1 6 JOURNEES SCIENTIFIQUES ET TECHNIQUES Hôtel Hilton, 20 to 22 june 2004, Algiers, Algeria MULTI-DISCIPLINARY TEAMWORK DELIVERS OUTSTANDING KRECHBA HORIZONTAL WELL PERFORMANCE FOSTER, L. AIDOO, A. TOURQUI, A. CASTLE-SMITH, J. MEZDOUR, J. TAYLOR, M. (1) (1) In Salah Gas, BP513, Hassi-Messaoud, Algeria. Phone (213) ABSTRACT Krechba is one of seven fields in the In Salah Gas Development in District 3 of Algeria. Early in the FEED stage for Krechba up to 25 vertical wells were envisaged to develop the thin Carboniferous reservoir. To reduce development costs, feasibility studies were performed on the option of drilling 6-8 horizontal wells, which included 2-3 CO 2 injection wells. This option was later adopted in the Development Plan. The horizontal wells were planned with 1000m horizontal legs, but in the execution phase this target was increased to 1500m to increase well deliverability and injectivity. Due to the variable sand quality, sophisticated LWD tools were used to geosteer the horizontal section through zones of the best porosity, maximizing the productivity of the wells. Real-time reservoir modelling and visualization software was used at the rig site and in the Subsurface team in Sunbury (London), to aid decision making while drilling the horizontal section and to effectively communicate changes in the plan. Because of the existence of high tectonic stresses in the area, a wellbore stability study was performed before the start of drilling. However, severe instability problems were encountered in the first well, requiring a major re-design of the programme. Despite this, the well successfully reached a horizontal length of 1300m. These design changes were agreed at a peer review meeting, which brought together expertise from within Sonatrach and BP to analyse and review the development team s experiences and plans. Subsequent wells using the new design demonstrated a remarkable improvement in drilling performance and a significant learning curve. This achievement was due in no small part to the efforts of the Drilling and Petroleum Engineering, and Subsurface teams to maintain a close working relationship, despite being geographically widely separated between Sunbury, Hassi Messaoud, and Teguentour. Keywords: Horizontal Drilling, Wellbore Stability, Geosteering, Real-time Software INTRODUCTION 3. The project is a phased development with the first three fields (Krechba, Teguentour and Reg) to be brought on line during The other 4 fields (Garet El Befinat, Hassi Moumene, In Salah and Gour Mahmoud) will be developed later. The development team is split between Hassi Messaoud and Teguentour in Algeria and Sunbury in the UK. The approximate distance between the bases in Algeria and Sunbury is 2400km and approx 500 km between the bases in Algeria. KRECHBA FIELD The Krechba field is located in the Northern part of the development area. There are three main reservoirs (see Fig. 1). The Carboniferous C10.2 sands are being developed for first gas in In addition to production, the C10.2 reservoir has been identified as suitable for CO2 injection below the Gas Water Contact. Lisbon Tangiers M O R O C C O MAURITANIA S P A I N Cordoba Cartagena ALGERIA M A L I Hassi R Mel Proposed ISG Pipeline Krechba Reg Garet el Befinat In Salah Algiers Fig. 1: In Salah Gas project location Teg Hassi Messaoud Hassi Moumene Gour Mahmoud Sunbury 1500 miles Skikda Hassi Bir Rekaiz REB Tiguentourine (BP) Tunis L I B Y A In Salah Gas Project N I G E R The In Salah Gas project consists of 7 fields within District

2 The In Salah Gas Project needs to strip out CO2 from produced gas in order that Sales Gas meets contractual specifications at the point of entry into Sonatrach s Northern Natural Gas Network in Hassi R Mel. Disposal of CO2 into the atmosphere is not an option, given Joint Venture s goals to reduce greenhouse gas emissions. Storage within an aquifer within the project area is therefore the only viable option available to the project. The Krechba field C10.2 aquifer has been identified as the most suitable within the area. The C10.2 sand is a thin, continuous structure with a low relief approximately metres thick at about 1800m depth. To develop this reservoir with vertical wells would have required approximately 25 penetrations, which was quickly eliminated as uneconomic. The field Development Plan, based on 2D seismic, therefore featured horizontal wells with 1000m legs in the reservoir. Due to uncertainty on the reservoir top and the thin section, it was anticipated that only 60% of the horizontal length would be in the reservoir itself. Based on this assumption, the Development Plan required four producing wells and three CO2 injectors. KRECHBA-501 FIRST CO2 INJECTOR WELL Fig. 2 shows the original trajectory (yellow) for KB-501, that was based was based on 2D mapping (net pore thickness). When the 3D porosity cube was loaded into the EarthVision software it became apparent that the original planned trajectory would not intersect the higher porosity lobes, which would have reduced the available injectivity in the well. The wellbore stability study performed in BP s Technology Group in Sunbury indicated that, due to the regional tectonic stresses, the preferred orientation for drilling directional wells was in the North-West South-East plane. All of the horizontal wells were therefore planned in this direction and the surface locations were built in advance of the start of drilling, based on the bottom hole targets in the Plan of Development. From offset wells, the most problematic formation was anticipated to be the Visean mudstone. The well was designed so that the 13-3/8 casing would be set in the upper part of the Visean, below the deepest incidence of lost circulation from the offset wells in which it had been a major problem. The mud weight would then be increased to approximately sg to control these mudstones until the next casing point, which would be set just above the reservoir in the C10.3 sandstone. The mud weight selected for the Visean interval was based on offset vertical wells, and the wellbore stability study, which predicted that a 1.2 sg mud weight would be sufficient to counteract the tectonic stresses at the planned deviation. Fig. 3 shows the typical field lithology. Lithology Cretaceous Superieur 171m TVD Continental Intercalaire Lost Circulation Alert Possible losses in Continental Intercalaire & Upper Visean 940m TVD KB501 w KB501 orig Visean Mudstone C20 Possible Packing Off Be alert for unstable Visean Hot Shale 1591m TVD KB501 x Fig. 2: KB-501 Original (yellow) and revised (blue) directional paths The well was therefore redesigned, red in the overburden and blue in the reservoir section, to intersect these lobes and the well length increased from 1000 to 1300m. In addition the pilot hole (KB-501x) can be seen in green. The new trajectory was a 3D design with changes in the azimuth in both the overburden and reservoir sections. C m TVD C m TVD D m TVD Fig. 3: Krechba field lithology column and drilling hazards During drilling of the KB501 well 12¼ section, hole problems soon indicated that there was wellbore instability, which was not being controlled with the mud weight in use. In particular as the hole angle increased close to 60 poor hole cleaning and cuttings beds caused severe tight hole.

3 These problems were compounded by frequent mud pump failures. Several packoffs and twist-offs were experienced in the lower part of the Visean, requiring the 12¼ hole to be sidetracked three times. The mud weight was eventually raised to the maximum that the 13-3/8 LOT would allow, i.e. 1.3 sg, without losses. However, it was necessary to set 9-5/8 casing early because, based on the experience prior to sidetracking, this was still not expected to be sufficient to control the lower Visean. Following a detailed review of all the drilling data and hole problems from the first three attempts to drill the 12¼ section the ISG Wells Team decided that a mud weight of 1.45 sg would be required for this mudstone. Since this was above the LOT value at the 13-3/8 shoe, it was necessary to set 9-5/8 casing and drill 8-½ hole through the lower Visean troublesome interval. This interval had been observed in offset vertical wells as an exceptionally washed-out section and was referred to as the C20.2 unstable zone, with direct correlation possible from the gamma ray logs. This enabled the rig site geologist to pick the 9-5/8 casing point just above this zone from the MWD On the third attempt the 12-¼ section was successfully drilled to 1872m MD just above the unstable zone and 9-5/8 casing was run and cemented at 1869 m MD. On drilling out the 9-5/8 shoe a LOT was performed to 1.66 sg, which allowed the mud weight to be raised to 1.45 sg. The 8½ interval was then drilled with no hole problems through the so-called unstable zone to 2027m MD, and a 7 drilling liner was run and cemented. The setting depth of this liner was also changed from the plan, since the mud weight was now much higher than originally expected, in order to avoid losses in the C10.3 sandstone. The liner was therefore set just into the top of the C10.3 instead of in the middle. The key lessons learned from KB501 were therefore: The mud weight required for the upper and lower Visean sections are different. In the upper section 1.3 sg is sufficient. The C20.2 lower Visean requires a higher mud weight than the leak-off at the 13-3/8 shoe will support. Because of this, a casing point is required above the Visean unstable zone. Drilling practices in the Visean are extremely important. The directional BHA s on KB501 were designed to build angle mainly in oriented mode, which aggravated hole cleaning problems due to the lack of pipe rotation. For subsequent wells BHA s were designed to build angle at the required rate in rotary mode. The directional profile was modified slightly to have more of the build to horizontal in the 6 hole to enable the 12-¼ and 8-½ intervals to be drilled mostly in rotary mode. Experience on KB501 showed that higher build rates were possible in the 6 hole than had previously been anticipated. The use of low viscosity followed by high weight (1.6 sg), high viscosity pills at each connection in the 12-¼ hole, is crucial to maintaining good hole cleaning. Large quantities of fine cuttings and cavings were seen in returns from the original hole when these sweeps were pumped. Wiper trips do not improve poor hole conditions in the tectonically stressed Visean in fact, when performed excessively, appear to aggravate them. The best solution to poor hole conditions is to prevent them occurring in the first place by use of the correct mud weight and good drilling practices. Following setting the 7 liner, a 6 pilot hole was drilled, cored and logged to TD below the C10.2 reservoir. The pilot hole was then plugged back and sidetracked to horizontal. Because the 7 liner had been set shallower than originally planned it was not necessary to use a whipstock, and the sidetrack was successfully achieved in 6 open hole in the C10.3 sandstone. The horizontal section was drilled with water-based mud weighted with calcium carbonate, with lubricants used to reduce torque. TD was reached at 3400m MD, of which 1300m was horizontal. A 4-½ pre-perforated liner was run and the well was treated with an organic acid to dissolve any mud filter cake and calcium carbonate solids. The liner included a non-return valve to isolate the horizontal section from the completion brine during the displacement from drilling mud. The 5 completion was then run, and the well was tested by injecting brine into the formation. The well was completed and tested in 153 days from spud, compared to the AFE of 93 days. Before spud of the second well, a Peer Review meeting was held in Sunbury with representatives from the ISG Wells and Subsurface teams, Sonatrach, and BP s Technology Group. The purpose of the meeting was to review the well data from KB501, and also to see how the plans for the first production well KB11, had been modified to incorporate lessons learned from KB501. The Peer Review team examined the ISG Wells Team proposals and recommended that as far as possible, the well design modifications that had been successful in allowing KB501 to reach TD should be duplicated in KB11 and future wells. This involved a change of production hole size from 8½ to 6, but the Subsurface team confirmed that this would not significantly impact the productivity of the wells. The other change to the KB11 well design was that, based on the 1300m achieved in KB501, the horizontal section for KB11 was extended to 1500m to maximize productivity. However, based on the 3D porosity modelling, extending the original plan by 500m would have taken the well parallel to a fault and into an area of very low porosity. This would have caused two potential problems: 1. Drilling parallel to a fault could be a hazard, there is a rubble zone associated with a fault plane and the lower the intersection angle between the wellbore trajectory and fault plane the longer the

4 bit spends in this zone, this increases the chance of a pack off, stuck pipe and losing the bottom hole assembly. 2. The lower porosity zone would have an impact on production. The low porosity zone had permeability in the fractions of a millidarcy and thus the incremental rate contribution from the extension would be very low. The well needed to be redesigned to avoid these challenges. In conjunction with the drilling team, a 3D trajectory was designed with a turn to the left keeping the well in higher porosity rock along the entire 1500m length. (See Fig. 4). so an ABI (At-Bit Inclination) sub was run to ensure the most accurate survey data was available. This was important to allow real-time decisions to be made concerning the well trajectory while drilling Days from Spud KB-11 KB-501 Fault C10.2 D70 Original planned KB-11 KB-2 Depth m Redesigned KB Change in Overburden Trajectory Fig. 4 KB-11 original and revised directional plan KRECHBA-11 FIRST PRODUCTION WELL KB-11 was spudded on 4 Feb The revised plan, with the 9-5/8 set above the C20.2 Visean unstable zone was followed and was extremely successful in avoiding the hole problems seen in KB501. The AFE time for KB11 was days, and the actual from spud to release was 79 days. Non-productive time was only 7% compared to 42.5% on KB501. Clearly, the design changes and incorporation of the lessons learned from KB501 were very successful in improving performance. A comparison of the time vs. depth curves is shown in Fig. 5. With the problems in the overburden largely solved, it was necessary to concentrate on the reservoir section to ensure that the primary objective of the well, to produce at least 85mm scf/d of gas, would be met. The thin reservoir section and the variable porosity dictated that the well path should be geosteered by real-time LWD tools in order to maximize the productivity of the well. Sperry-Sun Neutron Density tools were used in the horizontal section to allow real-time measurement of the formation porosity. Because of the length of the BHA the directional measurements were almost 20m behind the bit, Fig. 5: Comparison of KB-501 and KB11 time vs. depth plots GEOSTEERING Geosteering is the ability to react to changes in the prognosed plan often caused by sub-seismic reservoir heterogeneity or drilling challenges. Plans are based on seismic interpretation, structural modelling, analogues and offset well data. When drilling the reservoir section the observed data will often differ from the prognosis and the planned trajectory will have to be changed to take into account these observations in order to optimise production. In addition there could be drilling challenges e.g., the bit drifts to the left or right, these changes to the plan need to be examined, often it might not be necessary to spend rig time returning to the plan. While drilling the reservoir the trajectory and MWD data were updated and loaded into the model at the rig site after every stand. The forward plan was then discussed between the rig site geologist, directional driller and drilling engineer, and progress against the plan was monitored. Trajectory and MWD data were updated after each survey point, and the forward plan discussed with directional driller. The drilling supervisor was updated with progress and plans two or three times a day. Updates were sent to Sunbury whenever necessary.

5 K 11 K 11 Porosity trajectory drift to the left and cut the corner. Fig. 7 shows KB-11 planned trajectory in blue and drilled trajectory colour coded with porosity, the amended trajectory is in red. The brown surface shows the base of the reservoir and the 3D bodies show porosity (from seismic) less than 7% (areas of possible drilling hazards). Upon examination of the real time porosity data it was decided drill to a higher TVD than planned in the reservoir and not to return to the original path following the turn, but to continue along the revised azimuth. Fig. 6: KB-11 area showing porosity < 7%, planned well in blue and partially drilled well colour coded with real time porosity 766m into reservoir section Fig. 6 shows the first change to the planned KB-11. The planned trajectory is in blue and drilled trajectory colour coded with porosity. The brown surface shows the base of the reservoir and the 3D bodies show porosity (from seismic) less than 7% (areas of possible drilling hazards). The challenge was that the bit was drifting to the left and the directional drillers were concerned about the 7 dogleg turn. From the porosity cube there were no hazards to the left of the trajectory, and so it was possible to let the Geosteering decisions and model updates were made at the rig site and the incremental changes were sent to Sunbury. EarthVision software (EV) was used at both sites to view the progress of the well. It was possible to view the same data at each site and synchronize the views i.e., when the view was changed at one site this change was seen at the other. The power of these collaborative sessions should not be underestimated. The progress of the well can be readily understood and the forward plan easily communicated. One major advantage of these sessions is seen when further input is required. At the rig site it is possible to access the geologic model and limited seismic, if the observed results are not as prognosed. It is then possible to use the expertise and further seismic in Sunbury to formulate a forward plan, which is then discussed with the operations teams in Teguentour and Hassi-Messaoud. The whole team are then involved in the geosteering decisions. KB-11 Change 2 KB-11 Plan KB-11 Change 2 KB-11 Plan KB-11 Actual KB-11 Actual Porosity < 7% Fig. 7: KB-11 horizontal and vertical views after 861m drilled in the reservoir section

6 KB-11 RESULTS The KB-11 well reached TD of 3445m after only 57 days from spud, 29 days ahead of AFE, despite drilling 340m incremental horizontal section. A total section of 1500m was drilled with 100% in the reservoir. The production from the well was estimated at 3.4 x 10 6 m3/day (120mm scf/d) compared to the original expectation of 2.4 x 10 6 m3/day (85mm scf/d). The successes of this well were due mainly to several key factors: The detailed review of lessons learned from KB501 and application of these to the design of KB11, incorporating advice and expertise from both BP and Sonatrach By deviating vertically from the planned horizontal section it was possible to remain in higher porosity rock which drills with a faster rate of penetration. By managing the drilling challenges through forward planning, with cooperation between, and input from drilling, subsurface and petroleum engineering, rather than just trying to return to the original plan. SUBSEQUENT WELLS The next wells on the field, KB-13, KB-12 and KB-503 all benefited from the same design changes as were successfully used in KB-11. The drilling performances all showed the same substantial improvement over KB-501. Horizontal sections 1500m long were drilled in all the wells except KB-12 which encountered a fault in the reservoir, causing substantial lost circulation that prevented further progress. The improvement in performance can be seen from the chart of drilling days per 3208m (10,000 ft) drilled (see Fig. 8) Dry Hole days per 3208m (10K ft) Enafor 19 Enafor 20 In addition to the marked increase in drilling performance, the results of the production well tests showed that the first gas production commitment of 7.64 x 10 6 m3/day (270 mmscf/day) could be met with three production wells instead of four, and the CO2 injection requirement could be met with two wells instead of three. The mud weights required to counteract the wellbore stability problems in the Visean mudstone were underestimated in the Krechba pre-planning stage. The wells on which the stability studies were based were vertical, and lost circulation was expected to be a more severe problem than wellbore instability. The experiences on KB-501 showed that significantly higher mud weights were required in the deviated sections than expected. The casing programme selected at the Krechba preplanning stage did not allow the required mud weight to be used in the Lower Visean unstable zone C20.2. It was necessary to modify the programme to allow the 9-5/8 casing to be set above this zone. The multi-disciplinary Peer Review by personnel from both Joint Venture partners was critical in deciding how to best incorporate the lessons learned from KB-501 into the plans for subsequent wells. Utilization of the new plans on subsequent wells led to significantly improved drilling performance. Use of real-time software to model the reservoir during the horizontal sections allowed the geologists and directional drillers flexibility to optimise the plans without compromising well objectives. With 3D geologic visualization it has become easier to share information and ideas, not only within the Subsurface but also the Drilling community. The reasons why certain decisions are made become very clear when viewed using a 3D solid earth model. ACKNOWLEDGEMENTS KB501 KB11 KB12 KB13 KB503 Fig. 8: Krechba drilling progress learning curve The authors wish to thank all of the Sonatrach and BP personnel that assisted with overcoming the severe problems experienced on KB-501, and provided support and encouragement to the ISG Wells and Subsurface teams in formulating a successful forward plan.

Precise well placement in the Cygnus gas field. Ian Dredge ENGIE E&P UK Limited

Precise well placement in the Cygnus gas field. Ian Dredge ENGIE E&P UK Limited Precise well placement in the Cygnus gas field Ian Dredge ENGIE E&P UK Limited Executive summary The Lower Leman reservoir in the Cygnus gas field is highly layered with low vertical permeability The use

More information

Advances in Geosteering

Advances in Geosteering Advances in Geosteering SMART4D While Drilling Geosteering Marcellus Case Study Joint Presentation: Feb 27 th 2014, Houston, TX Rocky Mottahedeh, P.Geol. P.Eng. EOW Report University_31_18_2H Advances

More information

Horizontal Drilling Pilot In a Shallow Heavy Oil Reservoir in Northwestern Romania. Authors: John Lavelle, Amin Yaghoobi

Horizontal Drilling Pilot In a Shallow Heavy Oil Reservoir in Northwestern Romania. Authors: John Lavelle, Amin Yaghoobi Horizontal Drilling Pilot In a Shallow Heavy Oil Reservoir in Northwestern Romania Authors: John Lavelle, Amin Yaghoobi About Suplac Oil Field Discovered 1958 Oil Density 960 kg/m3 (16 API) Viscosity 2300

More information

X,800. X,850 ft. X,900 ft. X,950 ft. X,000 ft. GeoSphere. Reservoir Mapping-While-Drilling Service

X,800. X,850 ft. X,900 ft. X,950 ft. X,000 ft. GeoSphere. Reservoir Mapping-While-Drilling Service X,800 X,850 ft X,900 ft X,950 ft X,000 ft GeoSphere Reservoir Mapping-While-Drilling Service Discover reservoir mapping-while-drilling...... and reveal subsurface beddings and fluid contacts at the reservoir

More information

Cornish Institute of Engineers Conference th October 2013

Cornish Institute of Engineers Conference th October 2013 Wellbore Stability and Real Time Drilling Optimisation: Delivered Worldwide from Cornwall Sarah Marks Cornish Institute of Engineers Conference 2013 11 th October 2013 GeoScience Limited, Falmouth Business

More information

Drillworks. DecisionSpace Geomechanics DATA SHEET

Drillworks. DecisionSpace Geomechanics DATA SHEET DATA SHEET Drillworks overview DecisionSpace Geomechanics Key features Pre-drill, real-time, and post-drill analyses are all easily performed in one application using the latest data from across the field

More information

DEVEX Moving in the Right Direction; Realising Upside Potential in a Mature Field Using Real Time 3D Geo-Steering Technology

DEVEX Moving in the Right Direction; Realising Upside Potential in a Mature Field Using Real Time 3D Geo-Steering Technology DEVEX 2010 Moving in the Right Direction; Realising Upside Potential in a Mature Field Using Real Time 3D Geo-Steering Technology Authors: Lisa Chisholm, Chevron Upstream Europe David Holbrough, Baker

More information

Fluids, Hole Cleaning and Tripping Optimization

Fluids, Hole Cleaning and Tripping Optimization Fluids, Hole Cleaning and Tripping Optimization Overview Hole cleaning in highly deviated wells is probably one of the most misunderstood concepts. Primarily, relying on Plastic Viscosity and Yield Point

More information

Oil Company Company et al Foothills W6

Oil Company Company et al Foothills W6 800, 555 4 th Avenue SW, Calgary, AB T2P 3E7 Off: 403-234-7625, www.wellsitegeologists.com Cell: 660-9883, Dennis@WellsiteGeologists.com Geological Report for Oil Company Company et al Foothills 06-06-060-06W6

More information

Predicting the path ahead

Predicting the path ahead Predicting the path ahead Horizontal drilling has become a routine procedure in many parts of the world and is particularly popular in the Middle East. Despite increasing familiarity with the techniques,

More information

Directional Drilling. History

Directional Drilling. History Directional Drilling Directional drilling is the science of deviating a well bore along a planned course to a subsurface target whose location is a given lateral distance and direction from the vertical.

More information

Practical Application of Directional Drilling at Takigami Geothermal Field

Practical Application of Directional Drilling at Takigami Geothermal Field Proceedings World Geothermal Congress 2005 Antalya, Turkey, 24-29 April 2005 Practical Application of Directional Drilling at Takigami Geothermal Field Hisashi Jotaki 1 and Keisuke Ushijima 2 1 Idemitsu

More information

Shale Development and Hydraulic Fracturing or Frac ing (Fracking) What is it?

Shale Development and Hydraulic Fracturing or Frac ing (Fracking) What is it? P E T R O L E U M E N G I N E E R I N G D E P A R T M E N T Shale Development and Hydraulic Fracturing or Frac ing (Fracking) What is it? Dr. Will Fleckenstein, PE Colorado School of Mines 1 Who is involved

More information

The Deployment of an Azimuthal Resistivity Tool for Geosteering - A Case Study from the Foinaven Field (North Sea)*

The Deployment of an Azimuthal Resistivity Tool for Geosteering - A Case Study from the Foinaven Field (North Sea)* The Deployment of an Azimuthal Resistivity Tool for Geosteering - A Case Study from the Foinaven Field (North Sea)* Martin Bedrock 1 and Darren Moody 1 Search and Discovery Article #40540 (2010) Posted

More information

Drilling Challenges Related to Geopressure Compartmentalization Selim S. Shaker, Geopressure Analysis Services (G.A.S.)

Drilling Challenges Related to Geopressure Compartmentalization Selim S. Shaker, Geopressure Analysis Services (G.A.S.) AADE-05-NTCE-11 Drilling Challenges Related to Geopressure Compartmentalization Selim S. Shaker, Geopressure Analysis Services (G.A.S.) This paper was prepared for presentation at the AADE 2005 National

More information

Ensuring integrity of shale gas wells in Europe

Ensuring integrity of shale gas wells in Europe M4Shale Gas Final Conference, Krakow, Poland 19.10.2017 Ensuring integrity of shale gas wells in Europe M. Torsæter, K. Gawel, J. Todorovic, A. Stroisz, R. Skorpa and A. Lavrov SINTEF Petroleum Research,

More information

J.V. Herwanger* (Ikon Science), A. Bottrill (Ikon Science) & P. Popov (Ikon Science)

J.V. Herwanger* (Ikon Science), A. Bottrill (Ikon Science) & P. Popov (Ikon Science) 29829. One 4D geomechanical model and its many applications J.V. Herwanger* (Ikon Science), A. Bottrill (Ikon Science) & P. Popov (Ikon Science) Main objectives (i) Field case study demonstrating application

More information

Case History of First Liner Drilling Application in Romania

Case History of First Liner Drilling Application in Romania Case History of First Liner Drilling Application in Romania Ali Qureshi Well Delivery Team Leader-Team-5 OMV Petrom S.A. Bucharest, 28 th April 2016 Agenda Introduction Background (well design, prognosis

More information

Optimizing Drilling Performance by Wellbore Stability and Pore-Pressure Evaluation in Deepwater Exploration T. Klimentos, Schlumberger

Optimizing Drilling Performance by Wellbore Stability and Pore-Pressure Evaluation in Deepwater Exploration T. Klimentos, Schlumberger IPTC 10933 Optimizing Drilling Performance by Wellbore Stability and Pore-Pressure Evaluation in Deepwater Exploration T. Klimentos, Schlumberger Copyright 2005, International Petroleum Technology Conference

More information

EGYPT: SILDRIL Gives Top Performance in Nile Delta Well

EGYPT: SILDRIL Gives Top Performance in Nile Delta Well PERFORMANCE REPORT EGYPT: SILDRIL Gives Top Performance in Nile Delta Well The operator (PETROBEL) was faced with drilling a 8½ hole through reactive Kafr El-Sheikh shales and unconsolidated sands from

More information

Halliburton Engineering for Success in Developing Shale Assets

Halliburton Engineering for Success in Developing Shale Assets Halliburton Engineering for Success in Developing Shale Assets Nov 30, 2010 Shale is a Very Broad Name Used to Describe a Large Category of Rock In conventional petroleum geology shale is thought of as

More information

Pressure Regimes in Deep Water Areas: Cost and Exploration Significance Richard Swarbrick and Colleagues Ikon GeoPressure, Durham, England

Pressure Regimes in Deep Water Areas: Cost and Exploration Significance Richard Swarbrick and Colleagues Ikon GeoPressure, Durham, England Pressure Regimes in Deep Water Areas: Cost and Exploration Significance Richard Swarbrick and Colleagues Ikon GeoPressure, Durham, England FINDING PETROLEUM 26 th September 2012 OUTLINE of PRESENTATION

More information

MUDLOGGING, CORING, AND CASED HOLE LOGGING BASICS COPYRIGHT. Coring Operations Basics. By the end of this lesson, you will be able to:

MUDLOGGING, CORING, AND CASED HOLE LOGGING BASICS COPYRIGHT. Coring Operations Basics. By the end of this lesson, you will be able to: LEARNING OBJECTIVES MUDLOGGING, CORING, AND CASED HOLE LOGGING BASICS Coring Operations Basics By the end of this lesson, you will be able to: Understand why cores are justified and who needs core data

More information

Downhole Navigation for Oil & Gas Drilling

Downhole Navigation for Oil & Gas Drilling Downhole Navigation for Oil & Gas Drilling Martin E. Poitzsch Research Director, Sensor Physics Schlumberger-Doll Research, Cambridge, MA A Division of Schlumberger Ltd. Outline Importance of Accurate

More information

AGENDA. Criteria for Fluid Selection Controlling Cost Continuously Improving Performance

AGENDA. Criteria for Fluid Selection Controlling Cost Continuously Improving Performance AGENDA Criteria for Fluid Selection Controlling Cost Continuously Improving Performance WELLBORE STABILITY & HOLE ENLARGEMENT DRILLING FLUIDS COMPARISON Non Aqueous Fluids (diesel, synthetic, etc.) Brine

More information

Seismic Guided Drilling: Near Real Time 3D Updating of Subsurface Images and Pore Pressure Model

Seismic Guided Drilling: Near Real Time 3D Updating of Subsurface Images and Pore Pressure Model IPTC 16575 Seismic Guided Drilling: Near Real Time 3D Updating of Subsurface Images and Pore Pressure Model Chuck Peng, John Dai and Sherman Yang, Schlumberger WesternGeco Copyright 2013, International

More information

APPLICATION FOR AUTHORITY TO DRILL A WELL (ADW)

APPLICATION FOR AUTHORITY TO DRILL A WELL (ADW) APPLICATION FOR AUTHORITY TO DRILL A WELL (ADW) Operator: Pursuant to section 8 and 9 of the Petroleum and Natural Gas Act (R.S.N.L. 1990, c. P-10) and in compliance with section 29 of the Petroleum Drilling

More information

New downhole technologies helped develop horizontal thin sand

New downhole technologies helped develop horizontal thin sand Reprinted from: June 2005 issue, pgs 25-33. Used with permission. DRILLING AND COMPLETION TECHNOLOGY SPECIAL FOCUS New downhole technologies helped develop horizontal thin sand Completion of Well Ewan-YH

More information

Can Geomechanics Improve Your Drilling and Completions?

Can Geomechanics Improve Your Drilling and Completions? Can Geomechanics Improve Your Drilling and Completions? Spoiler Alert Yes. CSPG Operations Geology Division March 15, 2018 Presented by Amy Fox, Ph.D., P.Geo. Introduction Montney AFE vs. Actual Drilling

More information

Antelope Hills Directionally Drilled Water Well. Theresa Jehn-Dellaport Jehn Water Consultants, Inc.

Antelope Hills Directionally Drilled Water Well. Theresa Jehn-Dellaport Jehn Water Consultants, Inc. Antelope Hills Directionally Drilled Water Well Theresa Jehn-Dellaport Directional Well Applications Deep Bedrock Aquifers Proven Oil field technology Initial Analysis indicates up to 4 times the production

More information

GEOSTEERING Scope of work, project management and geosteering scenarios

GEOSTEERING Scope of work, project management and geosteering scenarios GEOSTEERING Scope of work, project management and geosteering scenarios Chinook Consulting Services Office: 403 242 1522 742 Memorial Drive NW Calgary, Alberta T2N 3C7 reports@chinookconsulting.ca www.chinookconsulting.ca

More information

geovision Resistivity imaging for productive drilling

geovision Resistivity imaging for productive drilling geovision Resistivity imaging for productive drilling geovision Resistivity imaging while drilling helps position wells in the best place in the reservoir in less time. Real-time resistivity measurements

More information

Western Kentucky CO 2 Storage Test

Western Kentucky CO 2 Storage Test Western Kentucky CO 2 Storage Test Principal Investigators: Rick Bowersox - Lexington Dave Williams - Henderson KGS First Friday Seminar Lexington, Kentucky March 4, 2011 The project proceeded in two phases:

More information

NOTICE CONCERNING COPYRIGHT RESTRICTIONS

NOTICE CONCERNING COPYRIGHT RESTRICTIONS NOTICE CONCERNING COPYRIGHT RESTRICTIONS This document may contain copyrighted materials. These materials have been made available for use in research, teaching, and private study, but may not be used

More information

Multi-target wells: a new concept to improve well economics

Multi-target wells: a new concept to improve well economics Multi-target wells: a new concept to improve well economics OMV AG, Vienna, Austria ABSTRACT: The Vienna Basin is a sedimentary basin more than 10 km in thickness and composed of more than a dozen hydrocarbon

More information

AADE-06-DF-HO-33. Copyright 2006, AADE Drilling Fluids Technical Conference

AADE-06-DF-HO-33. Copyright 2006, AADE Drilling Fluids Technical Conference AADE-6-DF-HO-33 Flexible Drilling Fluid Helps to Drill High Pressure Wells Offshore Louisiana Dave Smalling, Fairways Offshore Exploration, Inc; Mike Reid, Newpark Drilling Fluids, LLC; Mike Deshotels,

More information

Realtime Geopressure and Wellbore Stability Monitoring while Drilling. Eamonn Doyle VP Real-time Operations

Realtime Geopressure and Wellbore Stability Monitoring while Drilling. Eamonn Doyle VP Real-time Operations Realtime Geopressure and Wellbore Stability Monitoring while Drilling Eamonn Doyle VP Real-time Operations 1 2 Main points 1. Why bother with PPwD? Isn t the prognosis good enough? 2. Can it be justified?

More information

Heterogeneity Type Porosity. Connected Conductive Spot. Fracture Connected. Conductive Spot. Isolated Conductive Spot. Matrix.

Heterogeneity Type Porosity. Connected Conductive Spot. Fracture Connected. Conductive Spot. Isolated Conductive Spot. Matrix. Porosity Histogram Porosity Contribution 1.3.3.3 Connected 9.8 ohm.m U R D 9 18 7. 5.25 4.38 3.5 2.63 1.75 48 Heterogeneity Distribution Image Orientation, L U 27 36.4.3 X,X72.5 Depth, ft.3 1 Isolated.3

More information

ractical Geomechanics for Oil & Gas Industry

ractical Geomechanics for Oil & Gas Industry P ractical Geomechanics for Oil & Gas Industry Practical Geomechanics for Oil and Gas Industry The integrity of the wellbore plays an important role in petroleum operations including drilling, completion

More information

Exploration, Drilling & Production

Exploration, Drilling & Production Nontechnical Guide to PETMOLEUM Geology, Exploration, Drilling & Production Third Edition Norman J. Hyne, Ph.D. Contents Preface *i Introduction 1 The Nature of Gas and Oil 1 Petroleum 1 The Chemistry

More information

Recommendations for Injection and Storage Monitoring

Recommendations for Injection and Storage Monitoring Energy and Environmental Systems Group Institute for Sustainable Energy, Environment and Economy (ISEEE) Recommendations for Injection and Storage Monitoring WABAMUN AREA CO 2 SEQUESTRATION PROJECT (WASP)

More information

Implementing and Monitoring a Geomechanical Model for Wellbore Stability in an Area of High Geological Complexity

Implementing and Monitoring a Geomechanical Model for Wellbore Stability in an Area of High Geological Complexity AADE-10-DF-HO-15 Implementing and Monitoring a Geomechanical Model for Wellbore Stability in an Area of High Geological Complexity J. G. Vargas, Halliburton; J. Mateus, Halliburton; A. Jaramillo, Halliburton;

More information

MicroScope. Resistivity- and imagingwhile-drilling

MicroScope. Resistivity- and imagingwhile-drilling MicroScope Resistivity- and imagingwhile-drilling service MicroScope Magnify your reservoir Multidepth laterolog resistivity Multidepth borehole images Mud resistivity Azimuthal gamma ray Bit resistivity

More information

Wellsite Consulting Services Diversified Well Logging LLC. All Rights Reserved.

Wellsite Consulting Services Diversified Well Logging LLC. All Rights Reserved. Wellsite Consulting Services We are CUSTOMER FOCUSED: We seek to exceed customer expectations by providing solutions that improve their drilling, completions, and production economics OUR CORE VALUES DEFINE

More information

Horizontal well Development strategy

Horizontal well Development strategy Horizontal well Development strategy Pakawas Mangkang Team Member Yoseph Partono Stephan Otero Duangdao Chutanukarn Warin Lobtong Suarporn Ketpreechasawat B8/32 Asset, Thailand Chiangmai, 11 th Nov-13

More information

Technology. configured through the instructor application.

Technology. configured through the instructor application. dewjournal.com Fig.9 Hardware layout alternative 3 (Drillers cabin mock-up) projectors to view 3D or 2D data visualization of the processes in the well bore. The hardware configuration can be changed to

More information

Reservoir Rock Properties COPYRIGHT. Sources and Seals Porosity and Permeability. This section will cover the following learning objectives:

Reservoir Rock Properties COPYRIGHT. Sources and Seals Porosity and Permeability. This section will cover the following learning objectives: Learning Objectives Reservoir Rock Properties Core Sources and Seals Porosity and Permeability This section will cover the following learning objectives: Explain why petroleum fluids are found in underground

More information

short term reservoir behavior

short term reservoir behavior Available online at www.sciencedirect.com Energy Energy 00 (2010) 000 000 www.elsevier.com/locate/procedia www.elsevier.com/locate/xxx GHGT-10 In Salah CO 2 injection modeling: a preliminary approach to

More information

Surface and Wellbore Positioning Errors and the Impact on Subsurface Error Models and Reservoir Estimates

Surface and Wellbore Positioning Errors and the Impact on Subsurface Error Models and Reservoir Estimates Surface and Wellbore Positioning Errors and the Impact on Subsurface Error Models and Reservoir Estimates Ed Stockhausen 1 43 rd General Meeting March 4 th, 2016 Speaker Information Ed Stockhausen Horizontal

More information

A Field Case Example of Wellbore Strengthening Design and Verification Process

A Field Case Example of Wellbore Strengthening Design and Verification Process AADE-11-NTCE-26 A Field Case Example of Wellbore Strengthening Design and Verification Process Mario Bouguetta, Quanxin Guo, and J.D. Moffitt, M-I SWACO Copyright 2011, AADE This paper was prepared for

More information

Multi-skill software for Planning, Following-Up and Post Analysis of wells.

Multi-skill software for Planning, Following-Up and Post Analysis of wells. Multi-skill software for Planning, Following-Up and Post Analysis of wells. Calculation and presentation of the Well Plan Recalculate and update the prognosis during drilling including geology information.

More information

Abstract. 1. Introduction. Geophysics Engineer-Schlumberger 2. M.Sc. Petroleum-PEMEX 3,4 Geologists-PEMEX

Abstract. 1. Introduction. Geophysics Engineer-Schlumberger 2. M.Sc. Petroleum-PEMEX 3,4 Geologists-PEMEX IBP3018 MINIMIZING DRILLING RISKS FOR EXPLORATION WELL IN DEEP WATER USING SEISMIC WHILE DRILLING TECHNOLOGY Sanchez Adrian 1, Mora Alfonso 2 Aguilera Leonardo 3, Gaitan Rito 4 Copyright 2010, Brazilian

More information

SKM DRILLING ENGINEERING. Chapter 4 - Drilling Problems

SKM DRILLING ENGINEERING. Chapter 4 - Drilling Problems SKM 3413 - DRILLING ENGINEERING Chapter 4 - Drilling Problems Assoc. Prof. Abdul Razak Ismail Petroleum Engineering Dept. Faculty of Petroleum & Renewable Energy Eng. Universiti Teknologi Malaysia 2 Contents

More information

An Overview of the Tapia Canyon Field Static Geocellular Model and Simulation Study

An Overview of the Tapia Canyon Field Static Geocellular Model and Simulation Study An Overview of the Tapia Canyon Field Static Geocellular Model and Simulation Study Prepared for Sefton Resources Inc. Jennifer Dunn, Chief Geologist Petrel Robertson Consulting Ltd. Outline Background

More information

Drilling Engineering Design and Application of Well Fengshen-x601

Drilling Engineering Design and Application of Well Fengshen-x601 Advances in Petroleum Exploration and Development Vol. 8, No. 1, 2014, pp. 85-89 DOI:10.3968/5609 ISSN 1925-542X [Print] ISSN 1925-5438 [Online] www.cscanada.net www.cscanada.org Drilling Engineering Design

More information

Petrophysical Data Acquisition Basics. Coring Operations Basics

Petrophysical Data Acquisition Basics. Coring Operations Basics Petrophysical Data Acquisition Basics Coring Operations Basics Learning Objectives By the end of this lesson, you will be able to: Understand why cores are justified and who needs core data Identify which

More information

Title: Application and use of near-wellbore mechanical rock property information to model stimulation and completion operations

Title: Application and use of near-wellbore mechanical rock property information to model stimulation and completion operations SPE OKC Oil and Gas Symposium March 27-31, 2017 Best of OKC Session Chairperson: Matthew Mower, Chaparral Energy Title: Application and use of near-wellbore mechanical rock property information to model

More information

Introduction to Formation Evaluation Abiodun Matthew Amao

Introduction to Formation Evaluation Abiodun Matthew Amao Introduction to Formation Evaluation By Abiodun Matthew Amao Monday, September 09, 2013 Well Logging PGE 492 1 Lecture Outline What is formation evaluation? Why do we evaluate formation? What do we evaluate?

More information

Geohazards have a direct impact on the drilling and

Geohazards have a direct impact on the drilling and SPECIAL Geohazards SECTION: G e o h a z a r d s A new, fully integrated method for seismic geohazard prediction ahead of the bit while drilling CENGIZ ESMERSOY, ARTURO RAMIREZ, SHARON TEEBENNY, YANGJUN

More information

THE USE OF GIS IN GEOTHERMAL RESOURCE MANAGEMENT: A CASE STUDY OF OLKARIA GEOTHERMAL PROJECT

THE USE OF GIS IN GEOTHERMAL RESOURCE MANAGEMENT: A CASE STUDY OF OLKARIA GEOTHERMAL PROJECT Presented at SDG Short Course II on Exploration and Development of Geothermal Resources, organized by UNU-GTP, GDC and KenGen, at Lake Bogoria and Lake Naivasha, Kenya, Nov. 9-29, 2017. Kenya Electricity

More information

Sand Control Rock Failure

Sand Control Rock Failure Sand Control Rock Failure Why? A bit of Mechanics on rock failure How? Some choices that depend on the rock What is moving? Sand grains? Fines? 3/14/2009 1 Young s Modulus, E Young s Modulus is a material

More information

Geologic and Reservoir Characterization and Modeling

Geologic and Reservoir Characterization and Modeling Geologic and Reservoir Characterization and Modeling Scott M. Frailey and James Damico Illinois State Geological Survey Midwest Geologic Sequestration Science Conference November 8 th, 2011 Acknowledgements

More information

Rotary Steerable System Technology Case Studies in the Canadian Foothills: A Challenging Drilling Environment

Rotary Steerable System Technology Case Studies in the Canadian Foothills: A Challenging Drilling Environment AADE-07-NTCE-71 Rotary Steerable System Technology Case Studies in the Canadian Foothills: A Challenging Drilling Environment Essam Adly, Schlumberger Copyright 2007, AADE This paper was prepared for presentation

More information

Relinquishment Report for Licence Number P1356, Block 48/8c March 2008

Relinquishment Report for Licence Number P1356, Block 48/8c March 2008 Relinquishment Report for Licence Number P1356, Block 48/8c March 2008 Table of Contents 1.0 Header...3 2.0 Synopsis...3 3.0 Exploration Activities...4 4.0 Prospectivity Analysis...11 5.0 Conclusions...12

More information

State of the Art in Coalbed Methane Drilling Fluids SPE Len V. Baltoiu, P.Eng. Brent K. Warren, Ph.D. Thanos Natras, P.Geol.

State of the Art in Coalbed Methane Drilling Fluids SPE Len V. Baltoiu, P.Eng. Brent K. Warren, Ph.D. Thanos Natras, P.Geol. State of the Art in Coalbed Methane Drilling Fluids SPE 101231 Len V. Baltoiu, P.Eng. Brent K. Warren, Ph.D. Thanos Natras, P.Geol. 1 Key Points Introduction Geology & Rock Mechanics Drilling Recommendations

More information

ECS Elemental Capture Spectroscopy Sonde. Fast, accurate lithology evaluation

ECS Elemental Capture Spectroscopy Sonde. Fast, accurate lithology evaluation ECS Elemental Capture Spectroscopy Sonde Fast, accurate lithology evaluation Applications n Identify carbonate, gypsum, and anhydrite; quartz, feldspar, and mica; pyrite, siderite, coal, and salt fractions

More information

Critical Borehole Orientations Rock Mechanics Aspects

Critical Borehole Orientations Rock Mechanics Aspects Critical Borehole Orientations Rock Mechanics Aspects By R. BRAUN* Abstract This article discusses rock mechanics aspects of the relationship between borehole stability and borehole orientation. Two kinds

More information

Germany`s Deepest Hydro-Geothermal Doublet, Drilling Challenges and Conclusions for the Design of Future Wells

Germany`s Deepest Hydro-Geothermal Doublet, Drilling Challenges and Conclusions for the Design of Future Wells GRC Transactions, Vol. 42, 2018 Germany`s Deepest Hydro-Geothermal Doublet, Drilling Challenges and Conclusions for the Design of Future Wells Daniel Lackner, David Lentsch & Klaus Dorsch ERDWERK GmbH

More information

Identified a possible new offset location where the customer is currently exploring drill options.

Identified a possible new offset location where the customer is currently exploring drill options. GroundMetrics was hired to conduct a Full-Field Resistivity Survey for an oil and gas producer that needed to make crucial decisions to drive profitability at the location. The results saved them hundreds

More information

The Evolution of Drilling Techniques at the Camden Gas Project. Chris Holmes and Jon Black AGL 27 th June 2007

The Evolution of Drilling Techniques at the Camden Gas Project. Chris Holmes and Jon Black AGL 27 th June 2007 The Evolution of Drilling Techniques at the Camden Gas Project Chris Holmes and Jon Black AGL 27 th June 2007 1 Camden Gas Project Status AGL acquired operatorship from Sydney Gas February 2006 106 production

More information

Key Stage 3 - Volcano Fracking

Key Stage 3 - Volcano Fracking After the meeting Come out of your role. Write your own summary of the dilemmas facing the council, and recommend whether or not they should allow fracking to take place. Pupil worksheet is short for hydraulic

More information

Syn-drill Seismic Imaging through Seismic Guided Drilling A Case history from East coast India deep water example

Syn-drill Seismic Imaging through Seismic Guided Drilling A Case history from East coast India deep water example 10 th Biennial International Conference & Exposition P431 Syn-drill Seismic Imaging through Seismic Guided Drilling A Case history from East coast India deep water example C.Visweswara Rao*, S.Chandrashekar

More information

RWE Dea UK SNS Limited (50%, operator) Dana Petroleum (E&P) Limited (50%)

RWE Dea UK SNS Limited (50%, operator) Dana Petroleum (E&P) Limited (50%) 1. Licence Information Licence Number P1726 Licence Round 25 th (2008) Licence Type Traditional Blocks 43/17a & 43/18a Licensees Work Programme RWE Dea UK SNS Limited (50%, operator) Dana Petroleum (E&P)

More information

Optimum Mud Overbalance and ROP Limits for Managing Wellbore Stability in Horizontal Wells in a Carbonate Gas Reservoir

Optimum Mud Overbalance and ROP Limits for Managing Wellbore Stability in Horizontal Wells in a Carbonate Gas Reservoir Optimum Mud Overbalance and ROP Limits for Managing Wellbore Stability in Horizontal Wells in a Carbonate Gas Reservoir Authors: Khaqan Khan and Dr. Hamoud A. Al-Anazi ABSTRACT Saudi Aramco has been drilling

More information

Introduction to Oil and Gas Production

Introduction to Oil and Gas Production Introduction to Oil and Gas Production Steven Marzuola ATA Energy Conference May 4-6, 2007 Houston Texas Introduction Dope, Joints, Tripping Strippers Casing, Tubing, Liner API - American Petroleum Institute

More information

Helping people understand what drilling data is telling them. Frode Sørmo, Chief Technology Officer

Helping people understand what drilling data is telling them. Frode Sørmo, Chief Technology Officer TM Helping people understand what drilling data is telling them. Frode Sørmo, Chief Technology Officer Artificial Intelligence 2 Artificial Intelligence 3 3 Artificial Intelligence 4 Artificial Intelligence

More information

Module 1 : Site Exploration and Geotechnical Investigation

Module 1 : Site Exploration and Geotechnical Investigation Objectives In this section you will learn the following Displacement borings Wash boring Auger boring Rotary drilling Percussion drilling Continuous sampling Boring methods of exploration The boring methods

More information

Current challenges at CO 2 Sites

Current challenges at CO 2 Sites Current challenges at CO 2 Sites Ola Eiken et al., Statoil R&D Force seminar on injection safety 4 th December 2013 Offshore Sleipner Onshore In Salah Sub-sea Snøhvit 1 - Classification: External 2010-09-23

More information

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals

More information

Comprehensive Wellbore Stability Analysis Utilizing Quantitative Risk Assessment

Comprehensive Wellbore Stability Analysis Utilizing Quantitative Risk Assessment Comprehensive Wellbore Stability Analysis Utilizing Quantitative Risk Assessment Daniel Moos 1 Pavel Peska 1 Thomas Finkbeiner 1 Mark Zoback 2 1 GeoMechanics International, Palo Alto, CA 94303 2 Stanford

More information

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION

SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION SPE DISTINGUISHED LECTURER SERIES is funded principally through a grant of the SPE FOUNDATION The Society gratefully acknowledges those companies that support the program by allowing their professionals

More information

Relinquishment Report

Relinquishment Report Relinquishment Report Licence P.089 Block 22/15a 2 nd Round Traditional Licence Award (Operator): 100.0% Disclaimer No representation or warranty, express or implied, is or will be made in relation to

More information

Rocsol D-Series Technology

Rocsol D-Series Technology Rocsol D-Series Technology D-ROCK October 25, 2017 Rocsol Technologies Inc. Challenges of Horizontal Well Logging Conventional logging and rock mechanical testing are expensive (logging cost and rig time)

More information

Hot Creek Valley Oil Field

Hot Creek Valley Oil Field Hot Creek Valley Oil Field Discovery Well Eblana - 1 MAJOR OIL INTERNATIONAL LLC Brief on well sidetracking down to 13,000 ft Prepared by Soran Talabani and Karim Akrawi Field Location Eblana-1 (well status)

More information

Guideline REGULATORY REQUIREMENTS FOR FINAL WELL REPORTS ONSHORE TO OFFSHORE WELLS

Guideline REGULATORY REQUIREMENTS FOR FINAL WELL REPORTS ONSHORE TO OFFSHORE WELLS Guideline REGULATORY REQUIREMENTS FOR FINAL WELL REPORTS ONSHORE TO OFFSHORE WELLS 1. Introduction The requirement to prepare and submit a Final Well Report is specified by subsection 201(1) of the Newfoundland

More information

Stochastic Modeling & Petrophysical Analysis of Unconventional Shales: Spraberry-Wolfcamp Example

Stochastic Modeling & Petrophysical Analysis of Unconventional Shales: Spraberry-Wolfcamp Example Stochastic Modeling & Petrophysical Analysis of Unconventional Shales: Spraberry-Wolfcamp Example Fred Jenson and Howard Rael, Fugro-Jason Introduction Recent advances in fracture stimulation techniques

More information

PERFORMANCE EVALUATION OF DEEPENED WELLS 420DA AND 517DA IN THE LEYTE GEOTHERMAL PRODUCTION FIELD, PHILIPPINES

PERFORMANCE EVALUATION OF DEEPENED WELLS 420DA AND 517DA IN THE LEYTE GEOTHERMAL PRODUCTION FIELD, PHILIPPINES PROCEEDINGS, Thirty-Eighth Workshop on Geothermal Reservoir Engineering Stanford University, Stanford, California, February 11-13, 213 SGP-TR-198 PERFORMANCE EVALUATION OF DEEPENED WELLS 42DA AND 517DA

More information

Torque and drag modelling for Redhill South-1 in the Northern Perth Basin, Australia

Torque and drag modelling for Redhill South-1 in the Northern Perth Basin, Australia Petroleum and Mineral Resources 97 Torque and drag modelling for Redhill South-1 in the Northern Perth Basin, Australia S. Smith & V. Rasouli Department of Petroleum Engineering, Curtin University, Australia

More information

GEOSTEERING SERVICES. Geosteering Technologies develops the software for geosteering in real-time and provides technical support in this areas.

GEOSTEERING SERVICES. Geosteering Technologies develops the software for geosteering in real-time and provides technical support in this areas. Компания «Геонавигационные Технологии» занимается производством программного обеспечения для сопровождения наклоннонаправленного бурения скважин, а также оказывает консультационные услуги в данной области.

More information

Carbonates vs Clastics How the Differences Impact our SAGD Assessments. Caralyn Bennett, P. Eng. July 6, 2011

Carbonates vs Clastics How the Differences Impact our SAGD Assessments. Caralyn Bennett, P. Eng. July 6, 2011 Carbonates vs Clastics How the Differences Impact our SAGD Assessments Caralyn Bennett, P. Eng. July 6, 2011 Source: Alberta Geological Survey Formations Prospective for Oil Sands Carbonates Clastics

More information

Source Sink Pipeline

Source Sink Pipeline An Overview of Carbon Storage presented by Robert J. Finley Advanced Energy Technology Initiative Illinois State Geological Survey University of Illinois USA IEA Summer School Longyearbyen, Norway August,

More information

Downloaded 09/16/16 to Redistribution subject to SEG license or copyright; see Terms of Use at

Downloaded 09/16/16 to Redistribution subject to SEG license or copyright; see Terms of Use at Data Using a Facies Based Bayesian Seismic Inversion, Forties Field, UKCS Kester Waters* (Ikon Science Ltd), Ana Somoza (Ikon Science Ltd), Grant Byerley (Apache Corp), Phil Rose (Apache UK) Summary The

More information

Shale Gas; Wellbore Positioning Challenges

Shale Gas; Wellbore Positioning Challenges Shale Gas; Wellbore Positioning Challenges Pete Clark, Directional Drilling Advisor ISCWSA, Copenhagen, 3/4/11 Shale Gas; Wellbore Positioning Challenges Why is it important to us? Emerging trend in drilling

More information

6. THE BOREHOLE ENVIRONMENT. 6.1 Introduction. 6.2 Overburden Pressures

6. THE BOREHOLE ENVIRONMENT. 6.1 Introduction. 6.2 Overburden Pressures 6. THE BOREHOLE ENVIRONMENT 6.1 Introduction Wireline logging has a single clearly defined purpose: to give accurate and representative data on the physical properties of the rock formations and fluids

More information

Relinquishment Report for Licence P.1265, Block 12/28

Relinquishment Report for Licence P.1265, Block 12/28 Relinquishment Report for Licence P.1265, Block 12/28 1. Licence Information Licence Number: P.1265 Licence Round: 23 rd Round Awarded 22 December 2005 Licence Type: Traditional Block Number(s): 12/28

More information

Exploring and Drilling for Oil and Gas. Prepared by Tom Sheeran

Exploring and Drilling for Oil and Gas. Prepared by Tom Sheeran Exploring and Drilling for Oil and Gas What are Oil and Gas? Oil and Gas are substances found within the earth s crust. They are thought to come from decomposed plant and animal matter. Scientists believe

More information

DRILLING REPORT NO.1 FOR DUNNART-2 IN EP437, PERTH BASIN, WESTERN AUSTRALIA FOR THE PERIOD 0600 HOURS 13 JULY 2014 TO 0600 HOURS 21 JULY 2014

DRILLING REPORT NO.1 FOR DUNNART-2 IN EP437, PERTH BASIN, WESTERN AUSTRALIA FOR THE PERIOD 0600 HOURS 13 JULY 2014 TO 0600 HOURS 21 JULY 2014 21 July 2014 The Manager The Australian Securities Exchange The Announcements Officer Level 4/20 Bridge Street SYDNEY NSW 2000 Dear Sir DRILLING REPORT NO.1 FOR DUNNART-2 IN EP437, PERTH BASIN, WESTERN

More information

P306 Seismic Velocity Anisotropy in the Illizi Basin of Eastern Algeria

P306 Seismic Velocity Anisotropy in the Illizi Basin of Eastern Algeria P306 Seismic Velocity Anisotropy in the Illizi Basin of Eastern Algeria M. Wallace* (GX Technology), J. Maher (GX Technology), S. Schapper (GX Technology), B. Taylor (BP) & S.R. Tod (BP) SUMMARY The Tiguentourine

More information

Revitalizing Mature Fields

Revitalizing Mature Fields JOURNAL OF PETROLEUM TECHNOLOGY www.jptonline.org OCTOBER 2012 O C TO B E R 2 0 1 2 VO LU M E 6 4, N U M B E R 1 0 Revitalizing Mature Fields Field Development Projects Tight Reservoirs Knowledge Management

More information

MULTIPLE CHOICE QUESTIONS OIL, GAS, AND PETROCHEMICALS. The Energy and Resources Institute

MULTIPLE CHOICE QUESTIONS OIL, GAS, AND PETROCHEMICALS. The Energy and Resources Institute MULTIPLE CHOICE QUESTIONS ON OIL, GAS, AND PETROCHEMICALS The Energy and Resources Institute Preface Petroleum as everyone knows consists of hydrocarbons of various molecular weights and other organic

More information