1 88th Avenue and Pecos Street Stormwater Drainage Design Report Reeve & Associates, Inc. Solutions You Can Build On for Maverik, Inc. 88th Avenue and Pecos Street Thornton, CO submitted to Reeve & Associates, Inc. Contact: Nate Reeve, PE 920 Chambers Street, Suite 14 Ogden, Utah Fax www. reeve-assoc.com City of Thornton 9500 Civic Center Drive Thornton, CO PH: (303) June 2, 2016 Ref:

2

3

4 Stormwater Drainage Design Report 1.0 Introduction 1.1 Purpose The purpose of this drainage report is to reflect proposed changes to the current drainage patterns associated with the proposed Maverik and subdivision. Proposed changes to the property include construction of a 5,518 sq. ft. Maverik convenience store with fuel pumps and associated utility service connections. The detention basin and associated facilities have been designed for a full build-out scenario. 1.2 General Property Description At the request of Thornton City, Reeve & Associates has prepared the following Storm Drainage Design Report for the proposed Maverik located at 88 th Avenue and Pecos Street in Thornton, Colorado. The site is located in the southeast quarter of section 21, township 2 south, range 68 west. See Figure 1 for a general location map that shows the proposed location and surrounding properties. A private storm sewer system will collect stormwater runoff from the proposed development. The storm sewer system will discharge into a private detention pond located on the eastern side of the property. An outlet pipe from the detention pond will outlet to the public right of way located along the north side of W. 88 th Avenue. The proposed development includes an access road and vacant land for future development. The detention basin and outlet structures are sized for a full buildout scenario for all future developments. 1.3 Pre-developed Drainage Characteristics The existing site is currently undeveloped and consists mostly of dry weeds and sandy loam with the soil type being C/D. The existing runoff from this property is divided into two subbasins (EX-1 and EX-2) but sheet flows primarily from the north to the south and into the curb and gutter on 88 th Avenue as outline in this section and depicted on the predevelopment drainage plan located in the Appendix; with design point Z being the outfall of these existing basins. There is a third drainage basin (EX-3) on the north east corner of the site that sheet flows to the north east and into the Orchard Hill Senior Apartment Complex with design point Y being the outfall of this basin. 4

5 Stormwater Drainage Design Report The property is bordered to the north by residential property to the west by Pecos Street and Water World Amusement Park, to the south by 88 th Ave, and to the east by Orchard Hill Senior Apartments. The pre-developed stormwater runoff leaves the site without the use of engineered quality or detention facilities. 1.4 Post-developed Drainage Characteristics The proposed site will operate as a Maverik Convenience Store with vehicle fueling stations. The entire parcel sits on 6.35 acres. The site will contain 197,154 s.f. of undeveloped area, 54,546 s.f. of hard surface area, 19,880 s.f. of landscaped area and 5,518 s.f. of building area. Note that the detention basin has been sized to accommodate future developments on the site to tie into the detention basin. The proposed grading will divide the site into twelve drainage basins and seven design points as outlined in this section and depicted on the developed drainage plan located in the Appendix. Basin R-1 encompasses 0.43 acres of sidewalk and landscape between the onsite curb and gutter and Pecos Street and W. 88 th Avenue right of way. Stormwater generated in this basin will sheet flow undetained into the curb and gutter within the right-of-way and into the southeast corner of the lot. Basin R-2 encompasses 0.23 acres of sidewalk and landscape between the onsite curb and gutter and W. 88 th Avenue right of way. Stormwater generated in this basin will sheet flow undetained into the curb and gutter within the right-of-way and into the southeast corner of the lot. Basin R-3 encompasses 0.02 acres of asphalt paving on the southeast corner of the lot. Stormwater generated in this basin will sheet flow undetained into the curb and gutter within the right-of-way in W. 88th. Basin R-4 encompasses 0.02 acres of asphalt paving on the northwest corner of the lot. Stormwater generated in this basin will sheet flow undetained into the curb and gutter within the right-of-way on Pecos and follow the curb and gutter to the southeast corner of the lot. Basin B-1 encompasses 0.63 acres of parking and drive aisles of the proposed convenience store. Stormwater generated in this basin will sheet flow to a low point on the curb with an inlet box titled A. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-2 encompasses 0.02 acres of parking and drive aisles of the proposed convenience store. Stormwater generated in this basin will sheet flow to a low 5

6 Stormwater Drainage Design Report point on the curb with an inlet box titled d B. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-3 encompasses 0.14 acres of parking and drive aisles of the proposed convenience store. Stormwater generated in this basin will sheet flow to a low point on curb with an inlet box titled C. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-4 encompasses 0.57 acres of parking and drive aisles, the building and canopy for the proposed convenience store. Stormwater generated in this basin will sheet flow to a low point on curb with an inlet box titled D. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-5 encompasses 0.40 acres of parking and drive aisles, the building and canopy for the proposed convenience store. Stormwater generated in this basin will sheet flow to a low point on curb with an inlet box titled E. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-6 encompasses 0.35 acres of parking and drive aisles, the building and canopy for the proposed convenience store. Stormwater generated in this basin will sheet flow to a low point on curb with an inlet box titled F and G. The water will be conveyed by a private storm sewer system to the private detention pond. Basin B-7 encompasses 0.82 acres of detention pond. This has been sized to detain the 100-year storm event per COT code with an outlet structure and orifice plates for the WQCV, EURV and 100-year storm event. It will be landscaped per COT code. Basin F-1 encompasses 2.73 acres and will be developed at a later date. However, the detention basin design has included this area in a full build-out scenario. Future developments will convey their storm water to the proposed private detention pond. Pipe P1 conveys the stormwater from Basin B-2 from the inlet box B. Pipe P2 conveys the stormwater from Basin B-1 from the inlet box A. This pipe also carries the water from Basin B-2. Pipe P3 conveys the stormwater from Basin B-3 from the inlet box C. Pipe P4 conveys the stormwater from Basin B-4 from the inlet box D. This pipe also carries the water from Basin B-2 and B-1. Pipe P5 conveys the stormwater from B-5 from the inlet box E. This pipe also carries the water from Basin B-4, B-3, B-2 and B-1. 6

7 Stormwater Drainage Design Report Pipe P6 conveys the stormwater from B-6 from the inlet box F. This pipe also carries the water from Basin B-5, B-4, B-3, B-2 and B-1. Pipe P7 also conveys the stormwater from B-6 from the inlet box G. This pipe also carries the water from Basin B-5, B-4, B-3, B-2 and B-1. Ultimately, all storm water runoff from this site is conveyed to the South Platte River. In a fully developed scenario, 1% or cfs and 0.17 cfs will exit the site at each access untreated during the 5-yr and 100-yr storms respectively. The remaining storm water from hard surface areas will be directed to a private detention pond that is sized for the WQCV, EURV and 100-yr volumes. It will release 0.5 cfs and 8.90 cfs into the 88 th Ave right-of-way during the 5-year and 100-year storm events respectively. 1.5 Water Quality A private water quality facility will be provided for the full build-out at this time. Post-development stormwater runoff will be collected via curb and gutter and private combination curb inlets throughout the property. A private storm sewer system will convey storm water flows to the private detention pond facility located along the northeast property line. The detention pond will provide storage for the water quality capture volume of acre-feet or 6,926 c.f. with a water surface elevation of and the EURV storage has also been provided with a volume of acre-feet or 13,765 c.f. with an elevation of An outlet structure within the detention pond will provide water quality and staged release of stored stormwater that meets the City of Thornton Storm Drainage Design requirements. Because the 5-yr, and 100-yr design storm event developed flows are larger than the pre-developed site runoff totals, the detention pond outlet structure also reduces the release rates of the post-developed flows to the pre-developed rates. The pond will provide storage for the 5-yr design storm event and the water quality volume of acre-feet or 21,867 c.f. with a water surface elevation of The pond will also provide storage for the 100-yr, design storm event and the water quality volume of acre-feet or 35,240 c.f. with a water surface elevation of During the 100-yr design storm event, the pond outlet structure will provide a release rate of 8.9 cfs which is less than the predeveloped outflow of 9.7 cfs provided the UD-Detention analysis of the detention pond volume. A private 24 RCP pipe will connect to the outlet structure and release into a sidewalk chase drain and into the curbline along the north side of W. 88 th Avenue. 7

8 Stormwater Drainage Design Report See Hydraulic Calculations located in the Appendix for more details regarding detention pond design. 1.6 Hydrology Calculations The City of Thornton Storm Drainage Design, Grading, and Water Quality Technical Criteria within the City of Thornton Standards and Specifications was used to perform hydrology calculations. The Rational Method has been used to compute storm water runoff, as preferred for drainage areas less than 100-acres. Design storms with the 5-yr, and 100-yr, occurrence intervals were used. Weighted or composite C values for the site were calculated using the following formula. 5-year, and 100-yr, flows for the proposed site are summarized in the Appendix. Table 1 shows a comparison between pre-development discharges and postdevelopment discharges from the project site. Tablie 1: Peak Discharge Comparison Pre-Development Discharge (cfs) Post-Development Discharge (cfs) Discharge Difference (cfs) Q5 Pecos Q100 Pecos Q5 88th Q100 88th NE Corner NE Corner Pipe and inlet capacity calculations were performed at each design point as shown on the drainage plan. Storm sewer for this project was designed to convey the required 10-yr storm even with a surcharge hydraulic grade line not less than one foot below finished grade. Hydrologic and hydraulic calculations are located in the Appendix. All assumptions shall be field verified by the contractor prior to commencing construction, and discrepancies shall be reported to the engineer immediately for review. 8

9 Stormwater Drainage Design Report 1.7 Floodplain Statement According to the Federal Emergency Management Agency (FEMA), as depictured on Flood Insurance Rate Map (FIRM) 08001C0582H with an effective date of March 5, 2007, the site lies within areas determined to be outside the 500- year floodplain. 1.8 Erosion Control It is respectfully requested that an erosion control plan be submitted in conjunction with the final grading plan and not be required to be submitted with this drainage report. 1.9 Summary Developed runoff generated from the project site during the 100-yr. design storm event are anticipated to be less than or equal to the pre-developed runoff rates. Prior to being released off-site, runoff will be treated via a private detention pond and water quality facility, while a small percentage of the site s runoff will discharge (un-detained) to the adjacent right-of-way or adjacent properties. Downstream of the detention pond, a private 24 RCP pipe and sidewalk chase drain will convey treated runoff into the W. 88 th Avenue right of way. A series of private combination inlets will collect runoff in multiple locations on site and convey the runoff to the proposed private detention pond east of the Maverik building. The storm sewer has been designed to handle developed flows in the required 10-yr. design storm event condition within minimal surcharge. Since the site s anticipated developed runoff rate is less than the allowed predevelopment runoff rate, development on this site as described in the enclosed drainage plan is not anticipated to adversely impact downstream stormwater infrastructure. Upon the completion of construction, if conditions or outfall locations differ from the assumptions stated within this drainage study, an amendment to this report must be completed. Maverik Inc. will be responsible for any maintenance on the drainage facilities. 9

10 10 Stormwater Drainage Design Report

11 Stormwater Drainage Design Report APPENDIX 11

12 Stormwater Drainage Design Report Figure 1 Vicinity Map 88 th Avenue and Pecos Street Project Site The project site is located at 88 th Avenue and Pecos Street in Thornton, CO. 12

13 13 Stormwater Drainage Design Report

14 14 Stormwater Drainage Design Report

15 15 Stormwater Drainage Design Report

16 16 Stormwater Drainage Design Report

17 17 Stormwater Drainage Design Report

18 18 Stormwater Drainage Design Report

19 19 Stormwater Drainage Design Report

20 Stormwater Drainage Design Report Allowable Capacity for one-half of Street (Minor & Major) 20

21 21 Stormwater Drainage Design Report

22 22 Stormwater Drainage Design Report

23 23 Stormwater Drainage Design Report

24 24 Stormwater Drainage Design Report

25 25 Stormwater Drainage Design Report

26 26 Stormwater Drainage Design Report

27 27 Stormwater Drainage Design Report

28 28 Stormwater Drainage Design Report

29 DETENTION BASIN STAGE-STORAGE TABLE BUILDER Project: 88th & Pecos Maverik Fueling Station Basin ID: Full Build-Out Detention Basin Depth Increment = 0.1 ft Optional Optional Example Zone Configuration (Retention Pond) Stage - Storage Stage Override Length Width Area Override Area Volume Volume Description (ft) Stage (ft) (ft) (ft) (ft^2) Area (ft^2) (acre) (ft^3) (ac-ft) Required Volume Calculation Media Surface , Selected BMP Type = No BMP Flood Control Only , Watershed Area = 6.35 acres , , Watershed Length = 762 ft , , Watershed Slope = ft/ft , , Watershed Imperviousness = 75.00% percent , , Percentage Hydrologic Soil Group A = 0.0% percent , , Percentage Hydrologic Soil Group B = 15.0% percent , , Percentage Hydrologic Soil Groups C/D = 85.0% percent , , Desired WQCV Drain Time = N/A hours Zone 1 (WQCV) , , Location for 1-hr Rainfall Depths = UDFCD Default , , Water Quality Capture Volume (WQCV) = acre-feet Optional User Input , , Excess Urban Runoff Volume (EURV) = acre-feet 1-hr Precipitation , , yr Runoff Volume (P1 = 0.95 in.) = acre-feet inches , , yr Runoff Volume (P1 = 1.34 in.) = acre-feet inches , , yr Runoff Volume (P1 = 1.64 in.) = acre-feet inches , , yr Runoff Volume (P1 = 2.02 in.) = acre-feet inches , , yr Runoff Volume (P1 = 2.32 in.) = acre-feet inches , , yr Runoff Volume (P1 = 2.61 in.) = acre-feet inches , , yr Runoff Volume (P1 = 3.29 in.) = acre-feet inches , , Approximate 2-yr Detention Volume = acre-feet , , Approximate 5-yr Detention Volume = acre-feet , , Approximate 10-yr Detention Volume = acre-feet , , Approximate 25-yr Detention Volume = acre-feet , , Approximate 50-yr Detention Volume = acre-feet Zone 2 (EURV) , , Approximate 100-yr Detention Volume = acre-feet , , , , Stage-Storage Calculation , , Zone 1 Volume (WQCV) = acre-feet , , Zone 2 Volume (EURV - Zone 1) = acre-feet , , Zone 3 Volume (100-year - Zones 1 & 2) = acre-feet , , Total Detention Basin Volume = acre-feet , , Initial Surcharge Volume (ISV) = N/A ft^ , , Initial Surcharge Depth (ISD) = N/A ft , , Total Available Detention Depth (H total) = 3.39 ft , , Depth of Trickle Channel (H TC) = 0.50 ft , , Slope of Trickle Channel (S TC) = ft/ft Zone 3 (100-year) , , Slopes of Main Basin Sides (S main) = 4 H:V , , Basin Length-to-Width Ratio (R L/W) = , , , , Initial Surcharge Area (A ISV) = 0 ft^ , , Surcharge Volume Length (L ISV) = 0.0 ft , , Surcharge Volume Width (W ISV) = 0.0 ft , , Depth of Basin Floor (H FLOOR) = 0.00 ft , , Length of Basin Floor (L FLOOR) = ft , , Width of Basin Floor (W FLOOR) = 61.8 ft , , Area of Basin Floor (A FLOOR) = 7,649 ft^ , , Volume of Basin Floor (V FLOOR) = 0 ft^ , , Depth of Main Basin (H MAIN) = 3.39 ft , , Length of Main Basin (L MAIN) = ft , , Width of Main Basin (W MAIN) = 89.0 ft , , Area of Main Basin (A MAIN) = 13,416 ft^ , , Volume of Main Basin (V MAIN) = 35,249 ft^ , , Calculated Total Basin Volume (V total) = acre-feet , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , , UD-Detention_v3.02.xlsm, Basin 6/9/2016, 3:32 PM

30 DETENTION BASIN STAGE-STORAGE TABLE BUILDER User Defined Stage-Area Boolean for Message Equal Stage-Area Inputs Watershed L:W 1 CountA 0 Calc_S_TC H_FLOOR L_FLOOR_OTHER Length, Width (ft.) ISV 0.00 ISV 0.00 Floor 0.00 Floor 0.84 Zone 1 (WQCV) 0.84 Zone 1 (WQCV) 2.21 Zone 2 (EURV) 2.21 Zone 2 (EURV) Area (sq.ft.) 3.39 Zone 3 (100-yea 3.39 Zone 3 (100-year) Stage (ft) Length (ft) Width (ft) Area (sq.ft.) Area (acres) Volume (ac-ft) Stage (ft.) Area (acres) Volume (ac-ft) UD-Detention_v3.02.xlsm, Basin 6/9/2016, 3:32 PM

31 Detention Basin Outlet Structure Design Project: 88th & Pecos Maverik Fueling Station Basin ID: Full Build-Out Detention Basin4 Stage (ft) Zone Volume (ac-ft) Outlet Type Zone 1 (WQCV) Orifice Plate Zone 2 (EURV) Orifice Plate Zone 3 (100-year) Weir&Pipe (Circular) Example Zone Configuration (Retention Pond) Total 24 User Input: Orifice at Underdrain Outlet (typically used to drain WQCV in a Filtration BMP) Calculated Parameters for Underdrain Underdrain Orifice Invert Depth = N/A ft (distance below the filtration media surface) Underdrain Orifice Area = N/A ft 2 Underdrain Orifice Diameter = N/A inches Underdrain Orifice Centroid = N/A feet User Input: Orifice Plate with one or more orifices or Elliptical Slot Weir (typically used to drain WQCV and/or EURV in a sedimentation BMP) Calculated Parameters for Plate Invert of Lowest Orifice = 0.00 ft (relative to bottom of basin at Stage = 0 ft) WQ Orifice Area per Row = 2.083E-02 ft 2 Depth at top of Zone using Orifice Plate = 2.21 ft (relative to bottom of basin at Stage = 0 ft) Elliptical Half-Width = N/A feet Orifice Plate: Orifice Vertical Spacing = 8.80 inches Elliptical Slot Centroid = N/A feet Orifice Plate: Orifice Area per Row = 3.00 sq. inches (diameter = 1-15/16 inches) Elliptical Slot Area = N/A ft 2 User Input: Stage and Total Area of Each Orifice Row (numbered from lowest to highest) Row 1 (required) Row 2 (optional) Row 3 (optional) Row 4 (optional) Row 5 (optional) Row 6 (optional) Row 7 (optional) Row 8 (optional) Stage of Orifice Centroid (ft) Orifice Area (sq. inches) Stage of Orifice Centroid (ft) Orifice Area (sq. inches) Row 9 (optional) Row 10 (optional) Row 11 (optional) Row 12 (optional) Row 13 (optional) Row 14 (optional) Row 15 (optional) Row 16 (optional) User Input: Vertical Orifice (Circular or Rectangular) Calculated Parameters for Vertical Orifice Not Selected Not Selected Not Selected Not Selected Invert of Vertical Orifice = N/A N/A ft (relative to bottom of basin at Stage = 0 ft) Vertical Orifice Area = N/A N/A ft 2 Depth at top of Zone using Vertical Orifice = N/A N/A ft (relative to bottom of basin at Stage = 0 ft) Vertical Orifice Centroid = N/A N/A feet Vertical Orifice Diameter = N/A N/A inches User Input: Overflow Weir (Dropbox) and Grate (Flat or Sloped) Calculated Parameters for Overflow Weir Zone 3 Weir Not Selected Zone 3 Weir Not Selected Overflow Weir Front Edge Height, Ho = 2.21 N/A ft (relative to bottom of basin at Stage = 0 ft) Height of Grate Upper Edge, H t = 3.59 N/A feet Overflow Weir Front Edge Length = 2.00 N/A feet Over Flow Weir Slope Length = 5.67 N/A feet Overflow Weir Slope = 4.00 N/A H:V (enter zero for flat grate) Grate Open Area / 100-yr Orifice Area = N/A should be > 4 Horiz. Length of Weir Sides = 5.50 N/A feet Overflow Grate Open Area w/o Debris = 7.94 N/A ft 2 Overflow Grate Open Area % = 70% N/A %, grate open area / total area Overflow Grate Open Area with Debris = 3.97 N/A ft 2 Debris Clogging % = 50% N/A % User Input: Outlet Pipe w/ Flow Restriction Plate (Circular Orifice, Restrictor Plate, or Rectangular Orifice) Calculated Parameters for Outlet Pipe w/ Flow Restriction Plate Zone 3 Circular Not Selected Zone 3 Circular Not Selected Depth to Invert of Outlet Pipe = 3.40 N/A ft (distance below bottom of basin at Stage = 0 ft) Outlet Orifice Area = 0.73 N/A ft 2 Circular Orifice Diameter = N/A inches Outlet Orifice Centroid = 0.48 N/A feet Half-Central Angle of Restrictor Plate on Pipe = N/A N/A radians User Input: Emergency Spillway (Rectangular or Trapezoidal) Calculated Parameters for Spillway Spillway Invert Stage= 4.40 ft (relative to bottom of basin at Stage = 0 ft) Spillway Design Flow Depth= 0.89 feet Spillway Crest Length = 8.00 feet Stage at Top of Freeboard = 6.29 feet Spillway End Slopes = 4.00 H:V Basin Area at Top of Freeboard = 0.45 acres Freeboard above Max Water Surface = 1.00 feet Routed Hydrograph Results Design Storm Return Period = WQCV EURV 2 Year 5 Year 10 Year 25 Year 50 Year 100 Year 500 Year One-Hour Rainfall Depth (in) = Calculated Runoff Volume (acre-ft) = OPTIONAL Override Runoff Volume (acre-ft) = Inflow Hydrograph Volume (acre-ft) = Predevelopment Unit Peak Flow, q (cfs/acre) = Predevelopment Peak Q (cfs) = Peak Inflow Q (cfs) = Peak Outflow Q (cfs) = Ratio Peak Outflow to Predevelopment Q = N/A N/A N/A Structure Controlling Flow = Plate Plate Plate Overflow Grate 1 Overflow Grate 1 Overflow Grate 1 Overflow Grate 1 Outlet Plate 1 Outlet Plate 1 Max Velocity through Grate 1 (fps) = N/A N/A N/A Max Velocity through Grate 2 (fps) = N/A N/A N/A N/A N/A N/A N/A N/A N/A Time to Drain 97% of Inflow Volume (hours) = Time to Drain 99% of Inflow Volume (hours) = Maximum Ponding Depth (ft) = Area at Maximum Ponding Depth (acres) = Maximum Volume Stored (acre-ft) =

32 Detention Basin Outlet Structure Design FLOW [cfs] YR COUNTA IN for Basin Tab = 1 Ao Dia WQ Plate Type Vert Orifice 1 Vert Orifice 2 500YR Count_Underdrain OUT = eter = 3/8 inch) YR INCount_WQPlate = ter = 7/16 inch) 100YR OUT Count_VertOrifice1 = eter = 1/2 inch) Outlet Plate 1 Outlet Plate 2 Drain Time Message Boolean 50YR IN Count_VertOrifice2 = ter = 9/16 inch) 2 1 5yr, <72hr 0 50YR OUT 25YR IN Count_Weir1 = eter = 5/8 inch) >5yr, <120hr 0 25YR OUT Count_Weir2 = er = 11/16 inch) Max Depth Row 10YR Count_OutletPipe1 IN = eter = 3/4 inch) WQCV 77 Watershed Constraint Check 10YR Count_OutletPipe2 OUT = er = 13/16 inch) 2 Year 164 Slope YR IN COUNTA_2 (Standard FSD Setup)= eter = 7/8 inch) EURV 204 Shape YR OUT MaxPondDepth_Error? FALSE 0.67 er = 15/16 inch) 5 Year 233 2YR IN Hidden Parameters & Calculations 0.76 meter = 1 inch) 10 Year 267 Spillway Depth 2YR OUT /16 inches) 25 Year EURV IN WQ Plate Flow at 100yr depth = = 1-1/8 inches) 50 Year 316 EURV OUT CLOG #1= 35% /16 inches) 100 Year Z1_Boolean WQCV IN C dw #1 = = 1-1/4 inches) 500 Year Z2_Boolean WQCV OUT C do #1 = /16 inches) Zone3_Pulldown Message 1 Z3_Boolean Overflow Weir #1 Angle = = 1-3/8 inches) 1 Opening Message CLOG #2= #VALUE! /16 inches) Draintime Running C dw #2 = #VALUE! 1.73 = 1-1/2 inches) Outlet Boolean Outlet Rank Total (1 to 4) C do #2 = #VALUE! /16 inches) Vertical Orifice Overflow Weir #2 Angle = #VALUE! 2.03 = 1-5/8 inches) Vertical Orifice Boolean Underdrain Q at 100yr depth = /16 inches) Overflow Weir Max Depth 0.1 VertOrifice1 Q at 100yr depth = = 1-3/4 inches) Overflow 1 Weir yr Depth 10 VertOrifice2 Q at 100yr depth = /16 inches) TIME [hr] Outlet Pipe Freeboard PONDING DEPTH [ft] EURV_draintime_user = 2.72 = 1-7/8 inches) Outlet Pipe Spillway 4.5 Count_User_Hydrographs /16 inches) 0 Spillway Length 500YR CountA_3 (EURV & 100yr) = eter = 2 inches) Button Visibility Boolean 100YR 4 CountA_4 (100yr Only) = 50YR gular openings) 1 Button_Trigger 0 Underdrain 25YR YR 1 WQCV Plate 5YR 0 EURV-WQCV Plate 3 2YR EURV WQCV 0 EURV-WQCV VertOrifice 1 Outlet 90% Qpeak 0 Outlet Undetained DRAIN TIME [hr] AREA [ft^2], VOLUME [ft^3] User Area [ft^2] Interpolated Area [ft^2] Volume [ft^3] Outflow [cfs] 5, , , , , , , , , OUTFLOW [cfs] PONDING DEPTH [ft]

33 Detention Basin Outlet Structure Design Outflow Hydrograph Workbook Filename: Storm Inflow Hydrographs The user can override the calculated inflow hydrographs from this workbook with inflow hydrographs developed in a separate program. SOURCE WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK WORKBOOK Time Interval TIME WQCV [cfs] EURV [cfs] 2 Year [cfs] 5 Year [cfs] 10 Year [cfs] 25 Year [cfs] 50 Year [cfs] 100 Year [cfs] 500 Year [cfs] 5.19 min 0:00: :05: Hydrograph 0:10: Constant 0:15: :20: :25: :31: :36: :41: :46: :51: :57: :02: :07: :12: :17: :22: :28: :33: :38: :43: :48: :54: :59: :04: :09: :14: :20: :25: :30: :35: :40: :45: :51: :56: :01: :06: :11: :17: :22: :27: :32: :37: :42: :48: :53: :58: :03: :08: :14: :19: :24: :29: :34: :39: :45: :50: :55: :00: :05: :11: :16: :21: :26: :31: :37: :42: :47: :52: :57: :02: :08: :13:

34 Reference Figures and Equations Circular Pipe with Restrictor Plate WQ Elliptical Slot Weir (Alternative to WQ Orifice Plate for Large Watersheds) Watershed Runoff Volume Calculations Where WQCV is the water quality capture volume (acre-ft), EURV is the excess urban runoff volume (acre-ft), V #yr is the volume for the given return period (acre-ft), a is a coefficient corresponding to WQCV drain time (1.0 for 40 hours, 0.9 for 24 hours, and 0.8 for 12 hours), P 1 is the one-hour rainfall depth (in), A is the contributing watershed area (acres), I is the percentage imperviousness (expressed as a decimal), A%, B%, and CD% are the percent of each hydraulic soil group (expressed as a decimal). Initial Surcharge Volume: Basin Volume Calculations Where ISV is the initial surcharge volume (ft 3 ), A ISV is ISV surface area (ft 2 ), ISD is the initial surcharge depth (ft, typically 0.33 to 0.50), and L ISV and W ISV are the length and width of the ISV (ft). Basin Floor Volume: Where L floor and W floor (ft) are the length and width of the basin floor section at the point where the top of the basin floor section meets the toe of the basin main section, H floor is the depth of the basin floor section (ft), S TC is the trickle channel slope (ft/ft), S main is the side slope of the basin main section (H:V; e.g., 4 if the horizontal:vertical ratio is 4:1), R L:W is the basin length:width ratio (e.g., 2 if the basin length is twice the basin width), A floor is top area of the basin floor section (ft 2 ), and V floor is volume of the basin floor section (ft 3 ). Main Basin Volume: Where L main and W main (ft) are the length and width of the main basin section at the point at the top of the basin, H main is the depth of the main basin section (ft), A main is top area of the main basin section (ft 2 ), and V main is volume of the main basin section (ft 3 ). Total Basin Volume: Where V- total is the volume of the total basin (ft 3 ) and D TC is the depth of the trickle channel (ft). UD-Detention_v3.02.xlsm, Reference 6/9/2016, 3:32 PM

35 1 2 6/2/2015 7:10:47 AM A B C D 0" 1" 2" SEAL DATE STATUS DATE REVISION PROJECT NUMBER????? FILE DRAWN BY R. Hansen CHECKED BY J.Nate Reeve, P.E. SCALE As indicated PRE-DEVELOPED DRAINAGE MAP THORNTON MAVERIK 88TH AVENUE & PECOS STREET THORNTON, COLORADO

36 1 2 6/2/2015 7:10:47 AM A B C D 0" 1" 2" SEAL DATE STATUS DATE REVISION PROJECT NUMBER????? FILE DRAWN BY R. Hansen CHECKED BY J.Nate Reeve, P.E. SCALE POST - DEVELOPED DRAINAGE MAP As indicated THORNTON MAVERIK 88TH AVENUE & PECOS STREET THORNTON, COLORADO

37 D 0" 1" 2" US PATENT # ADDITIONAL PATENTS PENDING BMP, INC. 53 MT. ARCHER ROAD, LYME, CT (800) FAX: (860) C 18F SNOUT OIL & DEBRIS STOP 09/14/99 NONE 18F B 36" MIN. *NOTE- SUMP DEPTH OF 36" MIN. FOR < OR= 12" DIAM. OUTLET. FOR OUTLETS >OR= 15", DEPTH = 2.5-3X DIAM. THORNTON MAVERIK 88TH AVENUE & PECOS STREET THORNTON, COLORADO SEAL NOTES: 1. ALL HOODS AND TRAPS FOR CATCH BASINS AND WATER QUALITY STRUCTURES SHALL BE AS MANUFACTURED BY: BEST MANAGEMENT PRODUCTS, INC. 53 MT. ARCHER RD. LYME, CT (860) , (860) FAX TOLL FREE: (800) OR (888) WEB SITE: OR PRE-APPROVED EQUAL 2. ALL HOODS SHALL BE CONSTRUCTED OF A GLASS REINFORCED RESIN COMPOSITE WITH ISO GEL COAT EXTERIOR FINISH WITH A MINIMUM 0.125" LAMINATE THICKNESS. 3. ALL HOODS SHALL BE EQUIPPED WITH A WATERTIGHT ACCESS PORT, A MOUNTING FLANGE, AND AN ANTI-SIPHON VENT AS DRAWN. (SEE CONFIGURATION DETAIL) 4. THE SIZE AND POSITION OF THE HOOD SHALL BE DETERMINED BY OUTLET PIPE SIZE AS PER MANUFACTURER'S RECOMMENDATION. 5. THE BOTTOM OF THE HOOD SHALL EXTEND DOWNWARD A DISTANCE EQUAL TO 1/2 THE OUTLET PIPE DIAMETER WITH A MINIMUM DISTANCE OF 6" FOR PIPES <12" I.D. 6. THE ANTI-SIPHON VENT SHALL EXTEND ABOVE HOOD BY MINIMUM OF 3" AND A MAXIMUM OF 24" ACCORDING TO STRUCTURE CONFIGURATION. ANCHOR W/ BOLT (SEE DETAIL A) 1/2 D GASKET COMPRESSED BETWEEN HOOD AND STRUCTURE (SEE DETAIL B) FOAM GASKET W/ PSA BACKING (TRIM TO LENGTH) MOUNTING FLANGE DETAIL B INSTALLATION NOTE: POSITION HOOD SUCH THAT BOTTOM FLANGE IS A DISTANCE OF 1/2 OUTLET PIPE DIAMETER (MIN.) BELOW THE PIPE INVERT. MINIMUM DISTANCE FOR PIPES < 12" I.D. IS 6". DETAIL A DATE DATE STATUS REVISION A 6/2/2015 7:10:47 AM 7. THE SURFACE OF THE STRUCTURE WHERE THE HOOD IS MOUNTED SHALL BE FINISHED SMOOTH AND FREE OF LOOSE MATERIAL. 8. THE HOOD SHALL BE SECURELY ATTACHED TO STRUCTURE WALL WITH 3/8' STAINLESS STEEL BOLTS AND OIL-RESISTANT GASKET AS SUPPLIED BY MANUFACTURER. (SEE INSTALLATION DETAIL) 9. INSTALLATION INSTRUCTIONS SHALL BE FURNISHED WITH MANUFACTURER SUPPLIED INSTALLATION KIT. INSTALLATION KIT SHALL INCLUDE: A. INSTALLATION INSTRUCTIONS B. PVC ANTI-SIPHON VENT PIPE AND ADAPTER C. OIL-RESISTANT CRUSHED CELL FOAM GASKET WITH PSA BACKING D. 3/8" STAINLESS STEEL BOLTS E. ANCHOR SHIELDS DRILLED HOLE ANCHOR SHIELD EXPANSION CONE (NARROW END OUT) STAINLESS BOLT PROJECT NUMBER FILE DRAWN BY CHECKED BY SCALE DRAINAGE DETAILS????? R. Hansen J.Nate Reeve, P.E. As indicated

38 Reeve & Associates, Inc. 920 Chambers Street, Suite 14 Ogden, Utah Fax website: www. reeve-assoc.com

EROSION CONTROL NARRATIVE

EROSION CONTROL NARRATIVE EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment

More information

September 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report

September 6, City of Thornton 9500 Civic Center Drive Thornton, CO (303) RE: Maverik Thornton, CO - Drainage Report September 6, 2016 City of Thornton 9500 Civic Center Drive Thornton, CO 80229 (303) 538-7295 RE: Maverik Thornton, CO - Drainage Report As per your request, we are submitting to you the drainage report

More information

FINAL DRAINAGE REPORT Villages at Riverdale Carriage Homes Thornton, CO

FINAL DRAINAGE REPORT Villages at Riverdale Carriage Homes Thornton, CO FINAL DRAINAGE REPORT Villages at Riverdale Carriage Homes Thornton, CO October 14, 2016 Revised: March 30, 2017 JN: 15096 Prepared for: PCS Group, Inc. 1001 16 th Street #3 B-180 Denver, CO 80265 P: 303.561.4905

More information

EROSION CONTROL NARRATIVE

EROSION CONTROL NARRATIVE EROSION CONTROL NARRATIVE Erosion and sediment control has been designed for the Willow Bend Phase I Subdivision according to UDFCD and the City of Thornton criteria, in order to minimize erosion and sediment

More information

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO DRAINAGE REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 603 Park Point Dr. Suite 100 Golden, CO 80401 (303)-801-2900 June 29, 2015 Revised August 14, 2015 CERTIFICATE

More information

BROADSTONE VANTAGE POINT APARTMENTS NE corner of S. Parker Road, and E. Cottonwood Drive Parker, Colorado

BROADSTONE VANTAGE POINT APARTMENTS NE corner of S. Parker Road, and E. Cottonwood Drive Parker, Colorado BROADSTONE VANTAGE POINT APARTMENTS NE corner of S. Parker Road, and E. Cottonwood Drive Parker, Colorado PRELIMINARY DRAINAGE REPORT Strategic Land Solutions, Inc. JN: 16-002-15 Report Date/History: July

More information

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY

INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 2 (AP-2) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.

More information

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS

ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS ARTICLE 5 (PART 2) DETENTION VOLUME EXAMPLE PROBLEMS Example 5.7 Simple (Detention Nomograph) Example 5.8 Offsite and Unrestricted Areas (HEC-HMS) Example 5.9 Ponds in Series w/ Tailwater (HEC-HMS) Example

More information

Continuing Education Course #101 Drainage Design with WinTR-55

Continuing Education Course #101 Drainage Design with WinTR-55 1 of 5 Continuing Education Course #101 Drainage Design with WinTR-55 1. WinTR-55 uses the Kinematic Wave method for calculating storm runoff rates and volumes. 2. According to the Velocity Method, the

More information

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229 Development Engineering Land Surveying Construction Administration District Services October 20, 2017 City of Thornton Attn: Tim Semones Development Engineeering 9500 Civic Center Dr. Thornton, CO 80229

More information

Section 4: Model Development and Application

Section 4: Model Development and Application Section 4: Model Development and Application The hydrologic model for the Wissahickon Act 167 study was built using GIS layers of land use, hydrologic soil groups, terrain and orthophotography. Within

More information

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT

STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1. DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT STREUVER FIDELCO CAPPELLI, LLC YONKERS DOWNTOWN DEVELOPMENT PHASE 1 DRAFT ENVIRONMENTAL IMPACT STATEMENT For: PALISADES POINT Prepared by: PAULUS, SOKOLOWSKI & SARTOR STORMWATER MANAGEMENT 1. Methodology

More information

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3

STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 STORMWATER REPORT FRITO LAY SUBDIVISION NO. 3 May 2018 STORMWATER REPORT I. Subdivision Data a. The parcel is adjacent to the existing Frito Lay property in Topeka; and the subject plat application encompasses

More information

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT

BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT BRANDON LAKES AVENUE PRE AND POST CONDITIONS DRAINAGE REPORT Hillsborough County Public Works County Center, 22nd Floor 601 E. Kennedy Blvd. Tampa, FL 33602 BRANDON LAKES AVENUE DRAINAGE IMPROVEMENTS Capital

More information

3301 East 120 th Avenue Assited Living & Memory Care

3301 East 120 th Avenue Assited Living & Memory Care UTILITY REPORT FOR 3301 East 120 th Avenue Assited Living & Memory Care 1 st Submittal January 23, 2016 2 nd Submittal March 04, 2016 Prepared for: 3301 E. 120 th Ave, LLC. 8200 E. Maplewood Ave., Suite

More information

******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF

******************* Project Description ******************* File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF Autodesk Storm and Sanitary Analysis 2014 - Version 8.1.62 (Build 1) ----------------- *** Project Description *** File Name... NAAF Stormwater Improvement Project 11_21_2014.SPF Analysis Options Flow

More information

WATER MANAGEMENT REPORT FOR PAGE ESTATES

WATER MANAGEMENT REPORT FOR PAGE ESTATES WATER MANAGEMENT REPORT FOR PAGE ESTATES SLB Consulting of SW Florida, LLC PO Box 2826 Bonita Springs, FL. 34133 Phone: 239-948-9566 sandra@slbconsult.com C.O.A. # 25395 September 1, 2014 Sandra L. Bottcher

More information

Eastlake Assited Living & Memory Care

Eastlake Assited Living & Memory Care UTILITY REPORT FOR Eastlake Assited Living & Memory Care 1 st Submittal January 23, 2016 2 nd Submittal March 04, 2016 June 7, 2016 Final Submittal August 08, 2016 Prepared for: 3301 E. 120 th Ave, LLC.

More information

Hydrology Study Report

Hydrology Study Report Hafeez Consulting www.hafeezconsulting.com Civil/ Structural Engineering, Design & Construction 1451 S. Hacienda St. Anaheim CA 92804 (714) 225-4565 Fax (714)917-2977 engineer@hafeezconsulting.com Hydrology

More information

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY

LOCATED IN INDIAN RIVER COUNTY PREPARED FOR S.J.R.W.M.D. AND F.W.C.D. DECEMBER, 2003 Updated 2007 Updated May 2014 PREPARED BY FELLSMERE WATER CONTROL DISTRICT EAST MASTER DRAINAGE PLAN AND STORMWATER HYDROLOGIC ANALYSIS OF THE GRAVITY DRAINAGE SYSTEM LOCATED BETWEEN THE EAST BOUNDARY, LATERAL U, THE MAIN CANAL, AND DITCH 24 LOCATED

More information

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS

INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS INTRODUCTION TO HYDROLOGIC MODELING USING HEC-HMS By Thomas T. Burke, Jr., PhD, PE Luke J. Sherry, PE, CFM Christopher B. Burke Engineering, Ltd. October 8, 2014 1 SEMINAR OUTLINE Overview of hydrologic

More information

Stage Discharge Tabulation for Only Orifice Flow

Stage Discharge Tabulation for Only Orifice Flow Stage Discharge Tabulation for Only Orifice Flow DEPTH STAGE DISCHARGE (meters) (feet) (meters) (feet) (m 3 /s) (ft 3 /s) 0 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 0.7 1.3 2.0 2.6 3.3 3.9 4.6

More information

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details

Project Description. Project Options. End Analysis On... Apr 26, :00:00. Rainfall Details Project Description File Name... 323 - Att Pond 3 East PIPES ONLY.SPF Project Options Flow Units... Elevation Type... Hydrology Method... EPA SWMM Infiltration Method... Link Routing Method... Enable Overflow

More information

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610)

Stormwater Guidelines and Case Studies. CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) Stormwater Guidelines and Case Studies CAHILL ASSOCIATES Environmental Consultants West Chester, PA (610) 696-4150 www.thcahill.com Goals and Challenges for Manual State Stormwater Policy More Widespread

More information

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO

UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO UTILITY REPORT FOR THORNTON SELF STORAGE THORNTON, COLORADO Prepared by: Bowman Consulting 63 Park Point Dr. Suite 1 Golden, CO 841 (33)-81-29 June 29, 215 Revised August 14, 215 Revised September 3, 215

More information

D. B. G R A Y E N G I N E E R I N G I N C.

D. B. G R A Y E N G I N E E R I N G I N C. STORMWATER MANAGEMENT REPORT 948 Hunt lub Road Ottawa, Ontario Report No. 12020-SWM August 27, 2012 Revised April 21, 2014 Revised December 9, 2014 Revised April 14, 2015 D. B. G R A Y E N G I N E E R

More information

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water.

Pressure Head: Pressure head is the height of a column of water that would exert a unit pressure equal to the pressure of the water. Design Manual Chapter - Stormwater D - Storm Sewer Design D- Storm Sewer Sizing A. Introduction The purpose of this section is to outline the basic hydraulic principles in order to determine the storm

More information

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY

CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY CITY OF CAPE CORAL STORMWATER MASTER PLAN PHASE II - PART 1 BASINS 4, 10, & 14 SUB-BASIN DRAINAGE IMPROVEMENTS HYDRAULIC ANALYSIS SUMMARY Cape Coral, FL Prepared for: The City of Cape Coral Public Works

More information

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS

Advanced /Surface Hydrology Dr. Jagadish Torlapati Fall 2017 MODULE 2 - ROUTING METHODS Routing MODULE - ROUTING METHODS Routing is the process of find the distribution of flow rate and depth in space and time along a river or storm sewer. Routing is also called Flow routing or flood routing.

More information

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect

STORMWATER MANAGEMENT COMPUTATIONS. Mount Prospect STORMWATER MANAGEMENT COMPUTATIONS Mount Prospect MHG PROJECT No. 2011.173.11 November 6, 2014 Prepared for: Piney Meetinghouse Investments c/o Mr. Dennis Fling 14801 Clopper Road Boyds, MD 20841 (301)

More information

Final Drainage Report

Final Drainage Report Final Drainage Report Expo Rail Operations and Maintenance Facility Santa Monica, California Prepared for: Exposition Metro Line Construction Authority Prepared by: W2 Design, Inc. 50 S. De Lacey Avenue

More information

Villages at Riverdale Thornton, CO

Villages at Riverdale Thornton, CO FINAL UTILITY REPORT Villages at Riverdale Thornton, CO October 14, 216 Revised: March 29, 217 JN: 1539 Prepared for: PCS Group, Inc. 11 16 th Street #3 B-18 Denver, CO 8265 P: 33.531.495 Prepared by:

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

APPENDIX B DRAINAGE REPORT

APPENDIX B DRAINAGE REPORT APPENDIX B DRAINAGE REPORT B-1 South Lamar Blvd. Transportation Corridor Study Drainage Report Prepared for: City of Austin and HDR, Inc. Prepared by: and Services, Inc. Final 07-09-2015 Michael C. Meriwether,

More information

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By:

HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT. Prepared for: David Johnston Architect. Prepared By: HOTEL KANATA 160 HEARST WAY KANATA, ONTARIO SERVICING REPORT Prepared for: David Johnston Architect Prepared By: BaseTech Consulting Inc. 309 Roywood Crescent Newmarket, Ontario L3Y 1A6 BCI Project No.

More information

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design

The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention basin design Scholars' Mine Masters Theses Student Theses and Dissertations Spring 2010 The effectiveness of the Natural Resource Conservation Service (NRCS) and Huff rainfall distribution methods for use in detention

More information

Drainage Study for Civic Center Way

Drainage Study for Civic Center Way Drainage Study for 23401 Civic Center Way P.C.C.E. INC. CIVIL ENGINEERING AND DESIGN Drainage Study for 23401 Civic Center Way WHOLE FOODS AT THE PARK Prepared by: P.C.C.E. INC STEPHEN R. SMITH, P.E. 23801

More information

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway.

Sediment Trap. A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff through a stabilized spillway. Sediment Trap SC-15 Source: Caltrans Construction Site Best Management Practices Manual, 2003. Description A temporary runoff containment area, which promotes sedimentation prior to discharge of the runoff

More information

Chapter 7 Mudflow Analysis

Chapter 7 Mudflow Analysis Chapter 7 Mudflow Analysis 7.0 Introduction This chapter provides information on the potential and magnitude of mud floods and mudflows that may develop in Aspen due to rainfall events, snowmelt, or rain

More information

City of Columbia BMP Manual. Detailed Unified Sizing Criteria Example Wet Pond Design

City of Columbia BMP Manual. Detailed Unified Sizing Criteria Example Wet Pond Design City of Columbia BMP Manual Detailed Unified Sizing Criteria Example Wet Pond Design April 17, 2013 Wet Pond Example: Unified Sizing Criteria Methodology Base Data Location: Rome, GA Site Drainage Area

More information

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4

WQ Outlet Design Single Orifice Orifice diameter = 24. Perforated riser/orifice Plate Outlet area per perforation row = 4 These calculations should be used when designing the outlet structures for extended wet and dry detention basins (Sections 4. 7 and 4.8). The water quality outlet size and the trash rack design will vary

More information

SERVICING BRIEF & STORMWATER MANAGEMENT REPORT Colonial Road Sarsfield (Ottawa), Ontario. Report No June 15, 2017

SERVICING BRIEF & STORMWATER MANAGEMENT REPORT Colonial Road Sarsfield (Ottawa), Ontario. Report No June 15, 2017 SERVICING BRIEF & STORMWATER MANAGEMENT REPORT 2980 Colonial Road Sarsfield (Ottawa), Ontario Report No. 16033 June 15, 2017 D. B. G R A Y E N G I N E E R I N G I N C. Stormwater Management - Grading &

More information

Wellsgate Terrace SPECIFICATIONS.

Wellsgate Terrace SPECIFICATIONS. GRADING NOTES: 1. LOT GRADING SHALL BE COMPLETED TO PROVE SUFFICIENT DIRT ON EACH PAD TO ACHIEVE THE CRITICAL PAD GRADES AND SPOT GRADES ON EACH LOT. AFTER ACHIEVING CRITICAL PAD GRADES INDICATED ON THIS

More information

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

Sediment Control Practices. John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Sediment Control Practices John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources Practices Treat the Largest Soil Particles Sand Sand Silt Clay Treated Untreated Settleable

More information

Rucker Pond. Background

Rucker Pond. Background Rucker Pond Background The Rucker Basin consists of two subbasins (East and West) that drain to a single area known as Rucker Pond. Both subbasins have the same hydraulic parameters, but have different

More information

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226

Submitted to: St. Johns River Power Park New Berlin Road Jacksonville, FL 32226 RUN-ON/RUN-OFF CONTROL SYSTEM PLAN RUN-ON AND RUN-OFF CONTROL SYSTEM PLAN St. Johns River Power Park Byproduct Storage Area B Phase I Development Submitted to: St. Johns River Power Park 11201 New Berlin

More information

STORMWATER DESIGN CALCULATIONS

STORMWATER DESIGN CALCULATIONS STORMWATER DESIGN CALCULATIONS REF : C7011-2390 AT 19a-23 MEMORIAL AVENUE BLACKWALL FOR MR KERR Contents 1.0 Detention System Requirements 1.1 Storage-Area calcs. 1.2 Data Files for Pre & Post Developed

More information

WATERVIEW EAST PRELIMINARY DRAINAGE REPORT EL PASO COUNTY, COLORADO

WATERVIEW EAST PRELIMINARY DRAINAGE REPORT EL PASO COUNTY, COLORADO WATERVIEW EAST PRELIMINARY DRAINAGE REPORT EL PASO COUNTY, COLORADO PROJECT NO. 181710214 Prepared for: CPR ENTITLEMENTS 31 N. TEJON, SUITE 500 COLORADO SPRINGS, CO 80903 719.377.0244 Prepared by: STANTEC

More information

Hydrology and Hydraulics Design Report. Background Summary

Hydrology and Hydraulics Design Report. Background Summary To: National Park Services Montezuma Castle National Monument Richard Goepfrich, Facility Manager From: Multicultural Technical Engineers Date: Tuesday - February 13, 2018 Subject: 30% Hydrology and Hydraulics

More information

Stormwater Capacity Analysis for Westover Branch Watershed

Stormwater Capacity Analysis for Westover Branch Watershed Stormwater Capacity Analysis for Westover Branch Watershed Pimmit Run Little Pimmit Run, Mainstem Stohman's Run Gulf Branch Pimmit Run Tributary Little Pimmit Run, W. Branch Little Pimmit Run, E. Branch

More information

Basic Hydraulics June 2007

Basic Hydraulics  June 2007 Basic Hydraulics www.concrete-pipe.org June 2007 2007 Overview Open Channel Flow Manning Equation Basic Culvert Design Sanitary Sewer Design Flow, Velocity Stormwater Sewer Design Flow, Velocity 2 Open

More information

Appendix E Guidance for Shallow Flooding Analyses and Mapping

Appendix E Guidance for Shallow Flooding Analyses and Mapping Appendix E Guidance for Shallow Flooding Analyses and Mapping E.1 Introduction Different types of shallow flooding commonly occur throughout the United States. Types of flows that result in shallow flooding

More information

Coal Combustion Residuals Unit Inflow Design Flood Control System Plan

Coal Combustion Residuals Unit Inflow Design Flood Control System Plan Coal Combustion Residuals Unit Inflow Design Flood Control System Plan Virginia Electric and Power Company Chesterfield Power Station Upper (East) Pond Chesterfield County, Virginia GAI Project Number:

More information

Chapter 10 - Sacramento Method Examples

Chapter 10 - Sacramento Method Examples Chapter 10 Sacramento Method Examples Introduction Overview This chapter presents two example problems to demonstrate the use of the Sacramento method. These example problems use the SACPRE and HEC-1 computer

More information

The Effect of Stormwater Controls on Sediment Transport in Urban Streams

The Effect of Stormwater Controls on Sediment Transport in Urban Streams Hydrology Days 2004 The Effect of Stormwater Controls on Sediment Transport in Urban Streams Christine A. Rohrer, P.E. 1 Master s Candidate, Department of Civil Engineering, Colorado State University,

More information

CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1. ANNUAL ENGINEER S REPORT FISCAL YEAR 2015/2016 May 12, 2015

CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1. ANNUAL ENGINEER S REPORT FISCAL YEAR 2015/2016 May 12, 2015 CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1 ANNUAL ENGINEER S REPORT FISCAL YEAR 2015/2016 May 12, 2015 AGENCY: City of Perris PROJECT: Flood Control Maintenance District No. 1 TO: City Council

More information

Appendix B Equations and Examples

Appendix B Equations and Examples Equations and Examples Purpose The purpose of this appendix is to provide background equations and example problems for clarity of calculations used throughout the manual. This appendix is divided into

More information

STORMWATER MANAGEMENT REPORT

STORMWATER MANAGEMENT REPORT STORMWATER MANAGEMENT REPORT THE FAIRWAYS AT EDGEWOOD LOTS 5 & 6, BLOCK 1201 TOWNSHIP OF RIVER VALE BERGEN COUNTY, NEW JERSEY PREPARED BY: DAPHNE A. GALVIN PROFESSIONAL ENGINEER LICENSE NO. 24GE03434900

More information

Caledon Villas Corporation

Caledon Villas Corporation Caledon Villas Corporation Functional Servicing Report Caledon Villas Residential Subdivision Town of Caledon Project No. L11-557 April 2014 Caledon Villas Corporation Town of Caledon Caledon Villas Residential

More information

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE

APPENDIX G APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE APPENDIX G SEDIMENT CONTAINMENT SYSTEM DESIGN RATIONALE March 18, 2003 This page left blank intentionally. March 18, 2003 G-2 FIGURES Page # Figure G.1 Estimated Runoff from Precipitation Over Different

More information

Materials. Use materials meeting the following.

Materials. Use materials meeting the following. 208.01 Section 208. SOIL EROSION AND SEDIMENTATION CONTROL 208.01 Description. Install and maintain erosion and sedimentation controls to minimize soil erosion and to control sedimentation from affecting

More information

Rock & Aggregate Drop Inlet Protection

Rock & Aggregate Drop Inlet Protection Rock & Aggregate Drop Inlet Protection SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System Supplementary Trap Dispersive Soils

More information

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii)

HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR (c)(1)(i) (xii) HISTORY OF CONSTRUCTION FOR EXISTING CCR SURFACE IMPOUNDMENT PLANT GASTON ASH POND 40 CFR 257.73(c)(1)(i) (xii) (i) Site Name and Ownership Information: Site Name: E.C. Gaston Steam Plant Site Location:

More information

HYDROLOGY REPORT Tentative Tract No. 5978

HYDROLOGY REPORT Tentative Tract No. 5978 ATTACHMENT 5 October 2016 HYDROLOGY REPORT Tentative Tract No. 5978 City of Simi Valley County of Ventura Prepared For: Landsea Holdings Corporation 7525 Irvine Center Drive Suite 200 Irvine, CA 92618

More information

WELCOME Lake Wabukayne OPEN HOUSE

WELCOME Lake Wabukayne OPEN HOUSE WELCOME Lake Wabukayne Sediment Removal Project OPEN HOUSE We are here to: Update you, the community, on recent developments and activities at Lake Wabukayne Present the preferred alternative and receive

More information

A HYDROLOGIC STUDY OF THE EFFECTS OF URBAN DEVELOPMENT ON STORM RUNOFF: A CASE STUDY IN QUEENS, NY ABSTRACT

A HYDROLOGIC STUDY OF THE EFFECTS OF URBAN DEVELOPMENT ON STORM RUNOFF: A CASE STUDY IN QUEENS, NY ABSTRACT 154 A HYDROLOGC STUDY OF THE EFFECTS OF URBAN DEVELOPMENT ON STORM RUNOFF: A CASE STUDY N QUEENS, NY Monica Tsang-Rakovan, Kevin J. Phillips, Khalid Bajwa, John Ferrelli, Fanning, Phillips and Molnar Fanning,

More information

Drainage Analysis. Appendix F

Drainage Analysis. Appendix F Drainage Analysis Appendix F Golden View Drive Elizabeth Street LMORE CREEK Ricky Road Rabbit Creek Road LITTLE RABBIT CREEK East 156th Avenue MOA Project #10-026 Golden View Drive Intersection

More information

Stone Outlet Sediment Trap

Stone Outlet Sediment Trap 3.12 Sediment Control Description: A stone outlet sediment trap is a small detention area formed by placing a stone embankment with an integral stone filter outlet across a drainage swale for the purpose

More information

APPENDIX B WORKSHEETS & EXHIBITS

APPENDIX B WORKSHEETS & EXHIBITS APPENDIX B WORKSHEETS & EXHIBITS A worksheet provides the designer a representation of a measure that allows for input of specific design criteria. The plan designer will be required to assess field conditions

More information

Standards for Soil Erosion and Sediment Control in New Jersey May 2012

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SEDIMENT BASIN Definition A barrier, dam, excavated pit, or dugout constructed across a waterway or at other suitable locations to intercept and retain sediment. Basins created by construction

More information

Analysis of Hydraulic Impacts on the Schuylkill River

Analysis of Hydraulic Impacts on the Schuylkill River Analysis of Hydraulic Impacts on the Schuylkill River Manayunk Sewer Basin Construction Project and the Venice Island Recreation Center Reconstruction Project Venice Island, Manayunk, Philadelphia, PA

More information

Coarse Sediment Traps

Coarse Sediment Traps Coarse Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils [2] Type 3 System Supplementary Trap Dispersive Soils [1] Though primarily

More information

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK

PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK PRELIMINARY CULVERT ANALYSIS REPORT FOR CULVERT NO. 008-C OREGON AVENUE OVER PINEHURST CREEK Prepared for The District of Columbia Department of Transportation Washington, D.C. Prepared by Parsons Transportation

More information

CCR Rule Annual Inspection Report (cont.) 2

CCR Rule Annual Inspection Report (cont.) 2 The inspection findings consisted of maintenance items and items that were not observed to be signs or potential signs of significant structural weakness. No deficiencies or disrupting conditions that

More information

Monitoring Considerations and Costs

Monitoring Considerations and Costs Monitoring Considerations and Costs Stormwater BMP Selection, Design, and Monitoring Florida Stormwater Association September 9, 2016 Harvey H. Harper, Ph.D., P.E. Environmental Research & Design, Inc.

More information

U-Shaped Sediment Traps

U-Shaped Sediment Traps U-Shaped Sediment Traps SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System Concentrated Flow Clayey Soils [1] Type 3 System Supplementary Trap Dispersive Soils [1] Generally

More information

Wal-mart Store # Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT. February 2017

Wal-mart Store # Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT. February 2017 Wal-mart Store #6746-00 Ft. Walton Beach, FL NE Corner of Eglin Parkway/S.R. 85 and South Street STORMWATER REPORT February 2017 CPH Project No. W13900 1031-C W. 23rd Street Panama City, FL 32405 Phone

More information

PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks

PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks PONDNET.WK1 - Flow and Phosphorus Routing in Pond Networks Version 2.1 - March 1989 William W. Walker, Jr. Ph.D., Environmental Engineer 1127 Lowell Road, Concord, Massachusetts 01742 508-369-8061 PONDNET.WK1

More information

FINAL UTILITY REPORT Creekside Thornton, CO

FINAL UTILITY REPORT Creekside Thornton, CO FINAL UTILITY REPORT Creekside Thornton, CO March 4, 216 Revised: June 27, 216 JN: 1539 Prepared for: HW Sodbusters, LLC 2733 E. Parleys Way, Suite 3 Salt Lake City, UT 8419 P: 81.485.777 Prepared by:

More information

CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1. ANNUAL ENGINEER S REPORT FISCAL YEAR 2011/2012 April 26, 2011

CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1. ANNUAL ENGINEER S REPORT FISCAL YEAR 2011/2012 April 26, 2011 CITY OF PERRIS FLOOD CONTROL MAINTENANCE DISTRICT NO. 1 ANNUAL ENGINEER S REPORT FISCAL YEAR 2011/2012 April 26, 2011 AGENCY: City of Perris PROJECT: Flood Control Maintenance District No. 1 TO: City Council

More information

Woodford County Erosion Prevention Plan and Permit. Application #

Woodford County Erosion Prevention Plan and Permit. Application # Woodford County Erosion Prevention Plan and Permit Application # Date Instructions: Applicant will complete Parts A and B, and attach a proposed site diagram. This diagram must be completed in accordance

More information

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins

Attachment B to Technical Memorandum No.2. Operations Plan of Ross Valley Detention Basins Attachment B to Technical Memorandum No.2 Operations Plan of Ross Valley Detention Basins Operations Plan of Ross Valley Detention Basins Stetson Engineers Inc. January 26, 2011 1.0 Introduction Achieving

More information

SPRINGVILLE CITY, UTAH PRESSURE IRRIGATION SYSTEM DRAFT. MASTER PLAN & CAPITAL FACILITIES PLAN For the WEST FIELDS. February 11, 2014.

SPRINGVILLE CITY, UTAH PRESSURE IRRIGATION SYSTEM DRAFT. MASTER PLAN & CAPITAL FACILITIES PLAN For the WEST FIELDS. February 11, 2014. SPRINGVILLE CITY, UTAH PRESSURE IRRIGATION SYSTEM MASTER PLAN & CAPITAL FACILITIES PLAN For the WEST FIELDS February 11, 2014 Prepared by: J-U-B ENGINEERS, INC. 240 West Center Street, Suite 200 Orem,

More information

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION

APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION APPENDIX B DESIGN CRITERIA FOR TEMPORARY WATER QUALITY BMPS USED DURING CONSTRUCTION This Appendix presents design criteria and example calculations for the following temporary water quality BMPs for use

More information

SPRINGVILLE CITY, UTAH

SPRINGVILLE CITY, UTAH SPRINGVILLE CITY, UTAH PRESSURE IRRIGATION SYSTEM MASTER PLAN & CAPITAL FACILITIES PLAN For the WEST FIELDS February 11, 2014 Adopted May 20, 2014 Prepared by: J-U-B ENGINEERS, INC. 240 West Center Street,

More information

TPDES: Soil, Erosion and Sedimentation Methods

TPDES: Soil, Erosion and Sedimentation Methods SAWS TPDES: Soil, Erosion and Sedimentation Methods Philip Handley Supervisor-Resource Protection & Compliance August 25, 2014 TPDES: Soil, Erosion and Sedimentation Methods Soil Common term: Dirt Common

More information

DRAINAGE REPORT. Ministry of Transportation and Infrastructure. Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design

DRAINAGE REPORT. Ministry of Transportation and Infrastructure. Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design DRAINAGE REPORT Ministry of Transportation and Infrastructure Highway 7 Four Laning Silverdale Avenue to Nelson Street 100% Detailed Design December 14, 2017 Reviewed by: Amanda Rust, P. Eng. Senior Drainage

More information

Preliminary Hydraulic Report

Preliminary Hydraulic Report Tarrant County, Texas Preliminary Hydraulic Report Prepared for: Texas Department of Transportation Fort Worth District Prepared by: AECOM Corporation Scott C. Williams, P.E. No. 101334, Date 2009 This

More information

Climate Adaptation Challenges for Boston s Water and Sewer Systems

Climate Adaptation Challenges for Boston s Water and Sewer Systems National Association of Flood & Stormwater Management Agencies Climate Adaptation Challenges for Boston s Water and Sewer Systems John P Sullivan P.E. October 15,2014 Boston 1630 Boston 1630-2012 Boston

More information

D.M. Wills Associates Limited PARTNERS IN ENGINEERING. Stormwater Management Report. City of Peterborough

D.M. Wills Associates Limited PARTNERS IN ENGINEERING. Stormwater Management Report. City of Peterborough Stormwater Management Report City of Peterborough P-20-12 Parkway Corridor Class Environmental Assessment Jackson Park Parkhill Road West to Chemong Road D.M. Wills Project No. 12-5061 D.M. Wills Associates

More information

PRELIMINARY ENGINEERING REPORT FOR SANITARY SEWER COLLECTION SYSTEM OSKALOOSA, IOWA 2017

PRELIMINARY ENGINEERING REPORT FOR SANITARY SEWER COLLECTION SYSTEM OSKALOOSA, IOWA 2017 PRELIMINARY ENGINEERING REPORT FOR SANITARY SEWER COLLECTION SYSTEM OSKALOOSA, IOWA 2017 PRELIMINARY ENGINEERING REPORT FOR SANITARY SEWER COLLECTION SYSTEM OSKALOOSA, IOWA 2017 I hereby certify that this

More information

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP

FOR PROJECTS INITIATED AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP AFTER NOVEMBER 1, 2008 ITEM 716 EMBANKMENT EARTH OUTLET SEDIMENT TRAP 716.1 Description. This work shall consist of furnishing, installing, maintaining, and removing temporary erosion protection and sediment

More information

Section 3.0 Existing Systems Hydrology and Hydraulics

Section 3.0 Existing Systems Hydrology and Hydraulics Section 3.0 Existing Systems Hydrology and Hydraulics This chapter summarizes the results and methodology of MACTEC s evaluation of the existing drainage systems and lakes for the City of Maitland, Florida.

More information

Culvert and Pipe Phasing

Culvert and Pipe Phasing Culvert and Pipe Phasing Barney Blackburn, PE, CPESC, CPSWQ NCDOT Roadside Environmental Unit Soil & Water Engineering Section Supervisor NCDOT Culvert Phasing Process Hydraulics Unit: Culvert Survey Report

More information

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area.

[1] Performance of the sediment trap depends on the type of outlet structure and the settling pond surface area. Sediment Trench SEDIMENT CONTROL TECHNIQUE Type 1 System Sheet Flow Sandy Soils Type 2 System [1] Concentrated Flow Clayey Soils Type 3 System [1] Supplementary Trap Dispersive Soils [1] Performance of

More information

FINAL STREAM. Prepared For: Discharge. Draft Stream. Level Hay Street, Subiaco WA Indiana Street. Golden, CO USA

FINAL STREAM. Prepared For: Discharge. Draft Stream. Level Hay Street, Subiaco WA Indiana Street. Golden, CO USA Draft Stream Discharge and Water Supply Estimates S F FINAL STREAM DISCHARGE AND WATER SUPPLYS ESTIMATES CITRONEN FJORD F DEVELOPMENT PROJECT Prepared For: Ironbark Zinc Limited Level 1 350 Hay Street,

More information

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards.

design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. design, construction, operation, and maintenance of the BAP is consistent with recognized and generally accepted good engineering standards. In addition to the field inspection, Associated Engineers, Inc.

More information

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0

PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 PENNSYLVANIA DEPARTMENT OF TRANSPORTATION ENGINEERING DISTRICT 3-0 LYCOMING COUNTY S.R.15, SECTION C41 FINAL HYDROLOGIC AND HYDRAULIC REPORT STEAM VALLEY RUN STREAM RELOCATION DATE: June, 2006 REVISED:

More information

Table of Contents Project Description... 1 Summary of Existing Conditions... 1 Summary of Proposed Conditions... 1 Stormwater Compliance... 2 Collecti

Table of Contents Project Description... 1 Summary of Existing Conditions... 1 Summary of Proposed Conditions... 1 Stormwater Compliance... 2 Collecti Table of Contents Project Description... 1 Summary of Existing Conditions... 1 Summary of Proposed Conditions... 1 Stormwater Compliance... 2 Collection... 2 Treatment... 3 Storage... 3 Disposal... 4 Soils...

More information

Chapter 5 CALIBRATION AND VERIFICATION

Chapter 5 CALIBRATION AND VERIFICATION Chapter 5 CALIBRATION AND VERIFICATION This chapter contains the calibration procedure and data used for the LSC existing conditions model. The goal of the calibration effort was to develop a hydraulic

More information