Chapter 5 : Design calculations

Size: px
Start display at page:

Download "Chapter 5 : Design calculations"

Transcription

1 Chapter 5 : Design calculations 5. Purpose of design calculations For design calculations, it is important to assess the maximum flow, maximum water level and maximum velocity which occur in every node or pipe with a certain return period. Therefore, a detailed model including all (relevant) pipes is necessary. However, the simulation of long time series using detailed models is extremely time consuming. Even if the pipe network is simplified to only the relevant pipes, a maximum reduction in calculation time by maybe a factor of 2 can be achieved. The simplification of the rainfall input is the remaining alternative. The simplification of the long rainfall series to single storm events with a certain return period leads to (relatively) fast calculations. In that case it is generally assumed that the return period of an effect (water depth, flow, etc...) is equal to the return period of the storm which causes this effect. This assumption of linearity is most often acceptable for design calculations because only peak discharges and maximum levels are important. The possible non-linear behaviour of sewer systems will not have a large influence for high return periods and short storm durations. For these extreme and short events the hydraulic performance will not be affected very much by the antecedent rainfall conditions and the variability of the rainfall. However, if the antecedent conditions become more important and the storm durations increase, the temporal variability should be incorporated. Furthermore, the spatial variation of the rainfall may also be important. Finally, it is important to note that design calculations do not only involve simulation software and rainfall input. Other aspects have to be taken into account such as boundary conditions, design criteria, accuracy of input data and the interpretation by the design engineer. In this chapter the different aspects involved in design calculations will be investigated with great emphasis on the influence of the rainfall and the correlations with the design criteria. Chapter 5 : Design calculations 5.

2 5.2 Design calculations using single storm events 5.2. Rainfall input used in Flanders before 996 Before 987, a rainfall intensity of 60 l/s/ha (for flat areas) or 90 l/s/ha (for steep areas) for a duration of 5 minutes was used for design calculations [De Backer, 978]. In this guideline of De Backer it is stated that the return period in this case is year and that for problem areas a return period of 2 years should be used. As compared with the new IDF-relationships, a rainfall intensity of 60 l/s/ha over 5 minutes has a return period of about 0.3 years and a rainfall intensity of 90 l/s/ha over 5 minutes has a return period of about 0.8 years. For longer storm durations (i.e. longer concentration times) the use of this rainfall volume will lead to even lower return periods. In 987, new guidelines were written, in which the design return period was fixed at 2 years (5 years for problem areas) and the use of a critical storm duration was generalised [Berlamont, 987]. The rainfall intensities in these guidelines were based on the IDF-relationships by Demarée [985]. As compared with the new IDF-relationships (see paragraph 2..5) the rainfall intensities in these guidelines still lead to a small overestimation of the return period (underestimation of the flow). The resulting return periods are shown in figure 5.. For every storm duration and the corresponding rainfall intensity, the return period following the new IDF-relationships is presented in this figure. In these guidelines only rainfall intensities up to a storm duration of 60 minutes were given. For sewer systems with larger critical storm durations (i.e. concentration times) the use of a maximum storm duration of 60 minutes will lead to a larger overestimation of the return period. This is shown by the small dashed lines in figure 5.. These small dashed lines are obtained using the rainfall volume over the largest used storm duration of 60 minutes and spreading them out over the considered storm duration. In 992, with the use of Sphyda version 2.02, English storms were introduced (rainfall generator version.42 [WS, 992]) (see paragraph.4.3). When this rainfall was compared with the IDF-relationships of Demarée [985], a significant disagreement was found (however the disagreement with the new IDF-relationships is limited for high return periods). Therefore, these English synthetic storms were slightly calibrated to the IDF-relationships of Demarée and added to Spida version 2. (rainfall generator version.44, [WS, 994]). The use of different storm types with different origin has an impact on the design return period. Again, the return period of previously used rainfall can be determined based on the new IDF-relationships. In figure 5.2, a comparison of the return period is made for the different design storms, which have been in use in Flanders since The influence of rainfall and model simplification on combined sewer system design

3 7 return period (years) guidelines 987, T = 5 years composite storm, T = 5 years 3 2 composite storm, T = 2 years guidelines 987, T = 2 years storm duration (min) Figure 5. : Return periods for the rainfall input corresponding to the guidelines of 987 (storm durations up to 60 minutes) as compared with the composite storms for 2 and 5 years (the effect for larger concentration times (i.e. storm durations longer than 60 minutes) on the return period is illustrated by the small dashed lines) return period T (year) Sphyda 2.02 T = 5 years Spida 2. T = 5 years composite storm T = 5 years Sphyda 2.02 T = 2 years Spida 2. T = 2 years composite storm T = 2 years storm duration (min) Figure 5.2 : Return periods for the different rainfall input used for combined sewer system design in Flanders since 992 as compared with the composite storms for 2 and 5 years. Chapter 5 : Design calculations 5.3

4 5.2.2 Combination of previously used software and rainfall Since each new type of design storm was introduced together with a change in simulation software, the global effect on the design must be studied. It was found that the return periods of previous designs were overestimated as compared with the current technology (i.e. the sewer pipes were underdesigned). For the Flemish design practice, it can roughly be concluded that a design which was made between 992 and 994 (with the idea to design it) for a return period of 5 years, only has a return period of 3 years. The main cause of this is the underestimation of the piezometric level by the software when the pipes get pressurised as described in paragraph.2.. These results were obtained by comparing the maximum water levels and peak flows in all nodes and pipes of two complex sewer systems for which the different combinations of software and rainfall input were applied [Vaes & Berlamont, 998a]. For a design between 994 and 996 this return period is about 4 years (for an original return period of 5 years), while the main cause in this period is the rainfall input, as described in paragraph.4.3. and illustrated in figure 5.2. This overestimation of the return period appears to be important, but it is not significantly larger than the uncertainty on the design. In figures 5.3 and 5.4 the influence of the water input into the sewer system (caused by rainfall, impervious area or runoff coefficient) on the return period is shown. In figure 5.3 the effect of an underestimation of the rainfall input into the sewer system with 0 % is shown. The relationship between the underestimation of the rainfall intensity and the return period is based on the new IDF-relationships which are described in paragraph return period T (year) T = 0 years T = 5 years T = 2 years storm duration (min) Figure 5.3 : Effect on the return period of an underestimation with 0 % of the water input (impervious area, rainfall intensity, losses, ) into the combined sewer system(for the composite storms with a return period of 2, 5 and 0 years). 5.4 The influence of rainfall and model simplification on combined sewer system design

5 An underestimation of the water input of 0 % already has a significant effect on the design. Moreover, an increase in water input into the sewer system often results in a more than linear increase of the piezometric levels, certainly when pressurised flow occurs in many pipes (head losses increase quadratically with the discharge in pressurised pipes). The piezometric level rises especially in these nodes where the level is critical already. This also means that in the previous designs, several critical nodes may not have been discovered. This uncertainty, which is inherent to the sewer system data (as well on rainfall input as on the parameters of the runoff model, e.g. impervious area and runoff coefficient), can lead to an extra overestimation of the return period in specific pipes. In figure 5.4, the effect of an overestimation of the water input into the sewer system of 0 % on the return period is shown return period T (year) T = 5 years T = 2 years storm duration (min) Figure 5.4 : Effect on the return period of an overestimation with 0 % of the water input (impervious area, rainfall intensity, losses, ) into the combined sewer system (for the composite storms with a return period of 2 and 5 years) Design calculations using composite storms The composite storms, as they have been derived in this work (see paragraph 2.3), include the mean rainfall characteristics, but neglect the intrinsic temporal rainfall variability. In order to assess the ability of these composite storms to predict the real discharges and piezometric levels in a sewer system, a comparison has been made between (full hydrodynamic) simulations with the composite storms on the one hand and long rainfall series on the other hand. To limit the calculation time this has only been done for a few small sewer systems. The rainfall input used for the continuous Chapter 5 : Design calculations 5.5

6 simulations is the rainfall series (of Uccle) of 27 years, which has also been used for the development of the composite storms (see paragraph 2.3). In figures 5.5 till 5.7, the simulation results are shown, which have been obtained for different pipes in three small sewer systems (i.e. 50 to 200 nodes). The lines show the relationship between flow and return period obtained with the composite storms, while the markers show these relationships for the continuous simulations. The relationships obtained with the composite storms show a very smooth line, because these composite storms are based on IDF-relationships which have been obtained by an extreme value analysis (see paragraph 2..5). The results obtained with the continuous simulations are the simulation results without any extreme value estimation or regression. For the figures 5.5 till 5.7 no independency criterion has been used to distinguish two effects (i.e. flow) above a certain threshold, which occur shortly after each other. However, the analysis for the IDF-relationships showed that the influence of dependent effects is very small for high return period. This has been confirmed by analysing the results of the continuous simulations using an independency criterion of a minimum of 2 hours between the events, which showed only small differences for the lower flows. 00 return period [year] 0 0. pipe ; continuous simulation pipe 2; continuous simulation pipe 3; continuous simulation corresponding simulation with composite storms flow [m 3 /s] Figure 5.5 : Comparison between the results of continuous simulations with a rainfall series of 27 years (markers) and the results of simulations with composite storms (lines) for three downstream pipes in a small sewer system with a gravitary outflow. 5.6 The influence of rainfall and model simplification on combined sewer system design

7 00 return period [year] 0 pipe ; continuous simulation 0. pipe 2; continuous simulation corresponding simulation with composite storms flow [m 3 /s] Figure 5.6 : Comparison between the results of continuous simulations with a rainfall series of 27 years (markers) and the results of simulations with composite storms (lines) for two downstream pipes in a small sewer system with a single pump at the outflow. 00 return period (year) 0 0. continuous simulation simulation with composite storms flow (m 3 /s) Figure 5.7 : Comparison between the results of continuous simulations with a rainfall series of 27 years (marker) and the results of simulations with composite storms (line) for a downstream pipe in a small sewer system with a single pump at the outflow. Chapter 5 : Design calculations 5.7

8 The results in figure 5.5 are those for a small sewer system with a gravitary outflow, which behaves linearly. The results obtained with the composite storms are very close to those obtained with the continuous simulations. Figures 5.6 and 5.7 show the results for two small sewer systems with a single pump at the downstream end. These sewer systems have a very non-linear relationship between storage in the sewer system and outflow. It is clear from figures 5.6 and 5.7 that the results obtained with the composite storms are not as close in agreement as those obtained with the continuous simulation as compared with the results in figure 5.5. From the large fluctuation on the results obtained with the continuous simulations, it is clear that the large uncertainty on the rainfall input also leads to a large uncertainty on the results, certainly for high return periods. Using the composite storms, this uncertainty will partially be covered up. For the three tested (small) combined sewer systems the results obtained with the composite storms were always on the safe side, i.e. the flow is slightly overestimated. However it is not clear from the limited number of test cases if this is a coincidence or a systematic difference The influence of the storm duration Increasing the storm duration (for design calculations in Flanders) from 20 minutes (before 996 [Aquafin, 994a]) to 360 minutes (using the composite storms) has only an effect on the piezometric levels at the downstream end of a large system. The piezometric level will not rise in the upstream critical nodes, but at the downstream end of the system the piezometric level can create a more critical situation in some nodes or some new critical nodes may be observed. Before 996, for each storm duration a specific storm had to be used. This led to a practice where only one critical storm duration was taken into account in order to limit the results processing and to cope with the problem of simultaneous visualisation of the results from different simulations. Mostly the critical storm duration for the most downstream part was therefore used, but sometimes even a mean critical storm duration was used. However, the critical storm duration is different for each part of the sewer system. Upstream parts can be associated with small critical storm durations, while downstream parts can be associated with longer critical storm durations. When using a different storm for every storm duration, the maximum water levels and peak flows in every node or pipe must be taken as the maximum that occurs in one of the simulations for the whole range of storm durations. This problem has been solved since the composite storms were introduced in 996 [VMM, 996]. 5.8 The influence of rainfall and model simplification on combined sewer system design

9 5.3 Including temporal rainfall variability 5.3. Need for temporal rainfall variability The comparison between the simulation results for continuous simulations and simulations with composite storms indicates that significant differences may be found when the intrinsic variability of the rainfall is neglected. The differences will be small for sewer systems which behave linearly, because the immediate rainfall determines the peak flow and maximum water levels. When the systems start to behave more as capacitive systems, i.e. where the storage becomes an important parameter, the differences will be larger. A capacitive system has a memory which remembers the antecedent rainfall. Often sewer systems have an emptying time, which tends towards 2 hours. If a severe storm occurs within a short period after an earlier storm, the antecedent rainfall may still occupy a large amount of the storage capacity in the combined sewer system. The larger the influence of the memory is, the larger the intrinsic variability of the rainfall will influence the simulation results. For example, for a sewer system in a flat region with one pump at the downstream end, the throughflow is almost independent of the storage volume. The storage volume in the system is therefore mainly dependent on the inflow. More and more capacitive sewer systems have been built recently and will still be built in future. The best combined sewer system, in order to obtain an optimal load into the treatment plant, has a throughflow which is as small and as constant as possible. Therefore, large storage volumes are necessary to retain the rainfall and to attenuate the flow. These storage volumes can be built in the sewer system (on-line storage) or at the combined sewer overflow (off-line storage). However, more and more attention is going to source control, certainly in recent years [VMM, 996, 999]. This means that storage is provided in rain water tanks, infiltration trenches, etc... For these source control implementations the influencing antecedent rainfall period is even larger. This requires larger storage volumes (relative to the contributing area) than for downstream storage [Vaes & Berlamont, 998c, d, e, 999]. This all amplifies the need to take into account the intrinsic variability of the rainfall for specific design calculations Modified single storm events When storage is built in upstream of the combined sewer system, i.e. before the rain water enters into the sewer pipes, the rainfall input can be preprocessed in order to take into account this storage. This can be done as described in paragraph 2.3.5, where the effect of rain water storage tanks has been incorporated in modified (composite) design storms in the program Rewaput. These local source control implementations are easy to model with a simple reservoir model, which can handle Chapter 5 : Design calculations 5.9

10 continuous long time simulations in a very short computation time. This methodology can also be used to incorporate the effect of a non-linear surface runoff model or to simulate the effect of infiltration facilities, even if they are influenced by the ground water table. Currently, for sewer system design a fixed runoff coefficient of 0.8 is used for the impervious area. If (long term) measurements were available, a more realistic runoff model could be calibrated and used, including a more capacitive (depression storage based) runoff model (e.g. [Vaes et al., 998c]). For this runoff model the long term behaviour could then be included in the design calculations by routing long rainfall series through the simple conceptual runoff model and incorporate the effect in the design storms. The same is true for infiltration facilities and runoff from pervious areas. Simple conceptual models can be used to reshape the design storms, so that simple design storms are obtained without neglecting the effect of the rainfall variability on the infiltration facilities. Infiltration and retention facilities often behave non-linearly, because the outflow is often very strictly limited. Continuous long term simulations are thus necessary. The implementation of a simple conceptual model for the upstream retention facilities is simple and the simulation of long time series in this conceptual model does not require long calculation times. One set of parameters for the Rewaput model requires only about 5 seconds of calculation time on a Pentium II 233 MHz computer. If the parameters vary over a specific catchment, the parameter distribution can be discretised and several sets of parameters can be taken into account. In that case the discretisation step, the deviation on the parameters and the number of varying parameters determine the number of calculations which have to be performed. In the model Rewaput, a triangular distribution is implemented to approximate the stochastic character of storage volume and water consumption (i.e. variation over a catchment) [Vaes & Berlamont, 998b]. For each variation within this triangular distribution the effect is multiplied by the weight corresponding to the parameter distribution in order to calculate the global effect. Using two stochastic parameters the calculation time quadratically increases. To reduce the calculation time the discretisation has to be chosen taking into account the deviation on the parameters. Although the storage in rain water tanks and infiltration facilities is not always completely available during severe rainfall, i.e. because the storage is already filled with the antecedent rainfall, this kind of upstream retention facility still can have a large influence on the rainfall runoff to the sewer system. It has been shown that well-designed rain water tanks can even significantly reduce the peak flow in sewer systems, if they are installed on a large scale [Vaes & Berlamont, 998b]. In figure 5.8, an example is shown of what the possible effect of rain water tanks on a design storm can be. In this case (figure 5.8), it is assumed that rain water tanks of 5000 l per 00 m 2 roof area are built for 30 % of the total impervious area and that 00 l per day and per 00 m 2 roof area rain water is consumed. This almost reduces the peak of the composite storm for 5 years to the value of the composite storm for year (figure 5.8). 5.0 The influence of rainfall and model simplification on combined sewer system design

11 rainfall intensity (mm/h) T = 2 year : 52.4 mm/h T = year : 4.9 mm/h design storm T = 5 year tank volume = 5000 l/00m 2 rain water use = 00 l/day/00m 2 30 % connected area modified composite storm original composite storm time (min) Figure 5.8 : Effect of the installation of rain water tanks on a large scale on the composite storm for a return period of 5 years. This example shows the effect if 30 % of the impervious areas is connected to rain water tanks with a volume of 5000 l per 00 m 2 roof area and a rain water use of 00 l per day and per 00 m 2 roof area Design calculations using short selected rainfall series If retention or infiltration facilities are built into the combined sewer system, the approach using modified single storm events (as described in paragraph 5.3.2) is not applicable anymore. In recent years the revaluation of ditches is promoted for rain water runoff in Flanders [VMM, 996, 999]. This means that the transport function at one side and the retention and infiltration function at the other side are combined. To obtain a good evaluation of these types of storm water runoff, the intrinsic rainfall variability must be retained. The same is valid for non-linearly behaving sewer systems, which is often the case when large in-line storage is used and the throughflow is strongly limited. This can also be the case when in-line storage has to be designed in order to prevent flooding from the system. In this case the rainfall variability can only be retained by selecting the specific short rainfall series (SSRS) out of the original long rainfall series as has been described in paragraph 4.2 (based on IDF-relationships). Besides the fact that the appropriate SSRS have to be selected, the reduction of the calculation time is the most important criterion in the judgement on the applicability of the SSRS. The design return period, the maximum storm duration and the necessary antecedent rainfall period have a large Chapter 5 : Design calculations 5.

12 influence on the reduction of the rainfall input. Therefore, these parameters have to be limited. This leads to a certain domain of applicability of these SSRS. As combined sewer system design calculations are always carried out for return periods starting from 2 years (minimum year for storm water systems), it is no problem to limit the return period (i.e. selecting only the events with a return period higher than e.g. year). The number of SSRS must however be large enough to be able to process the results in a statistically acceptable way. Also the maximum storm duration can be limited without hindering the applicability, e.g. to 360 or 720 minutes, because rarely these high concentration times occur. The remaining parameter is the antecedent period, which can increase to a very long period. In the Flemish guidelines it is stated that the maximum emptying time of a combined sewer system should be 2 hours [VMM, 996], but often this can be higher. Certainly for storm water sewers (where there is no strict limit for the emptying time in order to prevent septic reactions) and when more retention capacity is built in into the sewer system, the emptying time can increase to periods longer than 2 hours. However, the current applicability in practice imposes an upper limit for the antecedent period of 2 to 24 hours. The combination of IDF-relationships for the selection of short rainfall series for design applications and the emptying time for the corresponding antecedent period, does not guarantee that the selection is perfect. As explained in paragraph 4.4, the use of a reservoir model for the selection of the antecedent period could take into account larger antecedent periods without increasing significantly the length of the rainfall series or even further reducing (the antecedent periods for) the SSRS and thus the calculation time. A specific reduction of the rainfall input for a sewer system simulation will not lead to a proportional reduction in calculation time, because more iterations are necessary when the flow in the system becomes more complicated. To get an idea about the calculation times, tests were performed on three sewer systems using a set of SSRS for a minimum return period of 2 years, a maximum storm duration and a maximum antecedent period of 2 hours. The results, obtained with Hydroworks version 4.0 [WS, 998a] on a Pentium II 233 MHz computer, are shown in table 5.. It is clear from the results in the table that the complexity and the magnitude of the sewer system have a large influence on the calculation times. However, for normal and small sewer systems the methodology, using SSRS, reaches a stage of practical applicability. In the future, computers and software will become faster, which offers good perspectives for this methodology. However, this methodology will never replace design storms, because of the trial and error nature of design calculations, but will be useful to perform a check simulation following the design stage. As compared with the use of the composite storms, the use of SSRS results in a relative reduction in calculation time with a factor 2 to 3 per day of rainfall input. 5.2 The influence of rainfall and model simplification on combined sewer system design

13 sewer system Table 5. : Calculation times for a set of selected short time series with a total duration of 5 days for three different sewer systems. number of nodes total calculation time calculation time per day rainfall input calculation time per day rainfall input and per 000 nodes complex, different pumping stations including treatment plant simple, single pump hours 8.0 minutes 6.8 minutes hours 3.3 minutes 9.7 minutes 57 8 minutes 0.36 minutes 6.3 minutes A major limitation at this moment for the use of selected short time series (and continuous time series simulations) is the statistical processing of the results. It is not possible to perform a statistical analysis on a long time series of results or on a set of results obtained from simulations using a set of short time series with the (in Flanders) currently used software Hydroworks [WS, 998a]. It is not only necessary to determine the distributions of different hydraulic parameters, but also to perform an extreme value analysis on the results, because of the large variability of the phenomena for high return periods. As discussed in paragraph the system behaviour can change the type of extreme value distribution. This means that the type of extreme value distribution for the effect may be different from the one for the rainfall input. The new possibilities in Infoworks [WS, 998c] make the statistical processing easier. In Infoworks the percentage of exceedance can be determined for a certain threshold or the threshold for a certain percentile can be extracted. However, it is not possible to obtain a full distribution of the results or to apply an extreme value analysis. The second (longer) time step that can be chosen during dry weather flow when the simulations are not critical and no results are required, can boost continuous simulations. However, only instantaneous parameters can be chosen to control the use of this second time step during the insignificant periods. Parameters which describe cumulative effects (e.g. volume) are however often more important to select the significant parts from long time series. Therefore the selection of short time series based on IDF-relationships, as described in paragraph 4.2, is preferred. Chapter 5 : Design calculations 5.3

14 5.4 Spatial rainfall variation 5.4. Areal reduction coefficient In the past, often an areal distribution coefficient has been applied in Flanders for sewer system design in order to incorporate the spatial variation of the rainfall within a storm [Berlamont, 987; VMM, 996]. This areal reduction coefficient was based on the work of Frühling, who measured at Breslau (actually Wroclaw, Poland) that the rainfall intensity at 3 km from the centre of the storm was halved and was negligible at 2 km [Mennes, 90]. Frühling proposed a parabolic spatial distribution of the rainfall within a storm (figure 5.9) : i x i 0 = x (5.) in which i x is the rainfall intensity at a distance x of the centre of the storm, where i 0 is the maximum rainfall intensity. Figure 5.9 : Spatial rainfall distribution proposed by Frühling [Mennes, 90]. If this spatial distribution is integrated over a circular area, an areal reduction coefficient R A is obtained (table 5.2) : ψ A = L (5.2) in which L is the diameter of a circular area (in [m]) over which the rainfall is integrated. Although Frühling based his work on (a limited number of) experiments, the (rather arbitrary) assumption of a parabolic distribution is not in accordance with 5.4 The influence of rainfall and model simplification on combined sewer system design

15 what was recently found in the analysis of the rainfall from the dense pluviometric network of Antwerp [Luyckx & Herftijd, 996; Houbrechts & Truyen, 997; Luyckx et al., 998d; Willems, 998a, 999; Willems & Berlamont, 998a]. From this rainfall data of Antwerp, it could be concluded that the spatial distribution is more likely to be Gaussian and that the mean value for the standard deviation F using this Gaussian distribution is about 2.5 km : ψ A i x i 0 = x 2 exp 2 2 σ Integrated over a circular area, this leads to an areal reduction factor R A of (table 5.2) : (5.3) 8 σ 2 L 2 = exp L 2 8 σ 2 (5.4) Table 5.2 : Areal reduction coefficients R A as a function of the diameter L and the area of the circular region over which the rainfall is integrated. diameter L (m) circular area (ha) R A Frühling R A Gaussian Chapter 5 : Design calculations 5.5

16 When this Gaussian spatial rainfall distribution is compared with the proposed parabolic distribution (figure 5.0), it can be concluded that the influence of the spatial variation of the rainfall on the total rainfall volumes becomes important only starting from larger areas than assumed by Frühling. The results of the integration of the Gaussian distribution are shown in table 5.2. The comparison between the parabolic and the Gaussian variation may lead to the conclusion that for small catchments the rainfall input will be underestimated using the Frühling coefficient, while for large catchments the influence of the spatial variation of the rainfall is even larger. However, there is a large uncertainty on the shape of the storms. Furthermore, it is remarkable that this Gaussian distribution also fits to the experiments of Frühling (figure 5.9). i x /i Frühling Gaussian distance x (km) Figure 5.0 : Spatial variation of the rainfall in a storm using a Gaussian distribution. There is an additional important parameter to estimate, namely the peak intensity. The above discussed implementation of the spatial variability is only valid if the peak intensity is known. Based on point rainfall measurements the peak rainfall intensities are rarely observed. Because spatial distributed rainfall for a long measurement period (several decades) is not available in Flanders, all sewer system design is based on point rainfall measurements. Using an areal reduction factor in this case may lead to a significant underestimation of the rainfall volumes. If point rainfall measurements are taken for a long period, one can assume that a mean sample is obtained of the rainfall at one place. The measured peak intensities are however smaller than the real peak intensities and it is difficult to estimate the difference 5.6 The influence of rainfall and model simplification on combined sewer system design

17 between them. In figure 5. the spatial rainfall distribution is shown in a case where the peak intensity would be underestimated by the rain gauge measurement with 20 %. This figure also shows that in this case an areal reduction factor is not necessary for areas with a diameter smaller than 6 km (or a circular area of about 3000 ha). Taking into account the underestimation of the measured peak rainfall intensities, for small areas even an areal augmentation factor should be used instead. This leads to the conclusion that it is not recommended to use an areal distribution coefficient in sewer system design, unless the probability estimation of the peak rainfall measurements is taken into account i x /i distance x (km) Figure 5. : Spatial rainfall distribution when the peak intensity is underestimated by the rain gauge measurement with 20 % and the real rainfall intensity is thus 20 % higher. Chapter 5 : Design calculations 5.7

18 5.4.2 Dynamic influence of the spatial rainfall variation In the previous paragraph the spatial variation of the rainfall was assumed to be static. However, storms usually move over the catchment, which gives a dynamic character to the spatial variation of the rainfall. For large sewer systems the concentration time can be several hours. In this time a storm can move. This can have different effects depending on the direction of the storm as compared with the main flow direction : S If the main flow direction in the sewer system is the same as the dominant direction of the storms moving over a catchment, the use of an areal reduction coefficient will lead to an underestimation of the flow. In this case the discharges might be even larger than in the case that no reduction coefficient is used at all. S If the main flow direction in the sewer system is the opposite of the dominant direction of the storms moving over a catchment, the use of an areal reduction coefficient may still lead to an overestimation of the flow. S If the main flow direction in the sewer system is perpendicular to the dominant direction of the storms moving over a catchment, the incorporation of a static areal rainfall distribution will on average lead to a good flow prediction. All intermediate possibilities can occur. Tests performed by Luyckx & Herftijd [996] show that this dynamic effect of a storm moving over a catchment can result in a significant increase in flow and water depth. However, this study also showed that the mean result from four perpendicular storm directions (moving over the centre of the catchment) approaches the results of a static storm in the centre of the catchment. This means that there would be no influence of this dynamic storm behaviour if there is no preferential storm direction. However, the rainfall data from the dense pluviometric network of Antwerp show that there is a preferential storm direction, i.e. from south-west to north-east [Willems, 998a, 999; Willems & Berlamont, 998a]. Although this might be the general case, for thunderstorms the storm direction probably is less preferential. Because of the dynamic behaviour of the spatial variation of the rainfall, in theory, it could be preferable to avoid main sewers directed from south-west to north-east. The distribution of the storm directions is however broad and in practice other parameters (e.g. topography, etc...) play a larger role in the determination of the direction of the main sewers. In these cases extra safety could be included in the design using simulations with storms moving over the catchment. This is relatively easy to implement and does not require longer calculation time, although the choice of the storms must be considered carefully in terms of corresponding return period. 5.8 The influence of rainfall and model simplification on combined sewer system design

19 5.5 Other design aspects 5.5. Design safety The current return period for the design of sewer systems in Flanders is 2 years (5 years in problem areas) [VMM, 996]. For this return period the piezometric level must remain 0.5 m below ground level. An extra check simulation for flooding is required with a return period of 5 years (0 years in problem areas). The European guidelines (EN 752 [BIN, 996]) suggest higher return periods. They even state that the pipes may not be pressurised for the design return period. This is practically not feasible in flat regions as in Flanders. Moreover, there is little reason to restrict pressurised flow as long as the pipe capacity is higher than the flow and the pressurised flow is thus only caused by the downstream boundary condition, e.g. the combined sewer overflows. The capacity of a pipe is the maximum discharge that can be transported in a steady state with free outflow. The capacity of a pipe is large enough if the slope of the piezometric line is smaller than or equal to the slope of the pipe. Historically, the design return period has periodically fluctuated (see paragraph 5.2.). In 987, the design return period of 2 years (5 years for problem areas) was prescribed and the use of the critical storm duration was generalised [Berlamont, 987]. But at that time most sewer design was still carried out using the rational method or a variant of it. It is generally known that the rational method overestimates pipe sizes, although the dynamic effects are not taken into account. By only rounding off the diameters, the return period can rise from 2 years to even 5 years [Chow, 98]. The return period for flooding can be even 4 to 5 times higher than the design return period [Jensen and Prisum, 982]. These safety margins were taken into account in the design criteria. When hydrodynamic simulations were generally applied, the criteria were not changed. However, the safety margins on the design decreased considerably; for instance, because the real diameters are used for the calculations. If a sewer system is well designed and the return period for flooding is 5 years, the system will indeed flood on average every 5 years. The use of hydrodynamic simulations itself can also have a negative effect on the design quality. This software is accessible to more people and the stimulus to reflect on the design diminishes. In the end, the design will only comply with the formulated rules as there are : a piezometric level of 0.5 m below ground level for a return period of 2 years and no flooding for a return period of 5 years. This kind of designing 'up to the limit' increases the sensitivity of the system for flooding and is often not the most economical solution. This is illustrated in figure 5.2, were the longitudinal section of a few pipes is shown for a design up to the limit in the upper graph as compared with a normal design in the lower graph. The calculation for a return period of 5 years becomes a design calculation with respect to flooding, which leads to less safe situations, while it should be a check simulation in order to increase the safety. Chapter 5 : Design calculations 5.9

20 A return period of 5 years for flooding does not necessarily means that this water also causes damage (e.g. water on the street versus when it enters the houses). This difference is not made in the Flemish guidelines and design practice. Figure 5.2 : Longitudinal profile of a few pipes to show an example of a design up to the limit (upper graph) as compared with a normal design (lower graph) Boundary conditions System components such as overflows, pumps, discharge control devices, flap valves, etc... have a major influence on the flow through the sewer system. Therefore, they have to be modelled carefully. The relationships between piezometric level (or head) and the discharge must be determined accurately for these components. In practice, often default parameter values are used due to a lack of information. The modelling accuracy for these components often determines the accuracy of the water levels in the whole sewer system. Even more important is the operational uncertainty. Pumps may fail, flap valves may block, etc... The simulation of these failures can lead to a better understanding of the system and an increased safety of the design. The most important boundary conditions are the connections between the sewer systems and the receiving waters : the discharge capacities of pumps and overflows. Often the receiving waters influence the flow in the sewer system : flap valves close, 5.20 The influence of rainfall and model simplification on combined sewer system design

21 overflows submerge, etc... In addition, boundary conditions are often not constant. When the water level in the receiving water changes independently of the flow in the sewer system (e.g. tide rivers), superposition can be applied to determine the mean return period T : T = n n (5.5) i= Ti in which n different return periods T i are considered for the same phenomenon, but using n different boundary conditions (with the same probability). This means that the frequency (inverse of the return period) of a specific phenomenon (discharge or piezometric level) is the mean of the frequencies of the individual scenarios (if each scenario has the same probability; otherwise weight functions equal to the probability have to be used). In figure 5.3 this is illustrated for the piezometric level using two different scenario's for the boundary conditions. This is a quite laborious methodology, because for each scenario the same discharge or piezometric level must be assessed with the accompanying return period (mostly by interpolation). 4 piezometric level h (m) h scenario scenario 2 0 T T return period T (year) Figure 5.3 : Visualisation of the calculation of the return period T (i.e. the inverse of the frequency f) for a combination of two different boundary conditions : T = 4.3 year and T 2 = 8.3 year Y f = 0.23 / year and f 2 = 0.2 / year Y f mean = 0.8 / year Y T mean = 5.7 year. However, in most cases the variability of the water level in the receiving water is not independent of the flow in the sewer system. The rainfall will lead to an increase in discharge in both the combined sewer system and the receiving water; sometimes at the same time, but usually with a time shift. This was shown for example by Dahl et al. [996] for a specific case study. Often only rough estimations are made on the interaction between sewer systems and receiving waters. The integrated modelling Chapter 5 : Design calculations 5.2

22 with time series is the only possibility for a correct incorporation of the time differences in peak flow in sewers and receiving waters. However, this will not likely be standard practice in the near future Data validation It has been standard practice for some years in Flanders to perform rainfall and flow measurements to validate the hydrodynamic models [Aquafin, 992, 994a, 996, 997]. This is a crucial phase in the design process. The measurements are not meant to be used for model calibration, but to check that no large errors have been made. The necessity of these measurements rises from the uncertainty on the input data for the models and the large impact of it is shown in figure 5.3. In Flanders, a lot of sewer system data originates from years or even decades ago and changes might not have been accounted for. However, if all sewer data should be redrawn, this would require much time and money. Using the flow measurements, a more purposeful data correction can be performed. Still, data collection remains one of the most sensitive phases in the design process. Some years of short term flow measurement campaigns have improved the models, but also have shown the large uncertainties that still exist on the model input [Willems, 995, 998b; Willems & Berlamont, 998b, c, 999]. In the future, special attention should also be paid to the spatial variability of the rainfall as discussed in paragraph 5.4. Because of the high influence of the water input into the sewer system, flow measurements should in the future be extended to long term measurements. This can be most easily done at the system outflows (e.g. pumps, combined sewer overflows, etc ). As a result, this can lead to a real calibration of the models (dry weather flow, impervious area, losses, contributing pervious area, ) so that they become operational models. It is clear that the data acquisition is a major bottle neck in the current sewer system design. This is a time consuming work, which is however very important. In Flanders, a lot of sewer system design are not yet performed using hydrodynamic simulations. Moreover, many sewer system designs were made decades ago. The data are only available on plans and design notes. There is thus a technological discrepancy in time, but also from one sewer system to another. This discrepancy can only be eliminated by a general review of the municipal sewer system plans as has already been stressed several times in the past [Berlamont, 994; Vlario 994; Vaes & Berlamont, 998a, 999b]. The main task in this is certainly the inventorying of the existing sewer systems. Once the sewer system data are available, the implementation of hydrodynamic simulations will then only be a small step in the process. The inventorying of the sewer system data is not only necessary for the design simulations, but also for the management of the municipal sewer systems The influence of rainfall and model simplification on combined sewer system design

23 5.6 Conclusions Every hydrological design is driven by the rainfall input. The extreme variability of the rainfall makes the design calculations complicated. However, a good design is in most cases obtained using single storms with only the mean rainfall characteristics included. In the past (before 996) some underdesign has taken place partially due to the underestimation of the rainfall input. Since the use of the composite storms, the calculated hydraulic parameters are much closer to those calculated with continuous long term simulations. It is however important to emphasize that there is a large uncertainty on the storm water input, because of the rainfall variability, but also because of the uncertainty on the contributing area and the runoff model. It has been shown that a limited error on the rainfall input can lead to significant differences in design return periods. The composite storms lead to an accurate prediction of the hydraulic parameters if the sewer system does not behave non-linearly. When the system behaviour becomes too far from linear, the temporal variability of the rainfall should be incorporated. If the non-linearity is situated upstream of the sewer system (e.g. in rain water tanks, infiltration facilities, runoff model, etc...) the rainfall variability can be incorporated using a simple model and long term simulations. The results of these simulations can then be incorporated in modified composite design storms. One of the weakest points in the current design methodology is the runoff model. Long term measurements and calibration of the runoff model (contributing area, losses, etc...) are necessary to obtain a good estimation of the rainwater input. For the design simulation the effect of this runoff model then could be incorporated in modified composite design storms. With this kind of simple model it is even possible to incorporate the uncertainty on the runoff parameters as has been implemented for the rain water tanks. If the non-linearity is situated in the sewer system itself, it is necessary to perform calculations with the original rainfall series. The calculation time then can be reduced using only a selection of short rainfall series. This still requires long calculation times and will therefore not replace the single storm simulations in the near future. However, it might serve as a check simulation. Up to now, the spatial variability has most often been neglected, because little knowledge and data were available to lead to a practical incorporation of the spatial variability in the design. This certainly needs more research. The first steps in this direction show that it can have a large influence on the flow in the sewer system. The design of a sewer system is more than the use of a simulation software and some design storms. It involves catchment data input, design methodology, design criteria and boundary conditions, which are certainly of equal importance as the software and the rainfall. All these parameters cannot be discussed separately. Furthermore, all Chapter 5 : Design calculations 5.23

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details Project Description File Name... 323 - Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow

More information

Flood Frequency Mapping using Multirun results from Infoworks RS applied to the river basin of the Yser, Belgium

Flood Frequency Mapping using Multirun results from Infoworks RS applied to the river basin of the Yser, Belgium Flood Frequency Mapping using Multirun results from Infoworks RS applied to the river basin of the Yser, Belgium Ir. Sven Verbeke Aminal, division Water, Flemish Government, Belgium Introduction Aminal

More information

CIE4491 Lecture. Hydraulic design

CIE4491 Lecture. Hydraulic design CIE4491 Lecture. Hydraulic design Marie-claire ten Veldhuis 19-9-013 Delft University of Technology Challenge the future Hydraulic design of urban stormwater systems Focus on sewer pipes Pressurized and

More information

THE DEVELOPMENT OF RAIN-BASED URBAN FLOOD FORECASTING METHOD FOR RIVER MANAGEMENT PRACTICE USING X-MP RADAR OBSERVATION

THE DEVELOPMENT OF RAIN-BASED URBAN FLOOD FORECASTING METHOD FOR RIVER MANAGEMENT PRACTICE USING X-MP RADAR OBSERVATION Research Paper Advances in River Engineering, JSCE, Vol.19, 2013,June THE DEVELOPMENT OF RAIN-BASED URBAN FLOOD FORECASTING METHOD FOR RIVER MANAGEMENT PRACTICE USING X-MP RADAR OBSERVATION Seongsim YOON

More information

Presented at WaPUG Spring Meeting 1 st May 2001

Presented at WaPUG Spring Meeting 1 st May 2001 Presented at WaPUG Spring Meeting 1 st May 21 Author: Richard Allitt Richard Allitt Associates Ltd 111 Beech Hill Haywards Heath West Sussex RH16 3TS Tel & Fax (1444) 451552 1. INTRODUCTION The Flood Estimation

More information

Quantifying model uncertainty in the simulation of sewer overflow volume

Quantifying model uncertainty in the simulation of sewer overflow volume Quantifying model uncertainty in the simulation of sewer overflow volume Ambuj Sriwastava Marie Curie Early Stage Researcher, University of Sheffield This project has received funding from the European

More information

D. MATHEMATICAL MODEL AND SIMULATION

D. MATHEMATICAL MODEL AND SIMULATION D. MATHEMATICAL MODEL AND SIMULATION D - i TABLE OF CONTENTS D.1 Objective of Model Development... D - 1 D.2 Selection of Software... D - 1 D.3 General Steps of Simulation by MOUSE... D - 1 D.4 Cases of

More information

Storm rainfall. Lecture content. 1 Analysis of storm rainfall 2 Predictive model of storm rainfall for a given

Storm rainfall. Lecture content. 1 Analysis of storm rainfall 2 Predictive model of storm rainfall for a given Storm rainfall Lecture content 1 Analysis of storm rainfall 2 Predictive model of storm rainfall for a given max rainfall depth 1 rainfall duration and return period à Depth-Duration-Frequency curves 2

More information

9. Flood Routing. chapter Two

9. Flood Routing. chapter Two 9. Flood Routing Flow routing is a mathematical procedure for predicting the changing magnitude, speed, and shape of a flood wave as a function of time at one or more points along a watercourse (waterway

More information

FHWA - HIGHWAY HYDROLOGY

FHWA - HIGHWAY HYDROLOGY The unit peak discharge is computed with Equation 5.6 by interpolating c 0, c, and c Table 5.5 using a type II distribution. The peak discharge is also calculated as follows. from Variable SI Unit U Unit.5444

More information

Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams

Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams Practical methodology for inclusion of uplift and pore pressures in analysis of concrete dams Michael McKay 1 and Francisco Lopez 2 1 Dams Engineer, GHD Pty 2 Principal Dams/Structural Engineer, GHD Pty

More information

The University of Akron. William Troyer The Dr. Gary B. and Pamela S. Williams Honors College

The University of Akron. William Troyer The Dr. Gary B. and Pamela S. Williams Honors College The University of Akron IdeaExchange@UAkron Honors Research Projects The Dr. Gary B. and Pamela S. Williams Honors College Spring 2018 Applying Control Logic to the End of the Ohio Canal Interceptor Tunnel

More information

The most important equation to describe the water balance of a reservoir is the water balance: Equation 3.1

The most important equation to describe the water balance of a reservoir is the water balance: Equation 3.1 3 FLOOD PROPAGATION 3.1 Reservoir routing The most important equation to describe the water balance of a reservoir is the water balance: ds = I Q + A P E dt ( ) In finite differences form this equation

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY. Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc.

INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY. Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc. INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc. Course Contents Introduction to Random Variables (RVs) Probability Distributions

More information

Tarbela Dam in Pakistan. Case study of reservoir sedimentation

Tarbela Dam in Pakistan. Case study of reservoir sedimentation Tarbela Dam in Pakistan. HR Wallingford, Wallingford, UK Published in the proceedings of River Flow 2012, 5-7 September 2012 Abstract Reservoir sedimentation is a main concern in the Tarbela reservoir

More information

Rucker Pond. Background

Rucker Pond. Background Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different

More information

The Sensitivity Analysis of Runoff from Urban Catchment Based on the Nonlinear Reservoir Rainfall-Runoff Model

The Sensitivity Analysis of Runoff from Urban Catchment Based on the Nonlinear Reservoir Rainfall-Runoff Model PUBLS. INST. GEOPHYS. POL. ACAD. SC., E-6 (390), 2006 The Sensitivity Analysis of Runoff from Urban Catchment Based on the Nonlinear Reservoir Rainfall-Runoff Model Marcin SKOTNICKI and Marek SOWIŃSKI

More information

Probabilistic forecasting for urban water management: A case study

Probabilistic forecasting for urban water management: A case study 9th International Conference on Urban Drainage Modelling Belgrade 212 Probabilistic forecasting for urban water management: A case study Jeanne-Rose Rene' 1, Henrik Madsen 2, Ole Mark 3 1 DHI, Denmark,

More information

Leuven case study. International workshop & project meeting Leuven, April 2012

Leuven case study. International workshop & project meeting Leuven, April 2012 Leuven case study International workshop & project meeting Leuven, 16-17 April 2012 Johan Van Assel (Aquafin) Laurens Cas Decloedt, Patrick Willems (KU Leuven) Raingain Project meeting 17/04/2012 - Aquafin

More information

Improved rainfall estimates and forecasts for urban hydrological applications

Improved rainfall estimates and forecasts for urban hydrological applications Improved rainfall estimates and forecasts for urban hydrological applications Innovyze User Days - Drainage and Flooding User Group Wallingford, 20 th June 2013 Contents 1. Context 2. Radar rainfall processing

More information

Better estimation of Flood Wave Propagation Time in Meandering Reaches by using 2D-modelling

Better estimation of Flood Wave Propagation Time in Meandering Reaches by using 2D-modelling Better estimation of Flood Wave Propagation Time in Meandering Reaches by using 2D-modelling J. Persson M. Jewert N. Isaksson Norconsult AB, Sweden Norconsult AB, Sweden Fortum Generation AB, Sweden ABSTRACT

More information

Drought Criteria. Richard J. Heggen Department of Civil Engineering University of New Mexico, USA Abstract

Drought Criteria. Richard J. Heggen Department of Civil Engineering University of New Mexico, USA Abstract Drought Criteria Richard J. Heggen Department of Civil Engineering University of New Mexico, USA rheggen@unm.edu Abstract Rainwater catchment is an anticipatory response to drought. Catchment design requires

More information

STORMWATER DESIGN CALCULATIONS

STORMWATER DESIGN CALCULATIONS STORMWATER DESIGN CALCULATIONS REF : C7011-2390 AT 19a-23 MEMORIAL AVENUE BLACKWALL FOR MR KERR Contents 1.0 Detention System Requirements 1.1 Storage-Area calcs. 1.2 Data Files for Pre & Post Developed

More information

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES

PRELIMINARY DRAFT FOR DISCUSSION PURPOSES Memorandum To: David Thompson From: John Haapala CC: Dan McDonald Bob Montgomery Date: February 24, 2003 File #: 1003551 Re: Lake Wenatchee Historic Water Levels, Operation Model, and Flood Operation This

More information

EFFECTIVE DAM OPERATION METHOD BASED ON INFLOW FORECASTING FOR SENANAYAKA SAMUDRA RESERVOIR, SRI LANKA

EFFECTIVE DAM OPERATION METHOD BASED ON INFLOW FORECASTING FOR SENANAYAKA SAMUDRA RESERVOIR, SRI LANKA EFFECTIVE DAM OPERATION METHOD BASED ON INFLOW FORECASTING FOR SENANAYAKA SAMUDRA RESERVOIR, SRI LANKA Muthubanda Appuhamige Sanath Susila GUNASENA (MEE13632) Supervisors: Dr. Mamoru Miyamoto, Dr. Duminda

More information

INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY. Lecture -29 Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc.

INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY. Lecture -29 Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc. INDIAN INSTITUTE OF SCIENCE STOCHASTIC HYDROLOGY Lecture -29 Course Instructor : Prof. P. P. MUJUMDAR Department of Civil Engg., IISc. Summary of the previous lecture Goodness of fit Chi-square test χ

More information

Notes: We all know that Toulmins Spring Branch is a sub-watershed of Three Mile Creek watershed. Some part of it is in Mobile area and rest of it is

Notes: We all know that Toulmins Spring Branch is a sub-watershed of Three Mile Creek watershed. Some part of it is in Mobile area and rest of it is 1 Notes: This presentation is about some of our findings from a study carried out over the last 3-4 months on stormwater management of Toulmins Spring Branch watershed by NEP. The objective of this study

More information

Workshop: Build a Basic HEC-HMS Model from Scratch

Workshop: Build a Basic HEC-HMS Model from Scratch Workshop: Build a Basic HEC-HMS Model from Scratch This workshop is designed to help new users of HEC-HMS learn how to apply the software. Not all the capabilities in HEC-HMS are demonstrated in the workshop

More information

Haiti and Dominican Republic Flash Flood Initial Planning Meeting

Haiti and Dominican Republic Flash Flood Initial Planning Meeting Dr Rochelle Graham Climate Scientist Haiti and Dominican Republic Flash Flood Initial Planning Meeting September 7 th to 9 th, 2016 Hydrologic Research Center http://www.hrcwater.org Haiti and Dominican

More information

Opanuku Stream Benchmark Validation 1. Introduction. 2. The Opanuku Stream Model

Opanuku Stream Benchmark Validation 1. Introduction. 2. The Opanuku Stream Model Opanuku Stream Benchmark Validation 1. Introduction The model accuracy benchmark published by the Flood Risk Management Committee of the IAHR in http://members.iahr.org/imis/communitymanagement/communitylayouts/flood_risk_manageme

More information

Accuracy of Muskingum-Cunge flood routing

Accuracy of Muskingum-Cunge flood routing Alternative Hydraulics Paper 3, 02.03.2011 Accuracy of Musingum-Cunge flood routing Institute of Hydraulic and Water Resources Engineering Vienna University of Technology Karlsplatz 13/222, 1040 Vienna,

More information

CVE 372 HYDROMECHANICS EXERCISE PROBLEMS

CVE 372 HYDROMECHANICS EXERCISE PROBLEMS VE 37 HYDROMEHNIS EXERISE PROLEMS 1. pump that has the characteristic curve shown in the accompanying graph is to be installed in the system shown. What will be the discharge of water in the system? Take

More information

JUNE 2004 Flood hydrology of the Waiwhetu Stream

JUNE 2004 Flood hydrology of the Waiwhetu Stream JUNE 2004 Flood hydrology of the Waiwhetu Stream Laura Watts Resource Investigations Contents 1. Introduction 1 2. Catchment description 2 3. Data availability and quality 3 3.1 Rainfall data 3 3.2 Water

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

Flood Routing by the Non-Linear Muskingum Model: Conservation of Mass and Momentum

Flood Routing by the Non-Linear Muskingum Model: Conservation of Mass and Momentum Archives of Hydro-Engineering and Environmental Mechanics Vol. 56 (29), No. 3 4, pp. 121 137 IBW PAN, ISSN 1231 3726 Flood Routing by the Non-Linear Muskingum Model: Conservation of Mass and Momentum Dariusz

More information

WATER MANAGEMENT REPORT FOR PAGE ESTATES

WATER MANAGEMENT REPORT FOR PAGE ESTATES WATER MANAGEMENT REPORT FOR PAGE ESTATES SLB Consulting of SW Florida, LLC PO Box 2826 Bonita Springs, FL. 34133 Phone: 239-948-9566 sandra@slbconsult.com C.O.A. # 25395 September 1, 2014 Sandra L. Bottcher

More information

The HYDRATE network of hydrometeorological observatories:

The HYDRATE network of hydrometeorological observatories: The HYDRATE network of hydrometeorological observatories:. taking stock, looking ahead Marco Borga University of Padova Department of Land and Agroforest Environments marco.borga@unipd.it Outline HYDRATE-NHO:

More information

Generation of synthetic design storms for the Upper Thames River basin

Generation of synthetic design storms for the Upper Thames River basin Generation of synthetic design storms for the Upper Thames River basin CFCAS project: Assessment of Water Resources Risk and Vulnerability to Changing Climatic Conditions Project Report V. November 2004

More information

EFFICIENCY OF THE INTEGRATED RESERVOIR OPERATION FOR FLOOD CONTROL IN THE UPPER TONE RIVER OF JAPAN CONSIDERING SPATIAL DISTRIBUTION OF RAINFALL

EFFICIENCY OF THE INTEGRATED RESERVOIR OPERATION FOR FLOOD CONTROL IN THE UPPER TONE RIVER OF JAPAN CONSIDERING SPATIAL DISTRIBUTION OF RAINFALL EFFICIENCY OF THE INTEGRATED RESERVOIR OPERATION FOR FLOOD CONTROL IN THE UPPER TONE RIVER OF JAPAN CONSIDERING SPATIAL DISTRIBUTION OF RAINFALL Dawen YANG, Eik Chay LOW and Toshio KOIKE Department of

More information

2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (# )

2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (# ) www.fixmylake.com 18029 83 rd Avenue North Maple Grove, MN 55311 mail@freshwatersci.com (651) 336-8696 2012 Rainfall, Runoff, Water Level & Temperature Beebe Lake Wright County, MN (#86-0023) Prepared

More information

Storm Sewer Design [2]

Storm Sewer Design [2] Class 5 [1] Storm Sewer Design 9. Check Q < Qf and Vmax > vf > Vmin. Vmin is normally specified to avoid sedimentation. This will normally be 1.0 m/s at pipe full condition. (BS EN 752 suggests that for

More information

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1

A Simple Procedure for Estimating Loss of Life from Dam Failure. Wayne J. Graham, P.E. 1 A Simple Procedure for Estimating Loss of Life from Dam Failure Wayne J. Graham, P.E. 1 INTRODUCTION Evaluating the consequences resulting from a dam failure is an important and integral part of any dam

More information

HYDRAULIC MODELLING OF NENJIANG RIVER FLOODPLAIN IN NORTHEAST CHINA

HYDRAULIC MODELLING OF NENJIANG RIVER FLOODPLAIN IN NORTHEAST CHINA HYDRAULIC MODELLING OF NENJIANG RIVER FLOODPLAIN IN NORTHEAST CHINA Xiao Fei MEE08181 Supervisor: A.W. Jayawardena ABSTRACT In 1998, the worst flood recorded for over 200 years hit the Songhua River Basin

More information

Operational modelling & forecasting in urban catchments. Richard Body Product Sector Leader Operational Forecasting

Operational modelling & forecasting in urban catchments. Richard Body Product Sector Leader Operational Forecasting Operational modelling & forecasting in urban catchments Richard Body Product Sector Leader Operational Forecasting Contents What is operational forecasting Innovyze software ICMLive components Benefits

More information

Application of Real-Time Rainfall Information System to CSO control. 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd.

Application of Real-Time Rainfall Information System to CSO control. 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd. Application of Real-Time Rainfall Information System to CSO control 2 October 2011 Naruhito Funatsu METAWATER Co., Ltd. Presentation Points Objectives To verify the applicability of the real-time rainfall

More information

PLANNED UPGRADE OF NIWA S HIGH INTENSITY RAINFALL DESIGN SYSTEM (HIRDS)

PLANNED UPGRADE OF NIWA S HIGH INTENSITY RAINFALL DESIGN SYSTEM (HIRDS) PLANNED UPGRADE OF NIWA S HIGH INTENSITY RAINFALL DESIGN SYSTEM (HIRDS) G.A. Horrell, C.P. Pearson National Institute of Water and Atmospheric Research (NIWA), Christchurch, New Zealand ABSTRACT Statistics

More information

Drought Monitoring with Hydrological Modelling

Drought Monitoring with Hydrological Modelling st Joint EARS/JRC International Drought Workshop, Ljubljana,.-5. September 009 Drought Monitoring with Hydrological Modelling Stefan Niemeyer IES - Institute for Environment and Sustainability Ispra -

More information

WATER DISTRIBUTION NETWORKS

WATER DISTRIBUTION NETWORKS WATER DISTRIBUTION NETWORKS CE 370 1 Components of Water Supply System 2 1 Water Distribution System Water distribution systems are designed to adequately satisfy the water requirements for a combinations

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

The role of predictive uncertainty in the operational management of reservoirs

The role of predictive uncertainty in the operational management of reservoirs 118 Evolving Water Resources Systems: Understanding, Predicting and Managing Water Society Interactions Proceedings of ICWRS014, Bologna, Italy, June 014 (IAHS Publ. 364, 014). The role of predictive uncertainty

More information

WEIGHING GAUGES MEASUREMENT ERRORS AND THE DESIGN RAINFALL FOR URBAN SCALE APPLICATIONS

WEIGHING GAUGES MEASUREMENT ERRORS AND THE DESIGN RAINFALL FOR URBAN SCALE APPLICATIONS WEIGHING GAUGES MEASUREMENT ERRORS AND THE DESIGN RAINFALL FOR URBAN SCALE APPLICATIONS by M. Colli (1), L.G. Lanza (1),(2) and P. La Barbera (1) (1) University of Genova, Dep. of Construction, Chemical

More information

Probability Estimation of River Channel Capacity

Probability Estimation of River Channel Capacity 1 Paper N 0 : V.07 Probability Estimation of River Channel Capacity Jaromir Riha Pavel Golik Abstract: Recently, the risk analysis of floodplain areas has been one of the most frequently used tools for

More information

ENGINEERING HYDROLOGY

ENGINEERING HYDROLOGY ENGINEERING HYDROLOGY Prof. Rajesh Bhagat Asst. Professor Civil Engineering Department Yeshwantrao Chavan College Of Engineering Nagpur B. E. (Civil Engg.) M. Tech. (Enviro. Engg.) GCOE, Amravati VNIT,

More information

Chapter 5 CALIBRATION AND VERIFICATION

Chapter 5 CALIBRATION AND VERIFICATION Chapter 5 CALIBRATION AND VERIFICATION This chapter contains the calibration procedure and data used for the LSC existing conditions model. The goal of the calibration effort was to develop a hydraulic

More information

FLORA: FLood estimation and forecast in complex Orographic areas for Risk mitigation in the Alpine space

FLORA: FLood estimation and forecast in complex Orographic areas for Risk mitigation in the Alpine space Natural Risk Management in a changing climate: Experiences in Adaptation Strategies from some European Projekts Milano - December 14 th, 2011 FLORA: FLood estimation and forecast in complex Orographic

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

Design Storms for Hydrologic Analysis

Design Storms for Hydrologic Analysis Design Storms for Hydrologic Analysis Course Description This course is designed to fulfill two hours of continuing education credit for Professional Engineers. Its objective is to provide students with

More information

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS

CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS CONCEPTUAL AND TECHNICAL CHALLENGES IN DEFINING FLOOD PLANNING AREAS IN URBAN CATCHMENTS C Ryan 1, D Tetley 2, C Kinsey 3 1 & 2 Catchment Simulation Solutions, NSW 3 Co-ordinator Stormwater and Structural

More information

Environment Protection Engineering DEPTH-DURATION-FREQUENCY RAINFALL MODEL FOR DIMENSIONING AND MODELLING OF WROCŁAW DRAINAGE SYSTEMS

Environment Protection Engineering DEPTH-DURATION-FREQUENCY RAINFALL MODEL FOR DIMENSIONING AND MODELLING OF WROCŁAW DRAINAGE SYSTEMS Environment Protection Engineering Vol. 38 212 No. 4 DOI: 1.5277/EPE12411 BARTOSZ KAŹMIERCZAK*, ANDRZEJ KOTOWSKI* DEPTH-DURATION-FREQUENCY RAINFALL MODEL FOR DIMENSIONING AND MODELLING OF WROCŁAW DRAINAGE

More information

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No:

Technical Memorandum. City of Salem, Stormwater Management Design Standards. Project No: Technical Memorandum 6500 SW Macadam Avenue, Suite 200 Portland, Oregon, 97239 Tel: 503-244-7005 Fax: 503-244-9095 Prepared for: Project Title: City of Salem, Oregon City of Salem, Stormwater Management

More information

Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati

Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati Hydraulics Prof. Dr. Arup Kumar Sarma Department of Civil Engineering Indian Institute of Technology, Guwahati Module No. # 08 Pipe Flow Lecture No. # 05 Water Hammer and Surge Tank Energy cannot be consumed

More information

Susanna Glaze, Bobby Creel, and Christopher Brown New Mexico State University AWRA Spring Specialty Conference 4-6 May 2009 Anchorage, Alaska

Susanna Glaze, Bobby Creel, and Christopher Brown New Mexico State University AWRA Spring Specialty Conference 4-6 May 2009 Anchorage, Alaska Susanna Glaze, Bobby Creel, and Christopher Brown New Mexico State University 2009 AWRA Spring Specialty Conference 4-6 May 2009 Anchorage, Alaska Outline Introduction to general water resources issues

More information

REGULATORY, TECHNICAL AND MODELING CHALLENGES TO DEVELOPING A FREQUENCY BASED SSO CONTROL PROJECT IN WAYNE COUNTY, MICHIGAN

REGULATORY, TECHNICAL AND MODELING CHALLENGES TO DEVELOPING A FREQUENCY BASED SSO CONTROL PROJECT IN WAYNE COUNTY, MICHIGAN REGULATORY, TECHNICAL AND MODELING CHALLENGES TO DEVELOPING A FREQUENCY BASED SSO CONTROL PROJECT IN WAYNE COUNTY, MICHIGAN Robert Czachorski, P.E., P.H., Orchard, Hiltz & McCliment, Inc. * John Baratta.

More information

Using a high-resolution ensemble modeling method to inform risk-based decision-making at Taylor Park Dam, Colorado

Using a high-resolution ensemble modeling method to inform risk-based decision-making at Taylor Park Dam, Colorado Using a high-resolution ensemble modeling method to inform risk-based decision-making at Taylor Park Dam, Colorado Michael J. Mueller 1, Kelly Mahoney 2, Kathleen Holman 3, David Gochis 4 1 Cooperative

More information

Large Alberta Storms. March Introduction

Large Alberta Storms. March Introduction Large Alberta Storms Introduction Most of the largest runoff events in Alberta have been in response to large storms. Storm properties, such as location, magnitude, and geographic and temporal distribution

More information

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water. Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

RELIABILITY OF DESIGN STORMS IN MODELLING

RELIABILITY OF DESIGN STORMS IN MODELLING Page 1 of 13 RELIABILITY OF DESIGN STORMS IN MODELLING BY BEN URBONAS CHIEF, MASTER P LANNING P ROGRAM URBAN DRAINAGE AND FLOOD CONTROL DISTRICT DENVER, COLORADO Abstract. Stormwater runoff is generally

More information

Calibrate Rotameter and Orifice Meter and Explore Reynolds #

Calibrate Rotameter and Orifice Meter and Explore Reynolds # CM3215 Fundamentals of Chemical Engineering Laboratory Calibrate Rotameter and Orifice Meter and Explore Reynolds # Extra features! Professor Faith Department of Chemical Engineering Michigan Technological

More information

Numerical Hydraulics

Numerical Hydraulics ETH Zurich, Fall 2017 Numerical Hydraulics Assignment 2 Numerical solution of shallow water wave propagation (www.surfertoday.com) 1 Introduction 1.1 Equations Understanding the propagation of shallow

More information

Lecture Note for Open Channel Hydraulics

Lecture Note for Open Channel Hydraulics Chapter -one Introduction to Open Channel Hydraulics 1.1 Definitions Simply stated, Open channel flow is a flow of liquid in a conduit with free space. Open channel flow is particularly applied to understand

More information

Radar-raingauge data combination techniques: A revision and analysis of their suitability for urban hydrology

Radar-raingauge data combination techniques: A revision and analysis of their suitability for urban hydrology 9th International Conference on Urban Drainage Modelling Belgrade 2012 Radar-raingauge data combination techniques: A revision and analysis of their suitability for urban hydrology L. Wang, S. Ochoa, N.

More information

Reliability Assessment of Water Distribution Networks Considering Mechanical-Hydraulic Behavior Using Informational Entropy

Reliability Assessment of Water Distribution Networks Considering Mechanical-Hydraulic Behavior Using Informational Entropy Reliability Assessment of Water Distribution Networks Considering Mechanical-Hydraulic Behavior Using Informational Entropy H. Emamjomeh & M. Hosseini International Institute of Earthquake Engineering

More information

Flood and runoff estimation on small catchments. Duncan Faulkner

Flood and runoff estimation on small catchments. Duncan Faulkner Flood and runoff estimation on small catchments Duncan Faulkner Flood and runoff estimation on small catchments Duncan Faulkner and Oliver Francis, Rob Lamb (JBA) Thomas Kjeldsen, Lisa Stewart, John Packman

More information

Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica. An assessment of future flood risk. projections of future climate

Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica. An assessment of future flood risk. projections of future climate Terrestrial Flood Risk and Climate Change in the Yallahs River, Jamaica An assessment of future flood risk using hydrodynamic models driven by projections of future climate Matthew Wilson1, Arpita Mandal2,

More information

PRECIPITATION. Assignment 1

PRECIPITATION. Assignment 1 Assignment 1 PRECIPIAION Due: 25.10.2017 Monitoring of precipitation is based on an almost worldwide network of measuring stations (point measurements). However, for the investigation of fundamental questions

More information

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH

FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH FLOOD HAZARD AND RISK ASSESSMENT IN MID- EASTERN PART OF DHAKA, BANGLADESH Muhammad MASOOD MEE07180 Supervisor: Prof. Kuniyoshi TAKEUCHI ABSTRACT An inundation simulation has been done for the mid-eastern

More information

12 SWAT USER S MANUAL, VERSION 98.1

12 SWAT USER S MANUAL, VERSION 98.1 12 SWAT USER S MANUAL, VERSION 98.1 CANOPY STORAGE. Canopy storage is the water intercepted by vegetative surfaces (the canopy) where it is held and made available for evaporation. When using the curve

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

"Modelling air quality in the city"

Modelling air quality in the city "Modelling air quality in the city" Diede Nijmeijer Master thesis University of Twente Applied Mathematics Specialization: Mathematical Physics and Computational Mechanics Chair: Multiscale Modelling and

More information

Chapter 3.8: Energy Dissipators. By Dr. Nuray Denli Tokyay

Chapter 3.8: Energy Dissipators. By Dr. Nuray Denli Tokyay Chapter 3.8: Energy Dissipators By Dr. Nuray Denli Tokyay 3.1 Introduction A stilling basin is a short length of paved channel placed at the foot of a spillway or any other source of supercritical flow

More information

Sewer, pressurization, differential pressure monitoring, fully dynamic hydraulic modeling, air displacement modeling.

Sewer, pressurization, differential pressure monitoring, fully dynamic hydraulic modeling, air displacement modeling. Using Dynamic Hydraulic Modeling to Understand Sewer Headspace Dynamics A Case Study of Metro Vancouver s Highbury Interceptor Yuko Suda, P.Eng. Kerr Wood Leidal Associates Ltd. 200-4185A Still Creek Drive

More information

Flash Flood Guidance System On-going Enhancements

Flash Flood Guidance System On-going Enhancements Flash Flood Guidance System On-going Enhancements Hydrologic Research Center, USA Technical Developer SAOFFG Steering Committee Meeting 1 10-12 July 2017 Jakarta, INDONESIA Theresa M. Modrick Hansen, PhD

More information

Monte Carlo Simulations for Probabilistic Flood Hazard Assessment

Monte Carlo Simulations for Probabilistic Flood Hazard Assessment Monte Carlo Simulations for Probabilistic Flood Hazard Assessment Jemie Dababneh, Ph.D., P.E., 1 and Mark Schwartz, P.E. 1 1 RIZZO Associates, Monroeville, Pennsylvania Presentation to PSA 2017 International

More information

Impact of the Danube River on the groundwater dynamics in the Kozloduy Lowland

Impact of the Danube River on the groundwater dynamics in the Kozloduy Lowland GEOLOGICA BALCANICA, 46 (2), Sofia, Nov. 2017, pp. 33 39. Impact of the Danube River on the groundwater dynamics in the Kozloduy Lowland Peter Gerginov Geological Institute, Bulgarian Academy of Sciences,

More information

PSA on Extreme Weather Phenomena for NPP Paks

PSA on Extreme Weather Phenomena for NPP Paks PSA on Extreme Weather Phenomena for NPP Paks Tamás Siklóssy siklossyt@nubiki.hu WGRISK Technical Discussion on PSA Related to Weather-Induced Hazards Paris, 9 March, 2017 Background Level 1 Seismic PSA

More information

Contents. Diaphragm in pressure pipe: Steady state head loss evolution and transient phenomena. Nicolas J. Adam Giovanni De Cesare

Contents. Diaphragm in pressure pipe: Steady state head loss evolution and transient phenomena. Nicolas J. Adam Giovanni De Cesare Diaphragm in pressure pipe: Steady state head loss evolution and transient phenomena Nicolas J. Adam Giovanni De Cesare Contents Introduction FMHL pumped-storage plant Experimental set-up Steady head losses

More information

High intensity rainfall estimation in New Zealand

High intensity rainfall estimation in New Zealand Water New Zealand 31 st October 2013 High intensity rainfall estimation in New Zealand Graeme Horrell Engineering Hydrologist, Contents High Intensity Rainfall Design System (HIRDS Version 1) HIRDS Version

More information

Workshop on MCCOE Radar Meteorology /Climatology in Indonesia. Segel Ginting Wanny K. Adidarma

Workshop on MCCOE Radar Meteorology /Climatology in Indonesia. Segel Ginting Wanny K. Adidarma Workshop on MCCOE Radar Meteorology /Climatology in Indonesia BPPT, 28 Februari 2013 JAKARTA FLOOD EARLY WARNING SYSTEM (J-FEWS) Segel Ginting Wanny K. Adidarma JCP (Joint Cooperation Program) Indonesia

More information

Advanced Chemical Reaction Engineering Prof. H. S. Shankar Department of Chemical Engineering IIT Bombay. Lecture - 03 Design Equations-1

Advanced Chemical Reaction Engineering Prof. H. S. Shankar Department of Chemical Engineering IIT Bombay. Lecture - 03 Design Equations-1 (Refer Slide Time: 00:19) Advanced Chemical Reaction Engineering Prof. H. S. Shankar Department of Chemical Engineering IIT Bombay Lecture - 03 Design Equations-1 We are looking at advanced reaction engineering;

More information

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By:

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By: HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI Project No.

More information

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) Stormwater Guidelines and Case Studies CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Goals and Challenges for Manual State Stormwater Policy More Widespread

More information

GEOL 1121 Earth Processes and Environments

GEOL 1121 Earth Processes and Environments GEOL 1121 Earth Processes and Environments Wondwosen Seyoum Department of Geology University of Georgia e-mail: seyoum@uga.edu G/G Bldg., Rm. No. 122 Seyoum, 2015 Chapter 6 Streams and Flooding Seyoum,

More information

*Corresponding author,

*Corresponding author, Monitoring the performance of a storm water separating manifold with DTS J.G. Langeveld 1,3*, C. de Haan 1,3, M. Klootwijk 2 and R.P.S. Schilperoort, 1,3 1 Royal Haskoning, Barbarossastraat 35, P.O. Box

More information

Improvements to Southeast Louisiana s floodwalls and pump stations since Katrina: the Hurricane and Storm Damage Risk Reduction System (HSDRRS)

Improvements to Southeast Louisiana s floodwalls and pump stations since Katrina: the Hurricane and Storm Damage Risk Reduction System (HSDRRS) Improvements to Southeast Louisiana s floodwalls and pump stations since Katrina: the Hurricane and Storm Damage Risk Reduction System (HSDRRS) Pat Fitzpatrick Mississippi State University Review of levee

More information

How Wrong is Your Flood Model? Bill Syme, Senior Principal, BMT Water & Environment

How Wrong is Your Flood Model? Bill Syme, Senior Principal, BMT Water & Environment How Wrong is Your Flood Model? Bill Syme, Senior Principal, BMT Water & Environment Always! Really Accurate How Accurate is my Model? Sufficiently Accurate Young Modeller (or Salesperson!) Old Modeller

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

Technical Memorandum No

Technical Memorandum No Pajaro River Watershed Study in association with Technical Memorandum No. 1.2.10 Task: Evaluation of Four Watershed Conditions - Sediment To: PRWFPA Staff Working Group Prepared by: Gregory Morris and

More information

Optimal Artificial Neural Network Modeling of Sedimentation yield and Runoff in high flow season of Indus River at Besham Qila for Terbela Dam

Optimal Artificial Neural Network Modeling of Sedimentation yield and Runoff in high flow season of Indus River at Besham Qila for Terbela Dam Optimal Artificial Neural Network Modeling of Sedimentation yield and Runoff in high flow season of Indus River at Besham Qila for Terbela Dam Akif Rahim 1, Amina Akif 2 1 Ph.D Scholar in Center of integrated

More information