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity that he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resource and Ore Reserves. Dr Painter consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. 8
ONGAVA POLY-METALLIC PROJECT
QUARTERLY ACTIVITIES REPORT for the period ended 31 December 2009 ONGAVA POLY-METALLIC PROJECT Kaskara-Lucas Post Corridor is a 2,500 m long copper-lead-zinc trend containing the Kaskara, Kaskara West,
More informationONGAVA POLY-METALLIC PROJECT
QUARTERLY ACTIVITIES REPORT for the period ended 30 September 2009 ONGAVA POLY-METALLIC PROJECT Exploration focused on two major east-west mineralisation trends within the Ongava Project, the 15 km Pavian
More informationQUARTERLY ACTIVITIES REPORT
QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 31 MARCH 2012 KEY POINTS Sabre has identified three significant mineralised Base Metal Trends within its Ongava Polymetallic project in northern Namibia
More informationFor personal use only
ASX ANNOUNCEMENT 31 August 2012 DRILLING SUCCESS CONTINUES AT GUCHAB Near surface copper mineralisation in drill core from GCDD0002 HIGHLIGHTS The pilot programme of diamond drilling at Guchab continues
More informationFOR. Extract. Explore. Extend. moving. Kombat. Trend. RUUG fromm 0 metres
QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDEDD 30 JUNE 2012 Shattuckite (copper carbonate) mineralisation from Guchab, Kombat Copper Trend. HIGHLIGHTS Sabre has acquired a second strategic tenement
More informationFigure 1 View. Toggenburg. New event responsible. project areas. Interrogation. across. Sabre s. sites at
QUARTERLY ACTIVITIES REPO RT FOR THE QUARTER ENDED 31 DECEMBER 2015 Figure 1 View of the Otavi Mountain Land, approaching from the southwestt on the highway from Windhoek.. Drill sites finalised for the
More informationFor personal use only
ASX ANNOUNCEMENT 31 October 2016 QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDED 30 SEPTEMBER 2016 Figure 1 View of the Otavi Mountain Land, approaching from the southwest on the highway from Windhoek
More information29 July 2016 FOR. Figure 1 View. recent. Study. Preparation the. during. quarter. Zn-Pb. for the. Driehoek. Borderr. corridor
ASX ANNOUNCEMENT 29 July 2016 QUARTERLY ACTIVITIES REPORT FOR THE QUARTE ER ENDED 30 JUNE 2016 Figure 1 View of the Otavi Mountain Land, approaching from the southwest on the highway from Windhoek Border
More informationFor personal use only
29 July 2011 The Manager Company Announcements Office Australian Securities Exchange Exchange Centre 20 Bridge Street SYDNEY NSW 2000 Dear Sir Quarterly Activities Report for the period ended 30 June 2011
More informationFor personal use only
ASX ANNOUNCEMENT QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDEDD 31 DECEMBER 2016 Figure 1 View of the Otavi Mountain Land, approaching from the southwestt on the highwayy from Windhoek Preparation
More information288 APRIL prospects; key prospective. Preparation the. during. quarter. zinc-lead n within EPL and projects: Ag prospect.
ASX ANNOUNCEMENT 288 APRIL 2017 QUARTERLY ACTIVITIES REPORT FOR THE QUARTER ENDED 31 MARCH 2017 Figure 1 View of the Otavi Mountain Land, approaching from the southwest on the highway from Windhoek EPL
More informationNEW COBAR-STYLE COPPER DISCOVERY IN NSW
ASX / MEDIA RELEASE 2 AUGUST 2011 NEW COBAR-STYLE COPPER DISCOVERY IN NSW Broad zone of copper-polymetallic mineralisation intersected at 4-Mile prospect Highlights: Wide zone of copper-silver-gold-lead-zinc
More informationQUARTERLY REPORT FOR THE PERIOD ENDING 30 JUNE 2008
QUARTERLY REPORT FOR THE PERIOD ENDING 30 JUNE 2008 Highlights Surface sampling identified a potential mineralized zone at the Emperor zinc prospect at the Quartz Circle Project in Western Australia Desktop
More information704,000 OUNCE MIYABI GOLD PROJECT UPDATE
704,000 OUNCE MIYABI GOLD PROJECT UPDATE ASX/ RELEASE 21 April 2016 ASX code RVY Board of Directors: Geoff Gilmour Managing Director Greg Cunnold Technical Director Graeme Clatworthy Non-Executive Director
More informationExploration targets identified to increase Browns Range Project s mine life
Exploration targets identified to increase Browns Range Project s mine life Highlights Exploration Target estimate demonstrates the potential for very significant increases in Total Mineral Resource at
More informationAirborne EM Survey Confirms Multiple VMS Targets at Collerina
ASX Announcement 2 February 2017 Airborne EM Survey Confirms Multiple VMS Targets at Collerina A 600 line kilometre VTEM Max helicopter borne geophysics survey has been completed over the 25 kilometres
More informationROX DEFINES STRONG IP ANOMALIES AT PHA LUANG
ASX/MEDIA RELEASE ROX DEFINES STRONG IP ANOMALIES AT PHA LUANG Rox Resources (ASX: RXL, Rox ) has completed Induced Polarisation ( IP ) surveys at its Pha Luang zinc project in Laos. The survey was conducted
More informationASX RELEASE REVIEW OF GLANDORE DATA TO DEFINE DRILL PROGRAM
ASX RELEASE 4 April 2007 REVIEW OF GLANDORE DATA TO DEFINE DRILL PROGRAM The Directors of Hemisphere Resources Limited ( Hemisphere or the Company ) are pleased to announce that a review has been conducted
More informationBass Metals records further positive drill results & progress at 3 prospects.
16 March 2011 Bass Metals records further positive drill results & progress at 3 prospects. HIGHLIGHTS: New high-grade drilling intercept confirms Switchback potential; Drilling commences at Lake Margaret
More informationNi-Cu-Au-U TYPE AIRBORNE ANOMALIES OUTLINED
ABN 28 122 180 205 www.juttholdings.com ASX ANNOUNCEMENT (ASX Code: JUT) 29 February 2008 Ni-Cu-Au-U TYPE AIRBORNE ANOMALIES OUTLINED Tay - Munglinup Project: near Ravensthorpe in the SW of Western Australia
More informationSTRONG GOLD IN SOIL ANOMALY OUTLINED AT MARY HARRISON PROJECT HIGHLIGHTS
National Stock Exchange of Australia Company Announcements Level 2, 117 Scott Street Newcastle NSW 2300 25 th January 2013 STRONG GOLD IN SOIL ANOMALY OUTLINED AT MARY HARRISON PROJECT HIGHLIGHTS 100m
More informationHIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT
The Manager ASX Company Announcements PO Box H224, Australia Square Sydney NSW 2001 22 December 2010 HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT New true-width
More informationHighlights. Wa Project. Kandia Prospect. South Wa. Julie West Jang Trend. Corporate
29 th July 2010 June December 2010 Quarterly Report Report 2008 Highlights Wa Project Kandia Prospect» RC drilling defines open ended zones of sediment hosted gold mineralisation at the site of the Kandia
More informationFor personal use only
MARCH 2011 QUARTERLY ACTIVITIES REPORT ASX Release Thursday 21 April 2011 OAKLAND RESOURCES LIMITED Level 1 / 33 Richardson Street West Perth, Australia WA 6005 Tel: +61 8 9200 4491 Fax: +61 8 9200 4469
More informationMINCOR /GOLDEN RIM FIJI JOINT VENTURE SIGNIFICANT NEW EXPLORATION RESULTS
1 November 2007 MINCOR /GOLDEN RIM FIJI JOINT VENTURE SIGNIFICANT NEW EXPLORATION RESULTS Highlights Very high gold-in-soil sample results up to 17.3 g/t gold have been received from the Banana Creek Prospect.
More informationFor personal use only
22 April 2013 Drilling to commence at Majada, Copper-Gold Prospect, Chile. Red Gum Resources Limited (ASX: RGX, Red Gum or the Company ) is pleased to announce that drilling of its Majada Copper-Gold Prospect,
More informationCarrapateena Mineral Resources Explanatory Notes April OZ Minerals Limited. Carrapateena Mineral Resources Statement April
OZ Minerals Limited Carrapateena Mineral Resources Statement April 14 2011 CARRAPATEENA MINERAL RESOURCE STATEMENT April 14, 2011 The Carrapateena Resource Statement relates to an upgrading to an Inferred
More informationFIRST 2 DRILL HOLES AT NAKRU-2 PROSPECT BOTH INTERSECT SIGNIFICANT HIGHER GRADE COPPER MINERALISATION
ADDRESS PHONE PO Box 6965 +61(07) 5592 1001 Gold Coast Mail Centre FAX Qld 9726 Australia +61 (07) 5592 1011 EMAIL ABN 54 126 490 855 info@coppermoly.com.au WEBSITE www.coppermoly.com.au ASX Announcement
More informationCORPORATE UPDATE. Feasibility Study being finalised for completion towards the end of April.
16 March 2018 Company Announcement Officer ASX Limited 20 Bridge Street SYDNEY NSW 2000 Highlights CORPORATE UPDATE Inaugural Bowdens Reserve Statement due early April. Feasibility Study being finalised
More informationGEOPHYSICAL SURVEYING COMMENCES AT ESK TROUGH
ADDRESS PHONE PO Box 6965 +61(07) 5592 1001 Gold Coast Mail Centre FAX Qld 9726 Australia +61 (07) 5592 1011 EMAIL ABN 54 126 490 855 info@coppermoly.com.au WEBSITE www.coppermoly.com.au ASX Announcement
More informationATLAS GOLD LIMITED ABN QUARTERLY REPORT FOR THE PERIOD ENDED 31 MARCH 2005
ABN 63 110 396 168 FOR THE PERIOD ENDED 31 About Atlas Gold Limited The Company has four projects at varying stages of exploration located at Farrel Well, Pardoo, Mt Minnie and Pearana in the Pilbara region,
More informationNT RESOURCES LIMITED QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 JUNE 2010 ASX CODE: NTR
NT RESOURCES LIMITED QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 JUNE 2010 ASX CODE: NTR Activities Report Background NT Resources Limited ( NT Resources or the Company ) holds six granted Exploration
More informationGOULAMINA DRILLING AND GENERAL PROGRESS UPDATE
21 November 2017 GOULAMINA DRILLING AND GENERAL PROGRESS UPDATE HIGHLIGHTS RC drilling at Danaya and Yando completed. RC drilling at Danaya intersects very wide (>117m) spodumene bearing pegmatite zone.
More informationASX ANNOUNCEMENT 21 MARCH 2011
ASX ANNOUNCEMENT 21 MARCH 2011 Sihayo Pungkut Gold Project New JORC Compliant Estimate Sihayo Resource increases 43% to 1.30 Million ounces, total project resources grow to 1.4 million ounces Highlights
More informationROE HILLS COBALT AND GOLD DRILLING ADVANCES
ASX ANNOUNCEMENT 22 June 2017 ROE HILLS COBALT AND GOLD DRILLING ADVANCES Aircore drilling completed to test ROE-1 cobalt prospect with assays awaited; RC drilling now underway targeting three high-priority
More informationENCOURAGING GOLD-BASE METALS AT MAY DAY, MOLY- GOLD AT ATTUNGA
ASX / MEDIA RELEASE 5 JULY 2010 ENCOURAGING GOLD-BASE METALS AT MAY DAY, MOLY- GOLD AT ATTUNGA Peel Exploration is pleased to announce that recent drilling at the Company s Attunga and May Day projects
More informationHigh Grade Gold Intercepts at Bangaba
20th March 2012 ASX Announcement High Grade Gold Intercepts at Bangaba Level 2, 9 Colin Street West Perth WA 6005 ABN 11 127 171 877 p (08) 9216 1000 f (08) 9481 7939 w www.predictivediscovery.com e info@predictivediscovery.com
More informationMT PLEASANT AUGER GEOCHEM RESULTS OUTLINE A NEW GOLD ZONE TO THE NORTH-EAST OF FIDELATAS PROSPECT HIGHLIGHTS
MT PLEASANT AUGER GEOCHEM RESULTS OUTLINE A NEW GOLD ZONE TO THE NORTH-EAST OF FIDELATAS PROSPECT ASX RELEASE 21 MARCH 2011 HIGHLIGHTS Recently completed auger soil geochemistry program has defined a 130m
More informationSipa Resources Limited
30 October 2012 Sipa Resources Limited ABN 26 009 448 980 September Quarter 2012 Quarterly ASX Report HIGHLIGHTS The September Quarter, and through October, has seen a very high level of drilling and geophysical
More informationFor personal use only
ACN 097 088 689 ASX Announcement 1 EXPLORATION SUCCESS CONTINUES AT RAVENSWOOD RC drilling targeting shallow portions of Welcome breccia returns a number of significant new results including: 7m @ 7.84g/t
More information******************* *******************
This announcement lifts the trading halt requested by the Company on the 13 September 2012 Announcement to the Australian Securities Exchange Monday 17 September 2012 COMPANY UPDATE PARTIALLY UNDERWRITTEN
More informationAxiom Nightflower Drilling Progress and IP Survey Results, North Queensland
1 July 2008 The Manager, Companies Australian Securities Exchange Ltd Electronic Announcement System Dear Sir, AXIOM MINING LIMITED (ASX CODE: AVQ) ASX Announcement Axiom Nightflower Drilling Progress
More informationMagnus Copper Project exploration update
ASX ANNOUNCEMENT 30 SEPTEMBER 2011 CODE: ALY BOARD OF DIRECTORS Mr Warwick Davies Non-Executive Chairman Mr Robert Brierley Managing Director Mr John Arbuckle Non-Executive Director Mr Jeffrey Moore Non-Executive
More informationASX / MEDIA RELEASE 6 MAY MILE SILVER-LEAD-ZINC DISCOVERY; HIGH GRADE SILVER-GOLD IN ROCK CHIPS AT RUBY SILVER
ASX / MEDIA RELEASE 6 MAY 2011 4-MILE SILVER-LEAD-ZINC DISCOVERY; HIGH GRADE SILVER-GOLD IN ROCK CHIPS AT RUBY SILVER Highlights: Silver-lead-zinc discovery at 4-Mile; mineralisation intersected in all
More informationFor personal use only
(ASX:OUM) QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2011 MT WELLS HIGHLIGHTS IDENTIFICATION OF A FURTHER 1KM OF EXTENSIONAL POTENTIAL IN ADDITION TO THE 1KM OF KNOWN TIN/COPPER MINERALISATION.
More informationFor personal use only
Quarterly Activities Report September 2013 Equus Mining Limited (ASX: EQE) is pleased to report on its exploration activities in Chile, South America, and corporate developments for the quarter ended 30
More information30 October field conditions and. at surface. located. Khusib. resulted. Golden Deeps
30 October 2015 Quarterly Activities Report t for the period ended 30 September 2015 Golden Deeps Limited ( Deeps or the Company ) continued to progress the Grootfontein Base Metals Project in Namibia
More informationExploration Update: RC Drilling Commenced at Lucky Strike
L efroy ASX Announcement LEFROY EXPLORATION LIMITED Western Australian Focused Gold Explorer ASX Code: LEX Shares on Issue: 64.5m Current Share Price: 17c Market Capitalisation: $11m Board of Directors
More informationEXPLORATION ACTIVITY TO RECOMMENCE AT KOURI GOLD PROJECT IN BURKINA FASO
ASX/Media Announcement 26 April 2017 EXPLORATION ACTIVITY TO RECOMMENCE AT KOURI GOLD PROJECT IN BURKINA FASO Exploration program targeting the definition of a maiden JORC Mineral Resource by the end of
More informationRC drilling begins at Akoko Project marking commencement of 2010/11 exploration field season
29 th October 2010 September December Quarterly 2010 Quarterly Report 2008 Report Highlights RC drilling begins at Akoko Project marking commencement of 2010/11 exploration field season Major drill programs
More informationFor personal use only
Quarterly Report for quarter ended 30 September 2016 Meteoric Resources NL ABN 64 107 985 651 ASX Code: MEI Ground Floor 10 Outram Street West Perth WA 6005 T +61 8 9485 2836 F +61 8 9321 6571 E info@meteoric.com.au
More informationASX Announcement. FLEM survey underway at Henrietta Cobalt Nickel Prospect, Tasmania ASX: AX8 HIGHLIGHTS. Market Data. Board and Management.
FLEM survey underway at Henrietta Cobalt Nickel Prospect, Tasmania ASX Announcement Market Data ASX Code: AX8 Shares on Issue: 47,620,000 Board and Management Grant Mooney Non-Executive Chairman Andrew
More informationSilver City Minerals
ABN 68 130 933 309 ASX Code: SCI Silver City Minerals Annual General Meeting 15 November 2016 1 Important Disclaimer This presentation is provided to you for the sole purpose of providing background technical,
More informationASX Announcement. 28 January Drill results indicate large Porphyry Copper Gold System at Peenam
ASX Announcement 28 January 2010 Drill results indicate large Porphyry Copper Gold System at Peenam Highlights: 270 metres of visible copper (gold) mineralisation in first diamond core hole at Peenam Prospect
More informationFor personal use only
ASX:LEG 10 July 2014 Fraser Range Aeromagnetic Survey Identifies Targets Seven priority targets considered prospective for nickel-copper Targets interpreted to relate to intrusive mafic/ultramafic bodies
More informationHigh-grade Copper and Gold Discovered at Productora
ASX ANNOUNCEMENT Tuesday 25th September 2012 High-grade Copper and Gold Discovered at Productora Potential for High-grade Copper-Gold Shoots to Add New Dimension to Productora High-grade copper-gold discovered
More informationDIAMOND AND AIR CORE DRILLING TO COMMENCE ON WHITELAW GOLD BELT
ASX ANNOUNCEMENT 17 OCTOBER 2017 DIAMOND AND AIR CORE DRILLING TO COMMENCE ON WHITELAW GOLD BELT Reconnaissance Air Core drilling to commence at Macorna Bore and Sebastian Projects Diamond drilling planned
More information60% upgrade of Flying Doctor Resource to 104,600 tonnes of contained zinc and lead.
30 April 2008 60% upgrade of Flying Doctor Resource to 104,600 tonnes of contained zinc and lead. Perilya Limited (ASX: PEM) is pleased to announce a 60% increase in the mineral resource estimate for the
More informationExploring the Kombat Copper Trend Otavi Mountain Land, Northern Namibia
Exploring the Kombat Copper Trend Otavi Mountain Land, Northern Namibia Annual General Meeting Perth, Western Australia ASX Code - SBR 29th of November 2013 explore extend extract Disclaimer & Declaration
More informationAdditional significant gold and copper intercepts obtained in Sweden
18 November 2009 Additional significant gold and copper intercepts obtained in Sweden Drake Resources (ASX: DRK, Drake ) is pleased to announce that additional significant assays for the drilling programme
More informationFor personal use only
ASX ANNOUNCEMENT & MEDIA RELEASE 2 September 2015 COHERENT COPPER SULPH HIDE HALO DEFINED AT GUCHAB SOUTH H HIGHLIGHTS Disseminated metres. copper mineralisation at Guchab Southh exposedd over 850 x 100
More informationFor personal use only
18 April 2018 ASX Announcement DRILLING UNDERWAY AT SLATE DAM GOLD PROJECT HIGHLIGHTS 2nd Phase Drilling Program underway at Slate Dam - 9 RC holes for ~1,000m completed to date Program designed to expand
More informationFor personal use only
22 May 2012 Thick, high-grade copper intersection from First Extension Hole Assays at A-Zone, reaffirming the growth potential of the Viscaria Project Highlights Drill hole VDD0125 intersects 18.6m @ 1%
More informationFor personal use only
Exploring the Kombat Copper Trend Otavi Mountain Land, Northern Namibia Africa Down Under Conference Perth, Western Australia ASX Code - SBR August 2013 Disclaimer & Declaration This presentation has been
More informationFor personal use only
ASX ANNOUNCEMENT By e-lodgement 7th April 2017 Ground Magnetics Highlights Targets on 20km Gold Anomaly, Korhogo Project Cote d Ivoire (, the Company) is pleased to report first geophysical images have
More informationFURTHER DISCOVERY KM COPPER PROJECT
FURTHER DISCOVERY KM COPPER PROJECT ASX Release 24 October 2011 VOYAGER RESOURCES LIMITED ACN 076 390 451 Level 1 / 33 Richardson Street WEST PERTH stralia Tel: +61 8 9200 6264 Fax: +61 8 9200 4469 Contact:
More informationFor personal use only
ASX and Media Release 22 June 2018 CÁRMENES COBALT-COPPER PROJECT SPAIN DRILLING APPROVALS GRANTED AND NEW HIGH- PRIORITY TARGETS GENERATED NEAR PROFUNDA COBALT-COPPER MINE ACN 143 042 022 Suite 1, 6 Richardson
More informationGrowth Through Exploration
ROX RESOURCES LIMITED PRESENTATION ASX: RXL Ian Mulholland, Managing Director RIU Explorer s Conference 13 February 2013 Growth Through Exploration 1 Competent Person Statement The information in this
More informationFor personal use only
Citadel Project LandTEM Electromagnetic Survey Detailed Update No. 1 Magnum Unlocked Corker Unearthed Highlights The LandTEM electromagnetic survey showed the Magnum Deposit to have a significant electromagnetic
More informationSignificant Copper-Gold JORC Exploration Target
12 March 2013 Highlights: ASX & MEDIA ANNOUNCEMENT Significant Copper-Gold JORC Exploration Target ü JORC i Exploration Target 1 of 4.8-6.2Mt @ 2.00-2.78% Cu and 1.23-2.23g/t Au confirmed. ü Opportunity
More informationFor personal use only
30 May 2012 Potential 500 to 800 million tonne magnetite target zone( * see note below) identified from geophysical data modelling of HELITEM survey at Gabanintha. ASX [YRR]. Web page: www.yellowrock.com.au
More informationSILVER CITY MINERALS LIMITED ABN Silver City Minerals
ABN 68 130 933 309 ASX Code: SCI Silver City Minerals Annual General Meeting 20 November 2014 SILVER CITY MINERALS SNAPSHOT BROKEN HILL (Ag-Pb-Zn) Project Review and Prioritization: Focus and Plan Razorback
More informationFor personal use only
ASX ANNOUNCEMENT 29 July 2011 KATANNING UPDATE GOLD DISCOVERED AT JACKSON First-pass drilling at Jackson confirms presence of primary gold mineralisation Potential for third ore body at the Katanning Gold
More informationCOARSE GRAINED MAGNETITE DISCOVERED NORTH OF YORK
ASX Release ASX code: MAU 27 April 2012 Level 2, 16 Ord St West Perth WA 6005 PO Box 1388 West Perth WA 6872 Telephone 08 9226 1777 Facsimile 08 9485 2840 info@magres.com.au www.magres.com.au ABN 34 121
More informationNorthern Mining Limited 2012 Annual General Meeting Presentation
NORTHERN MINING LIMITED Northern Mining Limited 2012 Annual General Meeting Presentation www.northernmining.com.au 23 November 2012 NORTHERN MINING LIMITED DISCLAIMER This presentation has been prepared
More informationNew Drilling Program Commences at Mutiny s Deflector Deposit
New Drilling Program Commences at Mutiny s Deflector Deposit Drilling Program Highlights 12,000 metre RC and diamond drilling program underway New drilling program targets strike extensions in the Northern
More informationDrilling Program Commences on Iron Oxide Copper Gold Targets
3 June 2008 Manager Company Announcements Company Announcements Office Australian Stock Exchange Limited Level 10, 20 Bond Street SYDNEY NSW 2000 ABN 42 082 593 235 Electronic delivery No of pages: 6 Drilling
More informationNorwest successfully lists on ASX, Drilling commenced at Warriedar Gold Project
ASX ANNOUNCEMENT 4 December 2018 ASX: NWM Norwest successfully lists on ASX, Drilling commenced at Warriedar Gold Project Norwest Minerals listed on the ASX 29 th November following its successful $6.6
More informationFor personal use only
South America s Emerging Gold Explorer ASX Release 22 November 2012 OUTSTANDING GEOPHYSICS RESULTS FROM ALUMBRE AND QUINUAL CONCESSIONS HIGHLIGHTS Independent review of the Alumbre and Quinual concessions
More informationRC DRILLING TO RESUME THIS WEEK AT CARLISLE REEFS
Magmatic Resources Ltd Level 1, 11 Lucknow Place West Perth WA 6005 Phone: +61 8 6102 2709 www.magmaticresources.com ASX / MEDIA ANNOUNCEMENT 21 August 2017 RC DRILLING TO RESUME THIS WEEK AT CARLISLE
More informationChalice, Higginsville Drilling
Chalice, Higginsville Drilling 31 May 2006 Eastern Goldfields Higginsville Chalice First results from Chalice Gold Mines Limited s (Chalice Gold Mines or Company) drilling program have been received. Chalice
More informationEXPLORATION LICENCE SURROUNDING THE HISTORIC FALUN COPPER MINE GRANTED
ASX ANNOUNCEMENT 30 August 2007 EXPLORATION LICENCE SURROUNDING THE HISTORIC FALUN COPPER MINE GRANTED The Drake-Zinifex Alliance application for an exploration licence that covers the historic Falun copper
More informationMalachite Resources Limited ABN
Malachite Resources Limited ABN 86 075 63 268 ASX Announcement ASX Code: MAR 27 October 20 NEW DRILLING RESULTS AT LORENA SUPPORT COMMENCEMENT OF MINING FEASIBILITY STUDY Malachite Resources Limited (
More informationASX ANNOUNCEMENT 4 March 2019 VTEM SURVEY COMMENCED OVER LORRAINE AND ADZ PROJECT AREAS
ASX ANNOUNCEMENT 4 March 2019 VTEM SURVEY COMMENCED OVER LORRAINE AND ADZ PROJECT AREAS The Company is pleased to announce the commencement of a detailed airborne electromagnetic geophysical survey over
More informationDrilling program commences on Cloncurry and Mount Isa projects
1P P May UASX/Media Announcement st 2009 Drilling program commences on Cloncurry and Mount Isa projects Key Points 1,700 metres reverse circulation drilling program over two prospects on untested geochemical,
More informationASX Announcement. New economic gold results confirm Dave East as an exciting new discovery. Highlights. 4 July 2011
4 July 2011 ASX Announcement New economic gold results confirm Dave East as an exciting new discovery Level 2, 9 Colin Street West Perth WA 6005 ABN 11 127 171 877 p (08) 9216 1000 f (08) 9481 7939 w www.predictivediscovery.com
More informationMOUNT DOROTHY AND ELAINE DOROTHY PROSPECTS UPDATE
ASX/Media Announcement 20 th September 2010 MOUNT DOROTHY AND ELAINE DOROTHY PROSPECTS UPDATE MT DOROTHY: Phase 2 diamond drilling to commence. ELAINE DOROTHY New copper zone discovered and to be drilled.
More informationFor personal use only
VICTORIAN PORPHYRY COPPER GOLD TENEMENTS GRANTED ASX ANNOUNCEMENT 13 AUGUST 2013 Mantle Mining Corporation Limited (ASX: MNM) is pleased to report that three exploration licences highly prospective for
More informationASX Release. 16 December 2010 LIMITED. EXPLORATION UPDATE Highlights
ASX Release EXPLORATION UPDATE Highlights Bonsiega Joint Venture tenements minimum expenditure commitment met by 30 November 2010 Commencement of power auger bedrock drilling program at Fouli Prospect
More informationEXTENSIVE GOLD TREND DISCOVERED AT THE BASAWA GOLD PROJECT, LIBERIA
Suite 9, 5 Centro Ave, Subiaco WA 6008 P.O. Box 457, West Perth, WA 6872, Australia Ph+61 8 9286 3045 Fax: +61 8 9226 2027 info@birimiangold.com ABN 11 113 931 105 11 April 2012 The Company Announcements
More informationFor personal use only
MEDIA RELEASE 10 October 2016 CITADEL PROJECT 2016 RC DRILLING PROGRAMME Highlights Reverse-Circulation (RC) drilling programme up to approximately 6,000m testing 20km corridor of Induced Polarisation
More informationNEW DISCOVERIES AT THE RED OCTOBER MINE
23 July 2013 ASX & MEDIA RELEASE NEW DISCOVERIES AT THE RED OCTOBER MINE The Directors of Saracen Mineral Holdings Limited (the Company ) are pleased to provide an update on the Red October underground
More informationASX RELEASE ACTIVITY UPDATE SPARGOVILLE PROJECT WA MINING AND EXPLORATION
Ramelius Resources Limited ACN 001 717 540 140 Greenhill Road, Unley SA 5061 GPO Box 1373, Adelaide SA 5001 DX 52003, Unley Telephone (08) 8373 6473 / (08) 8373 5588 Facsimile (08) 8373 5917 ASX RELEASE
More informationFor personal use only
About Convergent ASX Code: CVG CVG owns 100% of the Bounty Goldfield in Western Australia with 872,000 ounces of gold Our Aim CVG s key objective is to define high grade gold and to recommence gold production
More informationFor personal use only
ASX Announcement 15 March 2017 HIGHLIGHTS Drill contractors have been engaged with drilling to commence April 2017 pending access approvals Two mineralised lodes within the oxide volcanogenic massive sulphide
More informationFor personal use only
MOZAMBI COAL LTD (ASX: MOZ, Company or Mozambi ) ASX RELEASE 7 SEPTEMBER 2011 EXPLORATION PROGRAMME UPDATE is pleased to announce an update on exploration activities in Mozambique including the results
More informationHigh-grade Gold in First Drilling Undertaken at Productora South
ASX ANNOUNCEMENT Wednesday 10th October 2012 High-grade Gold in First Drilling Undertaken at Productora South Shallow, high-grade, narrow-vein gold area adds further up-side to Productora Sierra Zapallo
More informationUPDATE ON DRILLING TO BE CONDUCTED AT AURORA TANK GOLD PROJECT
ASX ANNOUNCEMENT 1 April 2015 UPDATE ON DRILLING TO BE CONDUCTED AT AURORA TANK GOLD PROJECT Attached for shareholders information, is an announcement made to the market by Apollo Minerals Limited (ASX:
More informationDrilling Commences at Telfer West Gold Project
Level 7, 600 Murray Street West Perth WA 6005 PO Box 273 West Perth WA 6872 P 08 9486 9455 F 08 6210 1578 www.enrl.com.au 17 November 2016 ASX : ENR Company Announcements Office Australian Securities Exchange
More informationFor personal use only
DEEP DRILLING AT GLANDORE AND BULLOO DOWNS DEEP DRILLING AT GLANDORE AND BULLOO DOWNS HIGHLIGHTS Glandore Gold Project Successful EIS application for a deep diamond drill hole Four large-scale parallel
More information