3. MARINE HABITAT RESTORATION
|
|
- Hester Barber
- 5 years ago
- Views:
Transcription
1 Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 3. MARINE HABITAT RESTORATION Marine habitat restoration at Titlow Park could include restoration of the south beach, dredging the lower lagoon, and restoration of the lagoon shoreline and upper/lower lagoon connection. Design concepts and costs for these actions are described in this section. Appendix D provides detailed cost estimates for design, permitting, BNSF coordination, construction, and other items. Costs noted below include all of these project elements. Table 3-1 summarizes project costs and provides a comprehensive cost for three potential restoration alternatives. Table 3-1. Summary and Compilation of Estimated Project Costs Construction Element Interim Action for Existing Fish Passage Pipe Fish Passage Rail Bridge Fish Passage CONSTRUCTION COST Enhancing Existing Fish Passage $42,000 Dredging Lagoon $228,000 $228,000 $228,000 Upper/Lower Lagoon Connection Channel $133,000 $133,000 $133,000 Off-Site Disposal of Lagoon Sediment $1,023,000 $1,023,000 $1,023,000 Pipe Fish Passage $1,153,000 Rail Bridge Fish Passage $2,969,000 Total: $1,426,000 $2,537,000 $4,353,000 OPTIONAL/CONTINGENCY WORK ELEMENTS South Beach Restoration/Fill $520,000 $520,000 Off-Site Disposal of Lagoon Sediment $760,000 $760,000 $760,000 Total: $1,286,000 $3,817,000 $5,633, BEACH RESTORATION Figure 3-1 shows a beach restoration concept. Beach restoration is included in this Feasibility Study for completeness, but was not an element of the preferred alternative in the Master Planning process. The north beach appears to provide satisfactory intertidal habitat and does not require restoration. Ongoing beach nourishment from eroding shoreline bluffs is apparently maintaining the beach in good condition. The existing sediment delta offshore of the lagoon outlet pipe provides high quality intertidal habitat directly adjacent to lagoon connection. Restoration of the south beach would provide a slight increase in additional habitat value. Restoration of the south beach area by shoreline softening or pull-back is not possible due to the presence of the existing BNSF railroad embankment. Restoration of the south beach could be accomplished by placing approximately 27,000 cubic yards (cy) of sand and gravel in the existing intertidal zone in a wedge approximately 1,000 feet long by 160 feet wide by 8 feet deep at the revetment to create a beach extending above the intertidal zone and having a slope of approximately 8 horizontal to 1 vertical to seaward. The cost for this beach fill is estimated at approximately $800,000 to $1,000,000, if material is procured from upland sources. Clean dredged sediment from a source such as the Port of Tacoma could be obtained and used for the bulk of the fill; however, dredged material would likely be predominantly sand, which would be finer grained January (01/0202) 3-1
2 Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group and more prone to erosion than the preferred material (sand and gravel). The beach fill could be constructed primarily with dredged material, and then capped with gravel from an upland source. Using this approach, the cost for the beach fill is estimated at approximately $520,000. Maintaining the restored south beach would likely require periodic replacement of beach material lost by natural beach processes and transported offshore by the lagoon outflow. However, the replenish volume and schedule cannot be reliably estimated. Appendix B provides additional discussion of site geomorphology and beach restoration. 3.2 LAGOON RESTORATION Several actions are recommended to restore the Titlow Lagoon: Dredge the lower lagoon deeper to provide improved habitat for juvenile salmon during low water conditions (see Section 3.3). Replace the narrow wood drainage channel between the upper and lower lagoons with a broad natural channel (see Section 3.4). Modify the lower lagoon shoreline to increase its length and complexity; grade the shoreline to create salt marsh habitat; and soften the shoreline through removal of riprap, placement of woody debris and plants, and other restoration methods. Enhance the shoreline of the southeast portion of the upper lagoon between the existing pedestrian bridge and the creek. The remainder of the upper lagoon appears to provide good quality habitat that does not need restoration. This Feasibility Study addresses the first two actions noted above (see Sections 3.3 and 3.4). Figure 3-2 illustrates a lagoon restoration concept that addresses the latter two actions. The specific lagoon shoreline configuration and elevations will be determined during final design. The size and elevation of the lower lagoon bottom allows for dredging part of the lagoon without requiring excavation or setback of the lagoon shoreline; therefore, these two goals can be accomplished independently for the most part. The estimated cost to restore the lagoon shoreline is $1.0 million. This cost includes $300,000 to demolish the pool and pool building. This cost of pool demolition is a preliminary order of magnitude estimate. Preparation of a detailed pool demolition cost estimate was not part of the scope of work for this feasibility study Lower Lagoon Dredging Dredging the lower lagoon approximately 8 feet deeper (from -1 foot to -9 feet NGVD20 [+5 feet MLLW to -3 feet MLLW]) to provide improved habitat for juvenile salmon during low water conditions is one of the recommendations. The lagoon, but not the lagoon fish passage, would be deepened to maintain a deeper pool in the lagoon during low water conditions to provide improved water conditions (i.e., temperature, quality) in the lagoon and less bird predation. Figure 3-3 shows a possible scenario for dredging area and contours. Dredging to these contours would generate approximately 9,100 cubic yards of sediment. Dredging of the lagoon is expected to be subject to Puget Sound Dredge Disposal requirements and would require characterization, even if the sediment is excavated in the dry and disposed of on-site. In general, this means a sediment sampling and analysis plan must be negotiated with the Washington State Department of Natural Resources and the U.S. Corps of Engineers, and sampling protocols (including number of samples, sampling methods, and analyses) must 3-2 January (01/0202)
3 Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group meet Puget Sound Dredged Disposal Analysis (PSDDA) requirements. The characterization is expected to consist of two to three core samples (10 feet long) from the lagoon in the area of the proposed dredging. The cores would be segmented into sediment above and below the proposed dredging limit, and the sediment analyzed for physical properties (e.g., gradation) and chemical contaminants. Sediment characterization results from below the dredging limits would be indicative of sediment quality that would remain after dredging. Sediment characterization results from the dredging zone would be indicative of the material to be used as fill elsewhere in the park or requiring disposal. The estimated cost for dredging the lagoon is $230,000. This cost estimate assumes that dredged sediment would be disposed of on-site in the lawn area to the south of the lagoon. Historically, this area reportedly drains poorly, and the dredged sediments could be used as fill to provide more slope to the area to promote better drainage. If off-site disposal at a landfill is required due to lack of opportunity to re-use the material as on-site fill, or due to elevated contaminant concentrations, the estimated cost for sediment disposal is approximately $760,000. If disposal is required, the dredging prism would likely be reduced in depth and size so as to reduce dredging and disposal costs Upper/Lower Lagoon Reconnection Improvement of the upper/lower lagoon connection channel is not expected to have substantial benefit to juvenile salmonids because the lower lagoon will provide adequate habitat for juvenile salmon entering the lagoon from the Narrows, and little or no salmon spawning is believed to occur in the streams feeding the upper lagoon. Figure 3-4 provides a concept for reconnection of the upper and lower lagoon. The sill elevation of the existing wood weir would be maintained at the same elevation, but the new channel would be broader and have a natural gravel/cobble substrate. The estimated cost for the reconnection channel is $130,000. Due to the wider channel, the rate of water flow between the lagoons would be substantially increased compared to the present condition. The upper lagoon would drain and fill faster than at present; however, the minimum water level in the upper lagoon would not change. Due to the higher rates of flow between the lagoons, water in the upper lagoon would be more saline than at present. Combining the effects of the enlarged channel with the new fish passage structure (which would increase tidal exchange between the Narrows and the lower lagoon) would further intensify these effects. The upper lagoon currently has some salt tolerant vegetation. After construction of the new fish passage and re-connection channel, an increase in salt tolerant vegetation, along with a corresponding decrease in non-salt tolerant vegetation, can be expected. January (01/0202) 3-3
4
5 Parametrix 0 DATE: Dec 01, 2009 N SCALE IN FEET 200 Figure 3-1 Beach Restoration Concept Titlow Park Tacoma, Washington
6
7 Parametrix DATE: Dec 04, 2009 N SCALE IN FEET Water Dredging Zone Salt Marsh Tidal Channel Upland Source: Site Workshop 12/03/09 Figure 3-2 Lagoon Restoration Concept Titlow Park Tacoma, Washington
8
9
10
11
12
Solutions to Flooding on Pescadero Creek Road
Hydrology Hydraulics Geomorphology Design Field Services Photo courtesy Half Moon Bay Review Solutions to Flooding on Pescadero Creek Road Prepared for: San Mateo County Resource Conservation District
More information-- Lessons from a successful salmon stream and estuary relocation on Gravina Island
Re-inventing Government Creek -- Lessons from a successful salmon stream and estuary relocation on Gravina Island Jon Houghton, Ph.D. and Derek Ormerod, M.S., P.E. - Pentec Environmental/Hart Crowser,
More informationConnecticut Coastal Management Program
Connecticut Coastal Management Program Fact Sheet for SHORELINE FLOOD AND EROSION CONTROL STRUCTURES What are Shoreline Flood and Erosion Control Structures? The Connecticut General Statutes (CGS) define
More informationShoreline and Climate Change Adaptation Alternatives for The Letter Parcel, Bolinas Lagoon
Shoreline and Climate Change Adaptation Alternatives for The Letter Parcel, Bolinas Lagoon Scenic shoreline vista of Bolinas Lagoon and ridges, from Letter Parcel, March 2016 Peter Baye, Coastal Ecologist
More informationSediment Management in the Coastal Bays
Sediment Management in the Coastal Bays Introduction Need for ecosystem view of sediment management in Coastal Bays Island loss and restoration Navigation needs Habitat Trade offs Living Shoreline Requirements
More informationAppendix I. Dredged Volume Estimates. Draft Contractor Document: Subject to Continuing Agency Review
Appendix I Dredged Volume Estimates Draft Contractor Document: Subject to Continuing Agency Review Interoffice Correspondence Date: April 6, 2007 To: L. Bossi (WHI) Copy: S. Thompson (WHI), B. Fidler (NNJ)
More informationPlanning for the Future of Humboldt Bay: Sea Level Rise, Sediment Management, Sand Spits and Salt Marshes. Joel Gerwein
Planning for the Future of Humboldt Bay: Sea Level Rise, Sediment Management, Sand Spits and Salt Marshes Joel Gerwein Introduction to Humboldt Bay Setting Economy, community, and environment Sediment
More informationMaterials. Use materials meeting the following.
208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting
More informationElwha River response to dam removals through four years and a big flood:
Elwha River response to dam removals through four years and a big flood: Lessons learned, channel response, and sediment effects from the world s largest engineered dam removal Andy Ritchie NPS Elwha Restoration
More informationAnnual transport rates at two locations on the fore-slope.
Sediment Transport by Currents Fore-slope Sediment transport rates and sediment concentrations were computed from the hydrodynamic model runs as well as from direct measurements of current velocities at
More informationIntroduction. Methods. Keyword: Bulkhead, Armoring, Thurston County, SRFB, Forage Fish
Bulkheading in Thurston County: Impacts on Forage Fish Spawning Habitat José Carrasquero-Verde (jcarrasquero@herrerainc.com), Tim Abbe (tabbe@herrerainc.com), Herrera Environmental Consultants Steven Morrison
More informationPuget Sound Shorelines. Announcements
Announcements Puget Sound Shorelines Wednesday discussion of Bates paper Bham Bay project: Updates, finals week schedules Last portion of the class: Environmental issues in Puget Sound Puget Sound shorelines:
More informationHighland Lake Bathymetric Survey
Highland Lake Bathymetric Survey Final Report, Prepared For: The Town of Highland Lake 612 Lakeshore Drive Oneonta, AL 35121 Prepared By: Tetra Tech 2110 Powers Ferry Road SE Suite 202 Atlanta, GA 30339
More informationCarmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018
Carmel River Bank Stabilization at Rancho San Carlos Road Project Description and Work Plan March 2018 EXISTING CONDITION The proposed Carmel River Bank Stabilization at Rancho San Carlos Road Project
More informationCarbon Sequestration Potential from Coastal Wetlands Restoration Sites
Carbon Sequestration Potential from Coastal Wetlands Restoration Sites Insert then choose Picture select your picture. Right click your picture and Send to back. Paul Krause, Alyssa Beach Emily Cooper,
More informationRegional Sediment Management
Regional Sediment Management Linda S. Lillycrop Program Manager Coastal Engineer US Army Engineer Research and Development Center Coastal and Hydraulics Laboratory Q AVG Coastal Resilience: The Environmental,
More informationSummary of Hydraulic and Sediment-transport. Analysis of Residual Sediment: Alternatives for the San Clemente Dam Removal/Retrofit Project,
Appendix N SUMMARY OF HYDRAULIC AND SEDIMENT-TRANSPORT ANALYSIS OF RESIDUAL SEDIMENT: ALTERNATIVES FOR THE SAN CLEMENTE DAM REMOVAL/RETROFIT PROJECT, CALIFORNIA the San Clemente Dam Removal/Retrofit Project,
More informationTHIN-LAYER PLACEMENT OF DREDGE MATERIAL FOR MARSH NOURISHMENT, RESOTRATION, AND RESPONSE TO SEA LEVEL RISE
THIN-LAYER PLACEMENT OF DREDGE MATERIAL FOR MARSH NOURISHMENT, RESOTRATION, AND RESPONSE TO SEA LEVEL RISE Case studies and lesson learned regarding thin-layer deposition projects in Delaware, New Jersey,
More informationRelatively little hard substrate occurs naturally in the
CHAPTER FIVE Rock Habitats Relatively little hard substrate occurs naturally in the estuary, owing mainly to the vast quantities of fine sediment that have been deposited by the rivers. Rock habitat is
More informationEAGLES NEST AND PIASA ISLANDS
EAGLES NEST AND PIASA ISLANDS HABITAT REHABILITATION AND ENHANCEMENT PROJECT MADISON AND JERSEY COUNTIES, ILLINOIS ENVIRONMENTAL MANAGEMENT PROGRAM ST. LOUIS DISTRICT FACT SHEET I. LOCATION The proposed
More informationTom Ballestero University of New Hampshire. 1 May 2013
Tom Ballestero University of New Hampshire 1 May 2013 1 Hydrology 2 Basic Hydrology Low flows most common Flows that fill the stream to the banks and higher are much less common Filling the stream to the
More information3.6 GEOLOGY AND SOILS
3.6 GEOLOGY AND SOILS This section of the EIR examines the regional and local geologic and soil characteristics of the project site and surrounding area. For the lagoon enhancement component, the analysis
More informationIllinois State Water Survey Division
Illinois State Water Survey Division SURFACE WATER SECTION SWS Contract Report 413 AT THE UNIVERSITY OF ILLINOIS SEDIMENTATION SURVEY OF DAWSON LAKE, MORAINE VIEW STATE PARK, MC LEAN COUNTY, ILLINOIS by
More informationIn-channel coarse sediment trap Best Management Practice
In-channel coarse sediment trap Best Management Practice By Henry R. Hudson July 2002 Environmental Management Associates Ltd., Christchurch Complexity Environmental Value Cost Low Moderate High Low Moderate
More informationIsland Design. UMRS EMP Regional Workshop. Presentation for the
Island Design Presentation for the UMRS EMP Regional Workshop by Jon Hendrickson Hydraulic Engineer Regional Technical Specialist, Water Quality and Habitat Restoration August 17 19, 2005 Project Delivery
More informationRedwood City Harbor, California, Navigation Improvement Feasibility Study. Appendix D. Geotechnical Engineering. DRAFT April 2015
1 Redwood City Harbor, California, Navigation Improvement Feasibility Study Appendix D Geotechnical Engineering DRAFT April 2015 2 Contents 1 Purposes of Report... 3 2 Background... 3 3 References and
More informationAppendix E: Cowardin Classification Coding System
Appendix E: Cowardin Classification Coding System The following summarizes the Cowardin classification coding system and the letters and numbers used to define the USFWS NWI wetland types and subtypes:
More informationFlood and Stream Restoration
2 3 4 Pedestrian bridge under construction 3 CSPs perched on DS side Large area of sand deposition Bottom layer of gabions has been scoured out large bar of gabion stone Gabions slumping bank slope failure
More informationDel Mar Sediment Management Study
Del Mar Sediment Management Study Shoreline Preservation Working Group, June 7, 2018 Lindsey Sheehan Current work in Del Mar 2016 Sea-Level Rise Vulnerability Assessment 2018 Adaptation Plan 2018 Sediment
More informationAppendix F Channel Grade Control Structures
Stream Simulation Appendix F Channel Grade Control Structures This appendix briefly describes permanent grade control structures that are sometimes needed in the upstream and/or downstream reaches adjacent
More informationENGINEERING APPROACHES TO SHORELINE PLACEMENT FROM COAST TO COAST
ENGINEERING APPROACHES TO SHORELINE PLACEMENT FROM COAST TO COAST 237 237 237 217 217 217 200 200 200 0 0 0 163 163 163 131 132 122 80 119 27 252 174.59 83 36 118 110 135 120 112 92 56 62 102 130 Comparing
More information3.0 ROBERTS BANK TIDAL FLAT MORPHOLOGY
Vancouver Port Authority Northwest Hydraulic Consultants Ltd. /Triton Consultants Ltd. Roberts Bank Container Expansion File: 33863 Coastal Geomorphology Study - 19 - November 2004 3.0 ROBERTS BANK TIDAL
More informationLower South Fork McKenzie River Floodplain Enhancement Project
Lower South Fork McKenzie River Floodplain Enhancement Project McKenzie River Ranger District Willamette National Forest Project Location The project is located in the South Fork McKenzie River Watershed,
More informationDam Removal Analysis Guidelines for Sediment
A review of: Dam Removal Analysis Guidelines for Sediment Joe Rathbun (Retired) rathbunj@sbcglobal.net Some Potential Sediment Issues Reservoir restoration Downstream water quality Downstream deposition
More informationTom Glass, B.S. Whitman College Sarah Wasssmund, B.S. Humboldt State University Edgar Verdin, B.S. Portland State University Kelsi Lakey, B.S.
Tom Glass, B.S. Whitman College Sarah Wasssmund, B.S. Humboldt State University Edgar Verdin, B.S. Portland State University Kelsi Lakey, B.S. Washington State University Overview 1. Background 2. History
More informationCR AAO Bridge. Dead River Flood & Natural Channel Design. Mitch Koetje Water Resources Division UP District
CR AAO Bridge Dead River Flood & Natural Channel Design Mitch Koetje Water Resources Division UP District Old County Road AAO Bridge Map courtesy of Marquette County Silver Lake Basin McClure Basin
More informationHeather Schlosser Army Corps of Engineers Coastal Studies Group August 28, 2008
Got sand? Regional Sediment Management in Orange County Heather Schlosser Army Corps of Engineers Coastal Studies Group August 28, 2008 Regional Sediment Management Regional sediment management recognizes
More informationArmoring on Puget Sound: Progress towards a better baseline
Western Washington University Western CEDAR Salish Sea Ecosystem Conference 2016 Salish Sea Ecosystem Conference (Vancouver, BC) Armoring on Puget Sound: Progress towards a better baseline Hugh Shipman
More informationFluvial Driven Alluvial Fans
Fluvial Driven Alluvial Fans Restoration Project Evaluations - Examples from the Russian and Napa River Watersheds Mia Docto Masters Thesis UC Berkeley 1. Basic Fan Description 2. Fluvial Driven Fan Characteristics
More informationSediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.
Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff
More informationWhy Geomorphology for Fish Passage
Channel Morphology - Stream Crossing Interactions An Overview Michael Love Michael Love & Associates mlove@h2odesigns.com (707) 476-8938 Why Geomorphology for Fish Passage 1. Understand the Scale of the
More informationCase Study 2: Twenty-mile Creek Rock Fords
Case Study : Twenty-mile Creek Rock Fords Location Crossing Description Washington. Okanagan National Forest. Methow Valley Ranger District. Chewuch river basin, East Chewuch Road. The Twenty-mile Creek
More informationAssignment 1. Measuring River Characteristics- Vernon Creek. Applied Fluvial Geomorphology Field Techniques EESc 435
Assignment 1 Measuring River Characteristics- Vernon Creek Applied Fluvial Geomorphology Field Techniques EESc 435 Amanda Jardine 30100093 Jaime McDonald 14177083 Erica Massey 50870088 April 28, 2012 Introduction
More informationChapter Five. Synopsis
Chapter Five Synopsis .0 Proposed Level Assessments. Prioritization of Level Assessments. Recommended Level P Locations.3 Level RAPP Locations 5 & Mosley Creek & RA.0 Proposed Level Assessments Based on
More informationSunset Harbour / Huntington Harbour Maintenance Dredging and Waterline Installation Project. CMANC 21 January 2016
Sunset Harbour / Huntington Harbour Maintenance Dredging and Waterline Installation Project CMANC 21 January 2016 County of Orange Footprint Huntington Harbour Operational and Dredging Cost Sharing Agreements
More informationFish Passage at Road Crossings
Fish Passage at Road Crossings 1 Crossing Design Workshop Outline 1:00 to 2:00 Intro, Design Overview, Channel Width 2:00 to 2:15 Break 2:15 to 3:15 No-Slope, Stream Simulation Design 3:15 to 3:30 Break
More informationBetsy Stevenson and Allison Mohrs (Skagit County Planning and Development Services) Jenny Baker, The Nature Conservancy
TC Fisher Slough Final Design and Permitting Subject: Well Review Memorandum To: From: Betsy Stevenson and Allison Mohrs (Skagit County Planning and Development Services) Jenny Baker, The ature Conservancy
More informationOpportunities to Improve Ecological Functions of Floodplains and Reduce Flood Risk along Major Rivers in the Puget Sound Basin
Opportunities to Improve Ecological Functions of Floodplains and Reduce Flood Risk along Major Rivers in the Puget Sound Basin Christopher Konrad, US Geological Survey Tim Beechie, NOAA Fisheries Managing
More informationUpper Mississippi River Basin Environmental Management Program Workshop
Presentation to the Upper Mississippi River Basin Environmental Management Program Workshop by Michael Rodgers River Engineer US Army Corps of Engineers, St. Louis District August 17, 2007 Engineering
More informationFour Mile Run Levee Corridor Stream Restoration
Four Mile Run Levee Corridor Stream Restoration 30% Design Summary U.S. Army Corps of Engineers, Baltimore District Presentation Outline Four Mile Run 1.) Historic Perspective 2.) Existing Conditions 3.)
More informationDelaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes
City of New Castle Presentation Delaware Bay Dikes Repair and Prevention Project Preliminary Design for New Castle Dikes New Castle Conservation District DNREC August 22, 2012 Agenda Project Background
More informationPTM: A Lagrangian Particle Tracking Model. Joseph Gailani
PTM: A Lagrangian Particle Tracking Model Joseph Gailani Joe.Z.Gailani@usace.army.mil OUTLINE Motivation for sediment/constituent modeling system Objectives of modeling system Description of PTM PTM Example
More informationAPPENDIX H SAN DIEGUITO LAGOON W-19 INLET AND OCEAN ENTRANCE MAINTENANCE STUDY
APPENDIX H SAN DIEGUITO LAGOON W-19 INLET AND OCEAN ENTRANCE MAINTENANCE STUDY San Dieguito Lagoon W-19 Restoration Project Final EIR November 2018 Appendices 3780 Kilroy Airport Way, Suite 600 Long Beach,
More informationDETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6.
DETAILED DESCRIPTION OF STREAM CONDITIONS AND HABITAT TYPES IN REACH 4, REACH 5 AND REACH 6. The Eklutna River was divided into study reaches (figure 1) prior to this site visit. Prominent geologic or
More informationBob Van Dolah. Marine Resources Research Institute South Carolina Department of Natural Resources
Bob Van Dolah Marine Resources Research Institute South Carolina Department of Natural Resources Shoreline Change Will Occur! On our front beaches where it is not easy to retreat Shoreline Change Will
More informationC. STUDENT FIELD DATA SHEETS
C. STUDENT FIELD DATA SHEETS Student Name Date Time Stream Location Parameter to find Your Group s Results Units trial trial average Transparency cm Water Temperature Air Temperature Weather N sunny N
More informationStabilization Study. Prepared For: The Town of Bethlehem. Henry Hudson Park Shoreline Stabilization Study. June 2011
Henry Hudson Park Shoreline Stabilization Study Prepared For: The Town of Bethlehem 1 Company Introduction - OCC Ocean and Coastal Consultants (OCC) is a 50 person engineering consulting firm that specializes
More informationProject (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report No.2
MEMORANDUM TO: FROM: Jim Well, Ducks Unlimited Mike Harvey, PhD, PG SUBJECT: M&T/ Llano Seco Fish Screen Project (Project No. US-CA-62-2) Maintenance Inspection and Reports (Subtask 14.1) Inspection Report
More informationEXISTING CONDITIONS : EAST SEGMENT
EXISTING CONDITIONS : Area of Natural and Interest (ANSI) Environmentally Waterfront Trail Wetlands Hazard Setback Dunes Private Shoreline road ends Unsafe shoreline access Waterfront Trail on route FISH
More informationAssessment. Assessment
2001 SPRINGBROOK CREEK RESTORATION - THREE YEAR POST-CONSTRUCTION REVIEW - Presented by Bruce Henderson and Andy Harris 2005 River Restoration Northwest Symposium Skamania Lodge, Washington www.hendersonlandservices.com
More informationMaterial Workshop. Galveston District 2012 Beneficial Use of Dredged. Material Workshop. Custodians of the Coast
Galveston District 2012 Beneficial Use of Dredged Material Workshop Galveston District 2012 Beneficial Use of Dredged Material Workshop US Army Corps of Engineers BUILDING STRONG Welcome Opening Remarks
More informationStream Simulation: A Simple Example
Stream Simulation: A Simple Example North Thompson Creek, CO Paul T. Anderson U.S.D.A. Forest Service Here s How We Started May 2011 2-1 USDA-Forest Service Here s How We Finished Forest Service Aquatic
More informationGENERAL SUMMARY BIG WOOD RIVER GEOMORPHIC ASSESSMENT BLAINE COUNTY, IDAHO
GENERAL SUMMARY BIG WOOD RIVER GEOMORPHIC ASSESSMENT BLAINE COUNTY, IDAHO Prepared For Trout Unlimited 300 North Main Street, Hailey, Idaho, 83333 Prepared By P. O. Box 8578, 140 E. Broadway, Suite 23,
More informationPrimer on Coastal Erosion And Habitat Creation
2 nd Regional Conference Dredging, Beach Nourishment & Bird Conservation Primer on Coastal Erosion And Habitat Creation Timothy Kana Ph.D Source: Newsday 1962 Photo by Kelsey Aerials 1978 Source: U Mass
More informationPort of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project
2014 WEDA ENVIRONMENTAL EXCELLENCE AWARDS Category: Navigation Dredging Port of Kalama, 2013 TEMCO Berth Maintenance Dredging and In-water Flow-Lane Placement Project Port of Kalama, Washington 18 April
More informationCCR Rule Annual Inspection Report (cont.) 2
The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that
More informationSubcommittee on Sedimentation Draft Sediment Analysis Guidelines for Dam Removal
Subcommittee on Sedimentation Draft Sediment Analysis Guidelines for Dam Removal August 4, 2011 Jennifer Bountry, M.S., P.E. Tim Randle, M.S., P.E., D.WRE. Blair Greimann, Ph.D., P.E. Sedimentation and
More informationStream Restoration and Environmental River Mechanics. Objectives. Pierre Y. Julien. 1. Peligre Dam in Haiti (deforestation)
Stream Restoration and Environmental River Mechanics Pierre Y. Julien Malaysia 2004 Objectives Brief overview of environmental river mechanics and stream restoration: 1. Typical problems in environmental
More informationALTERNATIVES TO BULKHEADS IN THE PUGET SOUND REGION: WHAT IS SOFT SHORE PROTECTION? WHAT IS NOT? Jim Johannessen MS, Coastal Geologic Services, Inc.
Coasts at the Millennium Proceedings of the 17th International Conference of The Coastal Society, Portland, OR USA ALTERNATIVES TO BULKHEADS IN THE PUGET SOUND REGION: WHAT IS SOFT SHORE PROTECTION? WHAT
More informationEnvironmental Value. Low Moderate High
Boulder Clusters by Craig Fischenich and Rebecca Seal February Complexity Environmental Value Cost Low Moderate High Low Moderate High Low Moderate High OVERVIEW Boulder clusters are groups of large rocks
More informationRegional-scale understanding of the geologic character and sand resources of the Atlantic inner continental shelf, Maine to Virginia
Regional-scale understanding of the geologic character and sand resources of the Atlantic inner continental shelf, Maine to Virginia Workshop on Dredging, Beach Nourishment and Bird Conservation Atlantic
More informationGeneralized Conceptual Models Wetlands Regional Monitoring Program Compiled for the PEEIR
1 Generalized Conceptual Models Wetlands Regional Monitoring Program 2002 Compiled for the PEEIR 2 1. MANAGEMENT QUESTIONS DRIVE INDICATOR DEVELOPMENT The overarching wetland management questions are:
More information3.12 Geology and Topography Affected Environment
3 Affected Environment and Environmental Consequences 3.12 Geology and Topography 3.12.1 Affected Environment 3.12.1.1 Earthquakes Sterling Highway MP 45 60 Project Draft SEIS The Kenai Peninsula is predisposed
More informationLittle Swan Lake. Dam Inspection & Siltation Study Prepared By: William Klingner, P.E., CFM October 28, 2018
Little Swan Lake Dam Inspection & Siltation Study Prepared By: William Klingner, P.E., CFM October 28, 2018 Agenda Little Swan Lake Dam Inspection Theoretical Little Swan Lake Siltation Rate Calculations
More informationAPPENDIX E. GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2013
APPENDIX E GEOMORPHOLOGICAL MONTORING REPORT Prepared by Steve Vrooman, Keystone Restoration Ecology September 2 Introduction Keystone Restoration Ecology (KRE) conducted geomorphological monitoring in
More informationAppendix D Geotechnical
USACE JACKSONVIE DISTRICT Appendix D Geotechnical LEE COUNTY GASPARIA SHORE PROTECTION PROJECT 934 REPORT June 216 TABLE OF CONTENTS 1 Background... 1 1.1 Regional Geology... 1 1.2 Local Geology... 2 2
More informationBishopville Prong Study
Bathymetric and Sediment Assessment in the Bishopville Prong of St. Martin River Darlene V. Wells, Richard A. Ortt, Jr., and Stephen Van Ryswick Funded by MCBP 2011-2012 Implementation Grant Objectives
More informationEAST PASS UP-DATE SUMMARY OF FINDINGS REPORT and INLET MANAGEMENT IMPLEMENTATION PLAN
EAST PASS 2013 UP-DATE SUMMARY OF FINDINGS REPORT and INLET MANAGEMENT IMPLEMENTATION PLAN Introduction On June 8, 2000, the Florida Department of Environmental Protection adopted the East Pass Inlet Management
More informationDesign and Construction
Design and Construction Stream Simulation With power point slides shamelessly stolen from: Forest Service AOP Training Course Bob Gubernick Paul Anderson John Kattell USDA Forest Service Interim Directive
More informationTwo-Dimensional. Modeling and Analysis of Spawning Bed Mobilization Lower American River. October 2001
Two-Dimensional Modeling and Analysis of Spawning Bed Mobilization Lower American River October 2001 Prepared for: Sacramento District U.S. Army Corps of Engineers TABLE OF CONTENTS SECTION 1 MAIN REPORT
More informationAppendix K.2: Sediment Management Excerpt from South Orange County Hydromodification Management Plan
Appendix K.2: Sediment Management Excerpt from South Orange County Hydromodification Management Plan 4 Sediment Supply Management Requirements Permit Order R9-2013-0001 as amended by Order No. R9-2015-0001Section
More informationLower Snake River Programmatic Sediment Management Plan Final Environmental Impact Statement
U.S. Army Corps of Engineers Walla Walla District Lower Snake River Programmatic Sediment Management Plan Final Environmental Impact Statement EXECUTIVE SUMMARY August 2014 EXECUTIVE SUMMARY Introduction
More informationEstimating Stream Gradient Using NHD Stream Lines and DEM Data
Estimating Stream Gradient Using NHD Stream Lines and DEM Data David Nagel, John M. Buffington, and Daniel Isaak U.S. Forest Service, Rocky Mountain Research Station Boise Aquatic Sciences Lab Boise, ID
More informationWhat is weathering and how does it change Earth s surface? Answer the question using
7 th Grade Lesson What is weathering and how does it change Earth s surface? Answer the question using the sentence frame. You have 4 minutes. Weathering is. This changes the Earth s surface because. 1
More informationSessom Creek Sand Bar Removal HCP Task 5.4.6
Sessom Creek Sand Bar Removal HCP Task 5.4.6 Prepared by: Dr. Thomas Hardy Texas State University Dr. Nolan Raphelt Texas Water Development Board January 6, 2013 DRAFT 1 Introduction The confluence of
More informationBest Management Practices for Coldwater Fisheries Enhancement and Restoration
Best Management Practices for Coldwater Fisheries Enhancement and Restoration MACC Annual Environmental Conference 2017 March 3, 2017 Tim Dexter, MassDOT Highway Division 1 Leading the Nation in Transportation
More informationRAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION
RAILWAYS AND FISH: HOW TO PROTECT AND ENHANCE FISH HABITAT VALUES AT STREAM CROSSINGS THROUGH PROJECT DESIGN AND CONSTRUCTION Rail Environment Conference November 2016 AGENDA Objective Background Benefits
More informationDepositional Environment
Depositional Environment Sedimentary depositional environment describes the combination of physical, chemical and biological processes associated with the deposition of a particular type of sediment. Types
More informationAnderson-Ketron PSDDA Disposal Site Fate and Transport Modeling
Pierce County Washington Anderson-Ketron PSDDA Disposal Site Fate and Transport Modeling Design Memorandum September 2014 Table of Contents 1 Introduction... 3 1.1 Purpose and Scope... 3 1.2 Project Description:
More informationSediment Distribution and Characteristics
Sediment Distribution and Characteristics Sediments at the bottom of ponds are a source or sink for nutrients in relation to the water column, contribute to turbidity during storm events, serve as the
More informationSnead Pond Restoration
Snead Pond Restoration Project overview Location: Crewe, VA Date of Project: Summer 2016 Scope of work: Construction of check dam & hydraulic dredging of 530 cubic yards of in situ sediment utilizing geotubes
More informationSeagrass Transplantation & Environmental & Marine Consulting Services, Inc. Drew Campbell, Vice President & Lead Scientst.
Indian River Lagoon Symposium Seagrass Transplantation & Project Considerations Environmental & Marine Consulting Services, Inc. Drew Campbell, Vice President & Lead Scientst March 26 th, 2013 Regulatory
More informationOyster Reef for Shoreline Stabilization and Restoration. Jason Kirkpatrick Conservation Program Manager MacDill AFB Tampa, Florida
Oyster Reef for Shoreline Stabilization and Restoration Jason Kirkpatrick Conservation Program Manager MacDill AFB Tampa, Florida Interbay Penninsula Port of Tampa X The few remaining mangroves are being
More informationIN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION
IN SITU SPECIFIC GRAVITY VS GRAIN SIZE: A BETTER METHOD TO ESTIMATE NEW WORK DREDGING PRODUCTION Nancy Case O Bourke, PE 1, Gregory L. Hartman, PE 2 and Paul Fuglevand, PE 3 ABSTRACT In-situ specific gravity
More information1.0 INSPECTION ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER PROJECT, CARMACKS, YUKON. Dear Mr. West-Sells,
Doc. No. 162 Rev. 0 Mr. Paul West-Sells President & Chief Operating Officer Western Copper Corporation 2060-1111 West Georgia Street Vancouver, BC V6E 4M3 ANNUAL INSPECTION, JUNE 29, 2011 CARMACKS COPPER
More informationHISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)
HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:
More information5.5 GEOLOGY/SOILS EXISTING CONDITIONS. Regulatory Setting
5.5 GEOLOGY/SOILS This section describes existing environmental conditions related to geology and soils in the project area, including W-19, the disposal site, and beach placement sites proposed as part
More informationSELBY CREEK STREAM HABITAT RESTORATION AND RIPARIAN REVEGETATION PROJECT: GEOMORPHIC ANALYSIS AND REVIEW
SELBY CREEK STREAM HABITAT RESTORATION AND RIPARIAN REVEGETATION PROJECT: GEOMORPHIC ANALYSIS AND REVIEW Submitted to Bioengineering Institute P.O. Box 1554 Laytonville, CA 95454 By Matthew O Connor, PhD,
More informationCOASTAL SEDIMENT BUDGET FOR JUPITER INLET, FLORIDA
COASTAL SEDIMENT BUDGET FOR JUPITER INLET, FLORIDA By KRISTEN MARIE ODRONIEC A THESIS PRESENTED TO THE GRADUATE SCHOOL OF THE UNIVERSITY OF FLORIDA IN PARTIAL FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE
More informationRestoring the Napa River:
Restoring the Napa River: lessons learned from a long term private-public project Andy Collison Environmental Science Associates acollison@esassoc.com 1 Napa River Restoration Projects Rutherford Reach
More information