Austindo Resources Corporation N.L.

Size: px
Start display at page:

Download "Austindo Resources Corporation N.L."

Transcription

1 Austindo Resources Corporation N.L. QUARTERLY REPORT: Three months ending 31 December 2006 MAJOR POINTS Cibaliung Gold Project Indonesia Construction of the Gold Processing Plant by PT Petrosea Tbk is approximately 75% complete and advancing in accordance with schedule; The Decline Development Contract has been terminated. The decline contractor will extract the Roadheader and demobilise at its own cost. Discussions are taking place with an alternate contractor which is presently on site undertaking an investigation of ground conditions; Both the remedial work and the consequent delay in the development of the decline have already had a significant cost impact on the project. The targeted first gold pour of May 2007 will not be achieved - the Company is continuing its analysis of the likely schedule and cost impacts on the project; The Company has commenced a detailed review of the existing mine plan including a review of the decline support methodology and is considering in conjunction with external consultants, an alternate mine plan. Progress on the decline is presently suspended pending the removal of the Roadheader by the decline contractor; The Company is seeking additional debt and equity financing. Conditional bank approval for a further US$5m in debt has been obtained. Completion of the equity raising is important to ensure that the Cibaliung project adheres to schedule. Project Generation - Indonesia Surface work continued at several prospects on the Trenggalek Project during the quarter; Fieldwork at Pekalongan in Central Java continued at a significantly reduced level during the quarter; A 4000 m drilling program testing for porphyry targets neared completion at the Aisasjur Project in Papua in which ARX holds a 20% joint venture interest. Expenditure Total exploration and development expenditure in Indonesia during the quarter amounted to A$14.9 million.

2 CIBALIUNG GOLD PROJECT INDONESIA (89.75% as at 31 Dec 2005) The Cibaliung Gold Project is operated by PT. Cibaliung Sumberdaya, a joint venture company established between the Company and PT. Antam Tbk ( Antam ). Cibaliung is located in Banten Province near the western tip of the island of Java, 150km south west of Jakarta. The Company s interest in the Cibaliung Project as at 31 December 2005 stood at 89.75%. Site Development and Erection of Gold Processing Plant At the date of this report the status of the plant is as follows: Site access roads and bridges have been essentially completed Re-erection of the gold processing plant on site is well advanced Installation of CIL tanks and Thickener Tank have been completed Cyanide mixing tank installed SAG Mill installation is in progress Foundations for crusher 70% complete Foundations for Power Plant have been completed Construction of Elution Circuit and Gold Room Plant completed by Como in Western Australian and currently in transit to site. Foundations are in progress Tailings Dam construction survey is in progress and earthworks have commenced Gold Processing Plant under construction at Cibaliung ARX - December 06 Quarter Activity Report doc Page 2 of 10

3 Capital Expenditure and Funding The Company has previously reported details of capital cost increases in the order of US$18.5 million. These cost increases have related primarily to an initial underestimate in the process plant re-erection cost, a re-rating of seismic factors throughout the region, poorer than expected ground conditions in the process plant area and additional costs associated with construction, engineering, earthworks, steelwork and process plant foundations. In addition costs increases have been incurred in the areas of project delivery, finance costs, dewatering, travel, geotechnical, site preparation, equipment, transport and camp costs. The project is continuing to experience significant cost pressure, primarily associated with the difficulties encountered in the development of the decline. As reported below decline development to date remains unsatisfactory. The Company is continuing negotiations in respect of additional debt and additional equity finance to complete the development of the Cibaliung Gold Project. To date the Company has fully drawn the original ANZ Bank primary debt facility of US$26 million. The ANZ Bank has provided an offer for an additional debt facility in the amount of US$5 million. There are a number of pre-conditions associated with this facility including a requirement to restructure the existing hedging arrangements with the ANZ Bank and a requirement that the Company raise sufficient equity funds to complete the project development before the additional debt funds will become available. Currently the Company has hedged 185,000 ounces of gold on a fixed flat (par) forward basis at a price US$651/oz. Specifically the Company will have to restructure at least the first delivery obligation which arises in June Taking into account cost increases identified to date and the continuing cost pressure associated with the development of the decline, it is envisaged that the Company will need to raise additional equity in the order of US$20 million to complete the development of the Cibaliung Gold Project. The Company has arranged a Bridging Facility in the amount of US$5 million which has been provided by PT Austindo Nusantara Jaya, AuSelect Limited, Mr. Hermani Soeprapto (Chief Operating Officer) and Mr. John Carlile (Non-Executive Director). Notice has been given to draw down this facility. Further details in relation to project costs and funding arrangements for the Cibaliung Gold Project will be provided as details are finalised. Decline Development The Company reported the status of the Decline Development on 17 January For ease of reference, key sections of that report are reproduced below. The Company has previously reported that the development of the decline had been slow due to a variety of reasons including:- delayed mobilisation of the contractor to site; adverse ground conditions initially necessitating the erection of steel sets in order to properly support the opening; the sticky nature of the material encountered has had the effect of clogging the roadheader s conveyor system; ARX - December 06 Quarter Activity Report doc Page 3 of 10

4 insufficient skilled labour and supervision to achieve efficient operations; a large deformation had occurred at approximately the 70m mark resulting in a blockage of the decline; remedial work to clear the blockage of the decline has been more extensive than anticipated. 19 steel sets have been placed from the 65m mark to the 82m mark; voids have been encountered which have required filling with cement; large sections of the decline floor have required concreting; The remedial work has now extended beyond the 82m mark and the rear conveyor of the roadheader has been located. It has now been confirmed that the roadheader has been buried by the collapse of material around it The Decline Development Contract has been terminated. The decline contractor will extract the Roadheader and demobilise at its own cost. Progress on the decline is presently suspended pending the removal of the Roadheader by the decline contractor. Discussions are taking place with an alternate contractor which is presently on site undertaking an investigation of ground conditions; A large open void has been identified above the roadheader. As a result remedial work on the decline was suspended on 14 January 2007 while plans for safely dealing with the void are developed with the safety of personnel uppermost in mind. The safety of employees and contractors engaged in this remedial work remains of the highest priority. If the Company pursues the development of the existing decline, it is expected that the remedial work could be completed by mid March 2007 following which, under the present mine plan, the decline will need to be advanced by a further 1,300m. As a result the previously targeted first gold pour of May 2007 will not be achieved. A revised target date will be determined once a complete review of development options, including a review of the decline support methodology, has been undertaken. An alternate mine plan is being investigated by the Company in conjunction with external consultants. While there are many factors impacting upon the first gold pour date, a key factor remains the date at which the ore body is accessed. Until the review of development options has been completed the Company is presently unable to be more definitive about the proposed first gold pour date. Both the remedial work and the consequent delay in the development of the decline have already had a significant cost impact on the project. The Company is continuing its analysis of the likely cost impact and further guidance will be released to the market when some certainty is achieved in this regard. However completion of the equity raising is important to ensure that the Cibaliung project adheres to schedule. Alternate Mining Plan to achieve earlier gold production The Company is continuing to investigate an alternate mining plan which may enable earlier access to ore bodies so that first gold pour may be accelerated. The plan is based on the development of an alternative decline to access ore which can then be mined by hand held methods. Under the plan development would continue to the main ore body from where mechanised mining could commence. Pursuant to this plan ore would be stockpiled to permit gold production to commence at the earliest opportunity and to then ARX - December 06 Quarter Activity Report doc Page 4 of 10

5 continue at a limited rate until such time as the decline has been sufficiently developed to permit continuous mining at the originally anticipated rate of 220,000 tonnes per annum. Subject to confirming the plan s technical merit, the Company anticipates that this plan will generate revenue for the Company from gold sales at an earlier date while the development of the decline continues. Implementation of the plan will require approval from ANZ Bank as the project financier. While this plan, if adopted, may result in an earlier first gold pour date, the amount of ore to be processed will be limited and likely to be at a relatively low grade. At best, it is anticipated that this plan could see limited production achieved by the end of the second quarter of Expenditure Expenditure in relation to development of the Cibaliung Gold Project totalled A$14.5 million during the quarter. Cibaliung Exploration Last quarter it was announced that scout diamond drilling had commenced on the testing of several vein targets located within 2 km of the Cibaliung mine development area. The program was completed during this quarter with an additional three holes drilled (AC-124 to AC-126). This brings a cumulative total of 1,795 m completed in 15 holes for the entire program. These holes have tested the Ramada, Rorah Kadal, Cijagen, Cikamancing and Ilalang veins. Gold and silver assay results were received from all of the holes completed in the program. The best mineralised intersections from each hole are tabulated at the end of this report. As reported in the previous quarter, an intersection of 2.4 m (true-width) at 5.4 g/t Au and 45 g/t Ag, was returned in AC-118 on the Rorah Kadal vein. This intersection was interpreted to be a shallow up-plunge projection of a higher grade shoot within the Rorah Kadal vein. The plunge on this shoot appeared to be steep to the southeast and so two deep holes, AC-124 & AC-125, were drilled to test this interpretation. Both holes intersected the Rorah Kadal vein but returned only low-grade gold and silver intersections. This is not unusual at Cibaliung ARX - December 06 Quarter Activity Report doc Page 5 of 10

6 where the two known ore-shoots, Cikoneng and Cibitung, are enclosed by a low-grade vein structure. The plunge on the higher-grade mineralisation within the Rorah Kadal vein may still be open at a shallower angle and requires further drill testing. AC-126, drilled about 300 m north of the Cikoneng ore-shoot, intersected a barren 20 cm wide calcite beneath a 30 m thick sequence of younger volcanic cover rock. This narrow vein intersection occurs on a prominent geophysical resistivity and magnetic break, and is interpreted to lie on the northern strike-projection of the Cikoneng and Cibitung ore-shoot host-structure. Widespread argillic alteration surrounding this narrow calcite vein indicates that it may be a high-level expression of a deeper, mineralised vein target. Indeed, there is significant potential for the discovery of additional ore-shoots both down-plunge and along the strike of the Cibaliung host-structure because it is largely underexplored outside of the mine development area. Also reported in the previous quarter was encouraging drill intersections obtained from the initial testing of a +400 m long, MMI-soil gold anomaly over the northern strike projection of the Ramada vein. Narrow mineralised vein intersections were returned in three holes, AC- 114, AC-116 and AC-117 (see table of intersections), which confirmed the strike projection of the Ramada vein beneath shallow cover rocks. Follow-up work has included further prospecting due south of the MMI soil anomaly, which has confirmed the presence of relatively high-grade vein float shedding from the conglomeratic base of the cover rock sequence. Two float samples taken during the quarter assayed 8.1 and 30.3 ppm Au, respectively. The source of this float is uncertain but may be another vein located close to and parallel to Ramada and beneath the cover. A program of MMI soil sampling is planned to evaluate this area. The northern of the MMI soil anomaly is open and requires further evaluation. ARX - December 06 Quarter Activity Report doc Page 6 of 10

7 Table of Best Mineralised Intersections Cibaliung Exploration Hole ID Vein From (m) To (m) Interval (m) Au g/t Ag g/t Core Recovery True Width (m) AC-112 Ramada % 0.6 AC-113 Ramada NSR AC-114 Ramada % 0.3 AC-115 Ramada NSR AC-116 Ramada % 0.9 AC-117 Ramada % % 0.5 AC-118 Rorah Kadal 91.7 Incl/ % % 1.1 AC-119 Cijagen NSR AC-120 Cijagen NSR AC-121 Cijagen NSR AC-122 Cikamancing AC-123 Cikamancing NSR NSR AC-124 Rorah Kadal Incl/ % % 5.1 AC-125 Rorah Kadal % 0.25 NSR no significant gold or silver results (<1 g/t) Expenditure Expenditure in relation to Cibaliung Exploration totalled A$260,000. ARX - December 06 Quarter Activity Report doc Page 7 of 10

8 PROJECT GENERATION INDONESIA Java Total Expenditure for exploration completed on the Trenggalek and Pekalongan projects totalled A$142,000 during the quarter. Trenggalek Project, East Java (ARX 95%) The Trenggalek KP exploration area in East Java covers 17,586 ha. Surface work continued at several prospects on the Trenggalek Project during the quarter. Geological mapping and prospecting have helped identify further mineralised float on the Paces prospect, including three grab samples of vein float assaying 3.8, 5.9 and 57 ppm Au respectively. These samples were found on a ridge located on the western side of the prospect. As reported previously, the area containing the moderate to high grade vein float is about one kilometre-square and the float is believed to be sourced from thick soil-covered ridges. Soil sampling has so far failed to clearly define the potential bedrock sources. Trenching is planned to evaluate the ridges in the next quarter. Further mapping undertaken at Dalangturu and the Jati prospect, located east of Paces, has extended the previously known distribution of hot spring-related epithermal features such as silicified eruption breccia, mineralised vein-stockwork and silica sinter. This is further confirmation that these prospects, in particular, have potential for high-level preservation of high-grade lode systems at depth and perhaps stockwork and hydrothermal breccia targets nearer to surface. All three of these prospects, including the mineralised vein system reported at the Sentul Prospect in the previous quarter, lay within forestry production areas. A permit is awaited from the Department of Forestry, which will allow access in these areas to do trenching and scout diamond drilling in the first or second quarter of ARX - December 06 Quarter Activity Report doc Page 8 of 10

9 Pekalongan Project, Central Java (ARX 95%) The Pekalongan KP exploration area in Central Java covers 5,618 ha. Fieldwork continued at a significantly reduced level during the quarter due to the shift of work priorities to the other projects. A ground magnetics and soil geochemical survey is planned for the next quarter to investigate prospective structures extending for 3 to 4 km between the Kuning and Mudal prospects. As previously reported, the Kuning Prospect contains widespread gold anomalies associated with silicified fracture zones, whilst the Mudal Prospect is highlighted by mercury anomalies associated with silicified eruption breccias and possible silica sinters located at about m higher elevation than Kuning. The main prospects lay within forestry production areas. A permit is also awaited from the Department of Forestry, which will allow access in these areas to do more extensive trenching and plan a scout diamond drilling program if results justify. Papua Aisasjur Project - Anglo Strategic Alliance (ARX 20%) The Company has a strategic alliance with the Anglo American Group to explore for large copper/gold porphyry deposits in Papua. The Company has a 20% joint venture interest in the Aisasjur Project while the Anglo American Group has the obligation to fund all exploration activities pursuant to the terms of the strategic alliance. The Aisasjur Project covers an area of 9,486 hectares in the Kepala Burung area of Papua. Geologically, the project area lies within one of Indonesia s young Tertiary volcano- plutonic arcs and is prospective for both porphyry copper-gold and epithermal gold mineralisation styles. Last quarter it was announced that a 4000 m drilling program had commenced testing of porphyry targets on the Aisasjur Project. This drilling program is nearing completion. Results will be reported once all assays are received and fully evaluated by Anglo America Group, the operator of the project. ARX - December 06 Quarter Activity Report doc Page 9 of 10

10 The information in this report that relates to Exploration Results is based on information compiled by Mr. Brad Wake, who is a member of the Australian Institute of Geoscientists. Mr. Wake has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Wake consents to the inclusion in this report of the matters based on his information in the form and context in which it appears. ABOUT AUSTINDO RESOURCES CORPORATION NL (ARX) Formed in 1983, Austindo Resources Corporation NL is an Australian listed gold company focused on developing projects in Indonesia. The company s key project is Cibaliung, a high-grade epithermal gold/silver vein system located southwest of Jakarta in Banten Province, western Java. Cibaliung is expected to produce at an annual rate of 70,000 oz (gold equivalent) with an average life of mine cash operating costs of approximately US$215 per ounce. Two key strategic alliances in Indonesia are taking Austindo closer to achieving its growth objective. In association with Anglo American Group, the Company is exploring for large porphyry copper/gold deposits in Papua. In addition the Company has a 95% joint venture interest with PT Sumber Mineral Nusantara in the Pekalongan and Trenggalek tenements located in Central and East Java respectively, areas prospective for low sulphidation epithermal gold/silver deposits similar to the Cibaliung project. BOARD OF DIRECTORS Bruce Watson Chairman George Tahija Non-Executive Director John Carlile Non-Executive Director Christopher Melloy Non-Executive Director For further information please contact: Andrew J. Cooke Company Secretary Tel: andrewcooke@arx.net.au ARX - December 06 Quarter Activity Report doc Page 10 of 10

Austindo Resources Corporation NL. March 2008 Quarter Activities Report

Austindo Resources Corporation NL. March 2008 Quarter Activities Report Austindo Resources Corporation NL March 2008 Quarter Activities Report ABOUT AUSTINDO Formed in 1983, Austindo Resources Corporation NL (ASX Code: ARX) is an Australian listed gold company focused on developing

More information

December 2017 Quarter Activities Report

December 2017 Quarter Activities Report December 2017 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Arc Exploration Limited (ASX Code: ARX) is an Australian-listed company focused on gold and base metal exploration in Indonesia and

More information

March 2009 Quarter Activities Report

March 2009 Quarter Activities Report March 2009 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Cibaliung Gold Project Indonesia Formed in 1983, Arc Exploration Limited (ASX Code: ARX) is an Australian listed gold company focused

More information

March 2012 Quarter Activities Report

March 2012 Quarter Activities Report March 2012 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Formed in 1983, Arc Exploration Limited (ASX Code: ARX) is an Australian listed gold company focused on exploration in Indonesia. The

More information

SUMBA EXPLORATION UPDATE

SUMBA EXPLORATION UPDATE ASX RELEASE Tuesday, 23 November 2010 SUMBA EXPLORATION UPDATE Hillgrove Resources Limited (ASX:HGO) today announces a planned airborne geophysical survey, Pelitalira prospect progress and final results

More information

The Manager Companies ASX Limited 20 Bridge Street

The Manager Companies ASX Limited 20 Bridge Street ABN 79 106 879 690 10 July 2012 The Manager Companies ASX Limited 20 Bridge Street SYDNEY NSW 2000 (5 pages by email) Dear Madam, 1.54 Moz Gold Equivalent Maiden Gold/Copper Resource at Wonogiri The Directors

More information

King of the Hills Gold Project, Leonora, to commence production in Q2 2011

King of the Hills Gold Project, Leonora, to commence production in Q2 2011 King of the Hills Gold Project, Leonora, to commence production in Q2 2011 St Barbara is pleased to announce the King of the Hills gold project near Leonora (formerly referred to as the Tarmoola higher

More information

High Grade Gold Intercepts at Bangaba

High Grade Gold Intercepts at Bangaba 20th March 2012 ASX Announcement High Grade Gold Intercepts at Bangaba Level 2, 9 Colin Street West Perth WA 6005 ABN 11 127 171 877 p (08) 9216 1000 f (08) 9481 7939 w www.predictivediscovery.com e info@predictivediscovery.com

More information

TRENCHING CONFIRMS HIGH GRADE GOLD AT SUMBA

TRENCHING CONFIRMS HIGH GRADE GOLD AT SUMBA Thursday, 10 December 2009 TRENCHING CONFIRMS HIGH GRADE GOLD AT SUMBA Work has highlighted high grade gold in trenches in the Western Vein system at the Pahandanjal Prospect, with multiple veins striking

More information

September 2011 Quarter Activities Report

September 2011 Quarter Activities Report September 2011 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Formed in 1983, Arc Exploration Limited (ASX Code: ARX) is an Australian listed gold company focused on exploration in Indonesia.

More information

For personal use only

For personal use only BOARD OF DIRECTORS Mr Oscar Aamodt Non-Executive Chairman Ms Sofia Bianchi Non-Executive Director Mr Lindsay Dudfield Non-Executive Director Mr Anthony Ho Non-Executive Director ISSUED CAPITAL SHARES 156,852,955

More information

SUMBA EPITHERMAL GOLD SYSTEM

SUMBA EPITHERMAL GOLD SYSTEM Monday, 7 September 2009 Highlights: SUMBA EPITHERMAL GOLD SYSTEM On ground exploration has recommenced targeting drilling in early 2010. Compilation of exploration work completed by BHP has outlined a

More information

CORPORATE UPDATE. Feasibility Study being finalised for completion towards the end of April.

CORPORATE UPDATE. Feasibility Study being finalised for completion towards the end of April. 16 March 2018 Company Announcement Officer ASX Limited 20 Bridge Street SYDNEY NSW 2000 Highlights CORPORATE UPDATE Inaugural Bowdens Reserve Statement due early April. Feasibility Study being finalised

More information

For personal use only

For personal use only ABN 79 106 879 690 7 October 2011 The Manager Companies ASX Limited 20 Bridge Street SYDNEY NSW 2000 (6 pages by email) Dear Madam, Multiple zones intersected including 123 metres at 0.61 g/t Gold and

More information

HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT

HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT The Manager ASX Company Announcements PO Box H224, Australia Square Sydney NSW 2001 22 December 2010 HIGH-GRADE GOLD MINERALISATION CONTINUES ALONG STRIKE AT THE BODDINGTON SOUTH GOLD PROJECT New true-width

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 8 October 2012 FRESH REVIEW OF HIGH GRADE GOLD LODES ON BATANGAS PROJECT SOUTH OF MANILA A new review of available data on high grade epithermal gold lodes including beneath an historic

More information

December 2011 Quarter Activities Report

December 2011 Quarter Activities Report December 011 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Arc Exploration Limited (ASX Code: ARX) is an Australian listed gold company focused on exploration in Indonesia. The Company has a

More information

For personal use only

For personal use only 10 July 2012 Encouraging New Gold Results from Gunung Rosa Drilling Highlights Assay results from three drill holes at depth under the Cap Palu section confirm significantly wider intercepts of gold-copper-base

More information

For personal use only

For personal use only Wednesday, 13 June 2012 STRONG DRILLING RESULTS FROM INDONESIA Hillgrove Resources Limited (ASX:HGO) is pleased to announce results from its ongoing drilling operations at the Karipi Prospect, Sumba and

More information

ASX ANNOUNCEMENT 21 MARCH 2011

ASX ANNOUNCEMENT 21 MARCH 2011 ASX ANNOUNCEMENT 21 MARCH 2011 Sihayo Pungkut Gold Project New JORC Compliant Estimate Sihayo Resource increases 43% to 1.30 Million ounces, total project resources grow to 1.4 million ounces Highlights

More information

For personal use only

For personal use only ASX RELEASE 13 July 2012 ASX Code: PMQ Encouraging Field Exploration Results: Mount Borium Gold Project Key Points Third phase of field exploration underway the Company has been highly active since the

More information

Drilling Program Commences on Iron Oxide Copper Gold Targets

Drilling Program Commences on Iron Oxide Copper Gold Targets 3 June 2008 Manager Company Announcements Company Announcements Office Australian Stock Exchange Limited Level 10, 20 Bond Street SYDNEY NSW 2000 ABN 42 082 593 235 Electronic delivery No of pages: 6 Drilling

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 29 July 2011 KATANNING UPDATE GOLD DISCOVERED AT JACKSON First-pass drilling at Jackson confirms presence of primary gold mineralisation Potential for third ore body at the Katanning Gold

More information

September 2010 Quarter Activities Report

September 2010 Quarter Activities Report September 2010 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Formed in 1983, Arc Exploration Limited (ASX Code: ARX) is an Australian listed gold company focused on exploration in Indonesia.

More information

ASX Announcements & Media Release

ASX Announcements & Media Release ASX Announcements & Media Release October 15, 2010 Fast Facts ASX Code: RNS Shares on issue: 62.2 million Cash at bank: $5 million (Sept 2010) Board & Management Rick Hart, Chairman Justin Tremain, Managing

More information

Quarterly Activities Report For the Period Ended March HIGHLIGHTS

Quarterly Activities Report For the Period Ended March HIGHLIGHTS Quarterly Activities Report For the Period Ended March 31 2008 HIGHLIGHTS Merceditas Project, Chile Genesis Minerals Limited secured an Option to acquire a 100% interest in the significant Merceditas copper

More information

MARCH 2012 QUARTERLY REPORT. Highlights. Exploration Activities. Wyloo Iron Ore & Gold Project. Fast Facts

MARCH 2012 QUARTERLY REPORT. Highlights. Exploration Activities. Wyloo Iron Ore & Gold Project. Fast Facts MARCH 2012 QUARTERLY REPORT Highlights Magnetic and radiometric survey acquired for Wyloo Anomalous gold zones identified at Wyloo from desktop study Ongoing exploration program completed at Wyloo Application

More information

Mundo Minerals Limited

Mundo Minerals Limited Mundo Minerals Limited Stock Exchange Announcement 10 September 2007 Spectacular RAB Drilling Results From Tocantins 1 metre intersection averaging 242.2 g/t from 6 metres below surface. Further enhances

More information

SILVER CITY MINERALS LIMITED ABN Silver City Minerals

SILVER CITY MINERALS LIMITED ABN Silver City Minerals ABN 68 130 933 309 ASX Code: SCI Silver City Minerals Annual General Meeting 20 November 2014 SILVER CITY MINERALS SNAPSHOT BROKEN HILL (Ag-Pb-Zn) Project Review and Prioritization: Focus and Plan Razorback

More information

For personal use only

For personal use only ASX ANNOUNCEMENT ASX: IVG Date: 30 April 2012 Number: 030_300412 MARCH 2012 QUARTERLY REPORT SUMMARY Market Cap A$2.23m ($0.062 p/s) Issued Capital 36,006,006 Assay data and mineral alteration studies

More information

For personal use only

For personal use only About Convergent ASX Code: CVG CVG owns 100% of the Bounty Goldfield in Western Australia with 872,000 ounces of gold Our Aim CVG s key objective is to define high grade gold and to recommence gold production

More information

Hits of up to 123gpt show Chesterfield emerging as a high grade gold project

Hits of up to 123gpt show Chesterfield emerging as a high grade gold project ASX ANNOUNCEMENT 22 August 2013 General Mining Corporation ABN: 95 125 721 075 Hits of up to 123gpt show Chesterfield emerging as a high grade gold project Prospects are ideally located close to existing

More information

For personal use only

For personal use only Niuminco Group Suite 50, 14 Narabang Way, Austlink Corporate Centre, Belrose NSW 2085, Australia Tel: (02) 9450 0828 Fax: (02) 9450 0877 Email: info@niuminco.com.au ABN 44 009 163 919 QUARTERLY ACTIVITIES

More information

For personal use only

For personal use only ASX Release 28 March 2013 VOYAGER RESOURCES LIMITED ACN 076 390 451 Level 1 / 33 Richardson Street WEST PERTH Australia Tel: +61 8 9200 6264 Fax: +61 8 9200 4469 Contact: Joe Burke (Chief Executive Officer)

More information

For personal use only

For personal use only Quarterly Activities Report September 2013 Equus Mining Limited (ASX: EQE) is pleased to report on its exploration activities in Chile, South America, and corporate developments for the quarter ended 30

More information

GEOPHYSICAL SURVEYING COMMENCES AT ESK TROUGH

GEOPHYSICAL SURVEYING COMMENCES AT ESK TROUGH ADDRESS PHONE PO Box 6965 +61(07) 5592 1001 Gold Coast Mail Centre FAX Qld 9726 Australia +61 (07) 5592 1011 EMAIL ABN 54 126 490 855 info@coppermoly.com.au WEBSITE www.coppermoly.com.au ASX Announcement

More information

HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA

HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA ASX Release 13 AUGUST 2009 HERON ENTERS OPTION TO PURCHASE A1 GOLD MINE, EASTERN VICTORIA Heron Resources Limited (ASX:HRR, Heron) is pleased to announce it has purchased an Option (Option) to acquire

More information

KINGSTON RESOURCES LIMITED

KINGSTON RESOURCES LIMITED KINGSTON RESOURCES LIMITED ASX Announcement 26 September 2018 ASX Code: KSN Share Price: A$0.022 Shares Outstanding: 1,223,198,383 Market Capitalisation: A$26.9m Cash: A$4.4m (30 June 2018) Visible gold

More information

ASX Announcement. 28 January Drill results indicate large Porphyry Copper Gold System at Peenam

ASX Announcement. 28 January Drill results indicate large Porphyry Copper Gold System at Peenam ASX Announcement 28 January 2010 Drill results indicate large Porphyry Copper Gold System at Peenam Highlights: 270 metres of visible copper (gold) mineralisation in first diamond core hole at Peenam Prospect

More information

Chalice, Higginsville Drilling

Chalice, Higginsville Drilling Chalice, Higginsville Drilling 31 May 2006 Eastern Goldfields Higginsville Chalice First results from Chalice Gold Mines Limited s (Chalice Gold Mines or Company) drilling program have been received. Chalice

More information

For personal use only

For personal use only 2 May 2013 No. of Pages: 7 ASX CODE: ORS Market Cap.: $12.2 m ($0.115 p/s) Shares on issue: 106,048,002 Cash: $2.4 m (31 March 2013) BOARD & MANAGEMENT Ian Gandel, Chairman Anthony Gray, Managing Director

More information

GEOPACIFIC REPORTS HIGH GOLD VALUES IN AUGER SOIL SAMPLES FROM THE QALAU AND TATAIYA PROSPECTS, RAKI RAKI PROJECT,

GEOPACIFIC REPORTS HIGH GOLD VALUES IN AUGER SOIL SAMPLES FROM THE QALAU AND TATAIYA PROSPECTS, RAKI RAKI PROJECT, 20 June 2008 Companies Announcement Office Via Electronic Lodgement GEOPACIFIC REPORTS HIGH GOLD VALUES IN AUGER SOIL SAMPLES FROM THE QALAU AND TATAIYA PROSPECTS, RAKI RAKI PROJECT, Fiji. (Geopacific

More information

EXPLORATION UPDATE: BODDINGTON SOUTH GOLD PROJECT AND DOOLGUNNA STATION PROJECT

EXPLORATION UPDATE: BODDINGTON SOUTH GOLD PROJECT AND DOOLGUNNA STATION PROJECT The Manager ASX Company Announcements PO Box H224, Australia Square Sydney NSW 2001 20 September 2010 EXPLORATION UPDATE: BODDINGTON SOUTH GOLD PROJECT AND DOOLGUNNA STATION PROJECT Boddington South Gold

More information

New Drilling Program Commences at Mutiny s Deflector Deposit

New Drilling Program Commences at Mutiny s Deflector Deposit New Drilling Program Commences at Mutiny s Deflector Deposit Drilling Program Highlights 12,000 metre RC and diamond drilling program underway New drilling program targets strike extensions in the Northern

More information

March 2016 Quarter Activities Report

March 2016 Quarter Activities Report March 2016 Quarter Activities Report ABOUT ARC EXPLORATION LIMITED Arc Exploration Limited (ASX Code: ARX) is an Australian-listed company focused on gold and base metal exploration in Indonesia and Australia.

More information

SUMBA GOLD MINERALISATION EXPANDED

SUMBA GOLD MINERALISATION EXPANDED Wednesday, 21 January 2009 SUMBA GOLD MINERALISATION EXPANDED (ASX: HGO) is pleased to announce that further gold mineralisation has been identified on the Sumba license (Kuasa Pertambangan, KP ) (Hillgrove

More information

INAUGURAL FARM IN DRILL RESULTS AT CALARIE PROJECT

INAUGURAL FARM IN DRILL RESULTS AT CALARIE PROJECT March 1, 2012 INAUGURAL FARM IN DRILL RESULTS AT CALARIE PROJECT TriAusMin Limited (ASX: TRO) (TSX: TOR) ( TriAusMin or the Company ) is pleased to present the attached announcement of drill results by

More information

For personal use only

For personal use only Alloy Regains Control of the Horse Well Gold Project ASX Release 29 January 2018 Capital Structure ABN 20 109 361 195 ASX Code AYR Issued Shares 1,266,993,360 Unlisted Options 29,000,000 Corporate Directory

More information

ASX Announcement NAKRU DRILLING AND TRENCHING INTERSECTS 11 METRES AT 2.84 G/T GOLD AND 28.4 METRES AT 1.1% COPPER

ASX Announcement NAKRU DRILLING AND TRENCHING INTERSECTS 11 METRES AT 2.84 G/T GOLD AND 28.4 METRES AT 1.1% COPPER ADDRESS PHONE PO Box 6965 +61(07) 5592 1001 Gold Coast Mail Centre FAX Qld 9726 Australia +61 (07) 5592 1011 EMAIL ABN 54 126 490 855 info@coppermoly.com.au WEBSITE www.coppermoly.com.au ASX Announcement

More information

OYUT ULAAN COPPER GOLD PROJECT RECONNAISSANCE DRILLING RESULTS

OYUT ULAAN COPPER GOLD PROJECT RECONNAISSANCE DRILLING RESULTS ASX / MEDIA RELEASE Manager Company Announcements By Electronic Lodgement 7 pages Company Announcements Office 6 June 2013 Australian Securities Exchange 4th Floor, 20 Bridge Street SYDNEY NSW 2001 OYUT

More information

For personal use only

For personal use only March 22 nd, 2011 ASX & TSX: WSA News Release MUSTANG MINERALS ANNOUNCES NEW PLATINUM AND PALLADIUM DISCOVERY IN MANITOBA Mustang Minerals Corp ( Mustang ) has today announced a potentially significant

More information

FIVE RIGS DRILLING AT KARLAWINDA

FIVE RIGS DRILLING AT KARLAWINDA FIVE RIGS DRILLING AT KARLAWINDA Major resource in-fill and extensional drill program well underway at Karlawinda Gold Project with 88 holes already completed ASX ANNOUNCMENT 2 September 2016 Australian

More information

MINCOR /GOLDEN RIM FIJI JOINT VENTURE SIGNIFICANT NEW EXPLORATION RESULTS

MINCOR /GOLDEN RIM FIJI JOINT VENTURE SIGNIFICANT NEW EXPLORATION RESULTS 1 November 2007 MINCOR /GOLDEN RIM FIJI JOINT VENTURE SIGNIFICANT NEW EXPLORATION RESULTS Highlights Very high gold-in-soil sample results up to 17.3 g/t gold have been received from the Banana Creek Prospect.

More information

High Grade Gold Drill Results Extend Buccaneer

High Grade Gold Drill Results Extend Buccaneer ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 14 June, 2012 High Grade Gold Drill Results Extend 31 metres averaging 3.68g/t gold including 14 metres averaging 7.56g/t gold ABM Resources NL ( ABM or The Company

More information

AURA TO COMMENCE EXPLORATION DRILLING PROGRAM ON ITS TASIAST SOUTH GOLD PROJECT COPPER AND NICKEL PROSPECTS WILL ALSO BE EXPLORED

AURA TO COMMENCE EXPLORATION DRILLING PROGRAM ON ITS TASIAST SOUTH GOLD PROJECT COPPER AND NICKEL PROSPECTS WILL ALSO BE EXPLORED 8 FEBRUARY 2017 AURA TO COMMENCE EXPLORATION DRILLING PROGRAM ON ITS TASIAST SOUTH GOLD PROJECT COPPER AND NICKEL PROSPECTS WILL ALSO BE EXPLORED KEY SHAREHOLDERS HAVE ELECTED EARLY EXCERSISE OF OPTIONS

More information

Annual General Meeting

Annual General Meeting Slide 1 Annual General Meeting 8 November 2010 Slide 2 INVESTMENT HIGHLIGHTS Boddington South Gold Project Located within the Southwest Yilgarn region of Western Australia Gold mineralisation similar to

More information

For personal use only

For personal use only ASX Announcement ASX: ERM ABN: 53 117 086 745 June 18, 2015 Seismic Survey to underpin future gold discoveries at Tennant Creek First application of seismic geophysics to the Tennant Creek Mineral Field

More information

INV METALS ANNOUNCES DRILL RESULTS AT LOMA LARGA AND INITIAL PROSPECTING RESULTS ON NEW REGIONAL PROPERTIES

INV METALS ANNOUNCES DRILL RESULTS AT LOMA LARGA AND INITIAL PROSPECTING RESULTS ON NEW REGIONAL PROPERTIES INV METALS ANNOUNCES DRILL RESULTS AT LOMA LARGA AND INITIAL PROSPECTING RESULTS ON NEW REGIONAL PROPERTIES TORONTO, ON September 18, 2017 INV Metals ( INV Metals or Company ) (TSX: INV) is very pleased

More information

For personal use only

For personal use only 12 September 2012 ASX RELEASE ASX Code: WAC FIRST PASS FIELD WORK COMPLETED AT PERU IOCG TARGETS Site visits and reconnaissance sampling has been completed at the Yauca and Chaparra Iron Oxide Copper Gold

More information

Trouser Legs Mine Strong Drilling Results - including g/t Au Potential for Further Mine Development

Trouser Legs Mine Strong Drilling Results - including g/t Au Potential for Further Mine Development ABN 44 009 157 439 Company Announcement 22 November 2018 Level 2, 90 William St Melbourne Victoria 3000 Australia Telephone: +61 3 9605 5950 Facsimile: +61 3 9605 5999 Email: info@hawthornresources.com

More information

$2.5 Million Resource Drilling Program Commences at Siberia Mining Centre

$2.5 Million Resource Drilling Program Commences at Siberia Mining Centre ASX ANNOUNCEMENT 14 June 2016 $2.5 Million Resource Drilling Program Commences at Siberia Mining Centre Eastern Goldfields Limited (ASX: EGS) (Eastern Goldfields or the Company) is pleased to announce

More information

Highlights. Wa Project. Kandia Prospect. South Wa. Julie West Jang Trend. Corporate

Highlights. Wa Project. Kandia Prospect. South Wa. Julie West Jang Trend. Corporate 29 th July 2010 June December 2010 Quarterly Report Report 2008 Highlights Wa Project Kandia Prospect» RC drilling defines open ended zones of sediment hosted gold mineralisation at the site of the Kandia

More information

STRONG GOLD IN SOIL ANOMALY OUTLINED AT MARY HARRISON PROJECT HIGHLIGHTS

STRONG GOLD IN SOIL ANOMALY OUTLINED AT MARY HARRISON PROJECT HIGHLIGHTS National Stock Exchange of Australia Company Announcements Level 2, 117 Scott Street Newcastle NSW 2300 25 th January 2013 STRONG GOLD IN SOIL ANOMALY OUTLINED AT MARY HARRISON PROJECT HIGHLIGHTS 100m

More information

EXPLORATION LICENCE SURROUNDING THE HISTORIC FALUN COPPER MINE GRANTED

EXPLORATION LICENCE SURROUNDING THE HISTORIC FALUN COPPER MINE GRANTED ASX ANNOUNCEMENT 30 August 2007 EXPLORATION LICENCE SURROUNDING THE HISTORIC FALUN COPPER MINE GRANTED The Drake-Zinifex Alliance application for an exploration licence that covers the historic Falun copper

More information

Bass Metals records further positive drill results & progress at 3 prospects.

Bass Metals records further positive drill results & progress at 3 prospects. 16 March 2011 Bass Metals records further positive drill results & progress at 3 prospects. HIGHLIGHTS: New high-grade drilling intercept confirms Switchback potential; Drilling commences at Lake Margaret

More information

Lake Resources N L, Quarterly Report, January - March 2013 LAKE RESOURCES NL QUARTERLY REPORT JANUARY MARCH 2013

Lake Resources N L, Quarterly Report, January - March 2013 LAKE RESOURCES NL QUARTERLY REPORT JANUARY MARCH 2013 LAKE RESOURCES NL QUARTERLY REPORT JANUARY MARCH 2013 SUMMARY During the quarter ended 31 st March 2013, no exploration work was undertaken in Pakistan pending the granting of new security clearances for

More information

Sipa Resources Limited

Sipa Resources Limited 30 October 2012 Sipa Resources Limited ABN 26 009 448 980 September Quarter 2012 Quarterly ASX Report HIGHLIGHTS The September Quarter, and through October, has seen a very high level of drilling and geophysical

More information

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012

For personal use only OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012 OZ MINERALS CARRAPATEENA COPPER GOLD PROJECT SOUTH AUSTRALIA 27 MARCH 2012 WWW.OZMINERALS.COM DISCLAIMER This presentation has been prepared by OZ Minerals Limited ( OZ Minerals ) and consists of written

More information

Additional significant gold and copper intercepts obtained in Sweden

Additional significant gold and copper intercepts obtained in Sweden 18 November 2009 Additional significant gold and copper intercepts obtained in Sweden Drake Resources (ASX: DRK, Drake ) is pleased to announce that additional significant assays for the drilling programme

More information

******************* *******************

******************* ******************* This announcement lifts the trading halt requested by the Company on the 13 September 2012 Announcement to the Australian Securities Exchange Monday 17 September 2012 COMPANY UPDATE PARTIALLY UNDERWRITTEN

More information

TRENGGALEK BENCHING PROGRAM RESULTS

TRENGGALEK BENCHING PROGRAM RESULTS 26 February 2014 TRENGGALEK BENCHING PROGRAM RESULTS Highlights: First bench results at Singgahan Prospect, Trenggalek, confirm gold-copper-molybdenum anomalism in bedrock beneath soil anomaly; Anomalous

More information

GOULAMINA DRILLING AND GENERAL PROGRESS UPDATE

GOULAMINA DRILLING AND GENERAL PROGRESS UPDATE 21 November 2017 GOULAMINA DRILLING AND GENERAL PROGRESS UPDATE HIGHLIGHTS RC drilling at Danaya and Yando completed. RC drilling at Danaya intersects very wide (>117m) spodumene bearing pegmatite zone.

More information

For personal use only

For personal use only 18 April 2018 ASX Announcement DRILLING UNDERWAY AT SLATE DAM GOLD PROJECT HIGHLIGHTS 2nd Phase Drilling Program underway at Slate Dam - 9 RC holes for ~1,000m completed to date Program designed to expand

More information

ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA

ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA ACQUISITION OF THE MCCLEERY COPPER-COBALT PROJECT, CANADA HIGHLIGHTS New claims staked covering ~9km 2 to secure a 100% interest in the McCleery Copper-Cobalt Project in the Yukon Territory, Canada ABN

More information

RC DRILLING TO RESUME THIS WEEK AT CARLISLE REEFS

RC DRILLING TO RESUME THIS WEEK AT CARLISLE REEFS Magmatic Resources Ltd Level 1, 11 Lucknow Place West Perth WA 6005 Phone: +61 8 6102 2709 www.magmaticresources.com ASX / MEDIA ANNOUNCEMENT 21 August 2017 RC DRILLING TO RESUME THIS WEEK AT CARLISLE

More information

NEW COBAR-STYLE COPPER DISCOVERY IN NSW

NEW COBAR-STYLE COPPER DISCOVERY IN NSW ASX / MEDIA RELEASE 2 AUGUST 2011 NEW COBAR-STYLE COPPER DISCOVERY IN NSW Broad zone of copper-polymetallic mineralisation intersected at 4-Mile prospect Highlights: Wide zone of copper-silver-gold-lead-zinc

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 26 April 2016 QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDING 31 March 2016 ASX: NXM Capital Structure Shares on Issue 70.4 million First Earn-in milestone completed in the Pinnacles JV

More information

JUNE 2013 QUARTERLY ACTIVITY REPORT

JUNE 2013 QUARTERLY ACTIVITY REPORT JUNE QUARTERLY ACTIVITY REPORT The Board of Austral Gold Limited (ASX: AGD) is pleased to report the following update to shareholders for the quarter ended 30 JUNE. Key Highlights The Guanaco Gold Mine

More information

LATEST DRILL RESULTS REVEALS MINERALISATION OPEN AT STRIKE AND DEPTH AT KATANNING GOLD DEPOSIT

LATEST DRILL RESULTS REVEALS MINERALISATION OPEN AT STRIKE AND DEPTH AT KATANNING GOLD DEPOSIT ASX ANNOUNCEMENT 8 March 2011 LATEST DRILL RESULTS REVEALS MINERALISATION OPEN AT STRIKE AND DEPTH AT KATANNING GOLD DEPOSIT New true-width intercepts along strike from Katanning Deposit include: o BSRC0050-10m

More information

ASX announcement. Mylo-Frontier Pilbara Gold Project acquisition. 27 November Summary

ASX announcement. Mylo-Frontier Pilbara Gold Project acquisition. 27 November Summary ASX announcement 27 November 2017 Andromeda Metals Limited ABN: 75 061 503 375 Mylo-Frontier Pilbara Gold Project acquisition Corporate details: Summary ASX Code: ADN Cash: $0.546 million (at 30 June 2017)

More information

Malachite Resources Limited ABN

Malachite Resources Limited ABN Malachite Resources Limited ABN 86 075 63 268 ASX Announcement ASX Code: MAR 27 October 20 NEW DRILLING RESULTS AT LORENA SUPPORT COMMENCEMENT OF MINING FEASIBILITY STUDY Malachite Resources Limited (

More information

102 metres strike length averaging 32.62g/t Gold extends overall surface vein sampling to date to 726 metres strike length averaging 24.

102 metres strike length averaging 32.62g/t Gold extends overall surface vein sampling to date to 726 metres strike length averaging 24. ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 8 th February 2012 Old Pirate Phase 4 Longitudinal Trenching Results for veins on the Western Limb Lodes 102 metres strike length averaging 32.62g/t Gold extends

More information

Significant Copper-Gold JORC Exploration Target

Significant Copper-Gold JORC Exploration Target 12 March 2013 Highlights: ASX & MEDIA ANNOUNCEMENT Significant Copper-Gold JORC Exploration Target ü JORC i Exploration Target 1 of 4.8-6.2Mt @ 2.00-2.78% Cu and 1.23-2.23g/t Au confirmed. ü Opportunity

More information

FIRST RESULTS FROM RC DRILLING AT KONONGO

FIRST RESULTS FROM RC DRILLING AT KONONGO ASX Release Monday 29 March 2010 SIGNATURE METALS LIMITED Level 1 / 33 Richardson Street WEST PERTH Australia Tel: +61 8 9481 0101 Fax: +61 8 9200 4469 FIRST RESULTS FROM RC DRILLING AT KONONGO Signature

More information

New Zone of High Grade Gold Mineralisation Discovered at Balogo, Burkina Faso

New Zone of High Grade Gold Mineralisation Discovered at Balogo, Burkina Faso ASX/Media Announcement 24 May 2013 New Zone of High Grade Gold Mineralisation Discovered at Balogo, Burkina Faso A new zone of high grade gold mineralisation has been discovered 1km NE along strike from

More information

For personal use only

For personal use only Indonesia s leading explorer Investor Presentation October 2013 1 Investment Proposition Copper-gold explorer in Asia Pacific concentrating on high impact epithermal gold and porphyry copper-gold deposits

More information

MARKET UPDATE ON URANIUM AND GOLD PROJECTS

MARKET UPDATE ON URANIUM AND GOLD PROJECTS ASX Announcement 1 March 2011 MARKET UPDATE ON URANIUM AND GOLD PROJECTS HIGHLIGHTS 5,000 metre drilling programme to commence at Rio Puerco uranium project within the next two weeks. Drilling to commence

More information

Norwest successfully lists on ASX, Drilling commenced at Warriedar Gold Project

Norwest successfully lists on ASX, Drilling commenced at Warriedar Gold Project ASX ANNOUNCEMENT 4 December 2018 ASX: NWM Norwest successfully lists on ASX, Drilling commenced at Warriedar Gold Project Norwest Minerals listed on the ASX 29 th November following its successful $6.6

More information

For personal use only

For personal use only ASX/MEDIA ANNOUNCEMENT 16 NOVEMBER 2012 ASX Code: HOR Management Mr Jeremy Shervington Non Executive Chairman Mr Neil Marston Managing Director Mr Michael Fotios Non Executive Director Mr Stuart Hall Non

More information

SITE WORKS COMMENCE AT A1 GOLD MINE, EASTERN VICTORIA

SITE WORKS COMMENCE AT A1 GOLD MINE, EASTERN VICTORIA ASX Release 4 th November 2009 SITE WORKS COMMENCE AT A1 GOLD MINE, EASTERN VICTORIA Heron Resources Limited (ASX:HRR, Heron) is pleased to announce commencement of site works at the A1 Gold Mine in eastern

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 7 March 2012 High Priority Gold Drilling Targets at Marymia Project COMPANY DIRECTORS Mr Ian Tchacos Non-Executive Chairman Mr Bruce Franzen Executive Director HIGHLIGHTS High priority

More information

For personal use only

For personal use only ASX and Media Release 22 June 2018 CÁRMENES COBALT-COPPER PROJECT SPAIN DRILLING APPROVALS GRANTED AND NEW HIGH- PRIORITY TARGETS GENERATED NEAR PROFUNDA COBALT-COPPER MINE ACN 143 042 022 Suite 1, 6 Richardson

More information

For personal use only

For personal use only 17 December 2012 ASX ANNOUNCEMENT Mining at Zeta Pit ASX/BSE: DML MARKET CAPITALISATION Shares on Issue 487m Share Price A$1.62 Market Cap A$789m Cash (7 Dec) US$72.8m Debt (7 Dec) US$205m ABN 29 104 924

More information

For personal use only

For personal use only For personal use only AGM Presentation 2 November 2016 Greg Solomon Chairman 3 Investment in Eden Energy Ltd (ASX:EDE) Tasman holds 493 million shares (42%) in the issued capital of Eden and 101 million

More information

Trial Mining & Processing Update at the Old Pirate High-Grade Gold Project

Trial Mining & Processing Update at the Old Pirate High-Grade Gold Project ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 1st August, 2013 Trial Mining & Processing Update at the Old Pirate High-Grade Gold Project ABM Resources NL ( ABM or The Company ) presents an update on the Trial

More information

For personal use only

For personal use only INTEGRATED RESOURCES GROUP LIMITED REPORT ON ACTIVITIES, MARCH 2012 QUARTER HIGHLIGHTS Announcement of company transforming Maryborough Basin project acquisition, expected to be completed in June 2012.

More information

BUNDARRA RESOURCE UPDATE

BUNDARRA RESOURCE UPDATE t Friday 15 April 2011 Company Announcement ASX ANNOUNCEMENT ASX CODE: TMX, TMXOA CAPITAL STRUCTURE TMX - Shares on Issue 217.98m TMXOA - Options on Issue 18.24m - Unlisted Options 56.81m DIRECTORS & KEY

More information

High Grade Gold Results from RAB Drilling at the Central Bore Prospect

High Grade Gold Results from RAB Drilling at the Central Bore Prospect 16 th July 2009 Company Announcements Office Australian Securities Exchange Level 4 20 Bridge Street SYDNEY NSW 2000 Dear Sir / Madam High Grade Gold Results from RAB Drilling at the Central Bore Prospect

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 8 June 2016 Aeromagnetic Interpretation Identifies Pinnacles Targets ASX: NXM Capital Structure Shares on Issue 70.4 million Unlisted Options 3.5 million Corporate Directory Mr Paul Boyatzis

More information

For personal use only

For personal use only HIGHLIGHTS THIS QUARTER EXPLORATION Very strong zinc-silver-lead (Zn-Ag-Pb) mineralisation confirmed in 2 sampling programs (Program 1 and Program 2) at the Riqueza Project. Two highly prospective Zn-Ag-Pb

More information